PG&E Advice Letter 7919-E: transmission upgrades for GIC San Jose LLC (Tier 3, resolution required)
Where it stands: Pending before the commission as of May 26, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
PG&E's Tier 3 Advice Letter 7919-E (May 26, 2026) asks for approval of transmission upgrades for GIC San Jose LLC, which requested transmission-level electric service for a data center at 350 W Trimble Rd, San Jose with a maximum forecasted demand of 97.3 MW. The Q5 WG2 sweep put the estimated transmission upgrade cost at $58,280,000 including ITCC, plus $10,726,000 of special facilities (a new 115 kV switching station and a redundant 115 kV line), with facilities expected operational in the third quarter of 2028. No resolution disposing of the advice letter had been located as of the Q5 sweep, so the matter is rowed as pending.
The facts
- Regulator
- California Public Utilities Commission
- Docket number
- Advice Letter 7919-E
- Type
- Other
- Utility
- Pacific Gas & Electric Co.
- State
- California
- Filed
- May 26, 2026
- Status date
- May 26, 2026
- Large-load rules
- Yes, for loads of 97.3 MW or more
Projects served by Pacific Gas & Electric Co.
Related cases and proceedings
- Utility commission · DecidedApplication of Southern California Edison Company (U338E) to Establish Marginal Costs, Allocate Revenues, and Design Rates (2024 General Rate Case Phase 2)
- Utility commission · DecidedElectric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.
- Utility commission · DecidedElectric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities
- Utility commission · DecidedExceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California
- Utility commission · Pending before the commissionApplication of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service
- Court case · PendingImperial Valley Computer Manufacturing, LLC v. City of Imperial, et al.
- Utility commission · DecidedElectric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure
- Utility commission · Pending before the commissionOrder Instituting Rulemaking to Establish Energization Timelines
In the record
- Utility case, May 26, 2026. Utility case filed: PG&E Advice Letter 7919-E: transmission upgrades for GIC San Jose LLC (Tier 3, resolution required) California Public Utilities Commission, Advice Letter 7919-E
Sources
- 1Advice 7919-E: Electric Rules 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Upgrades for GIC San Jose LLC
Pacific Gas and Electric Company (CPUC advice letter)Tier 2 · Advice Letter 7919-E (PG&E, dated May 26, 2026): GIC San Jose LLC requested transmission-level electric service for a data center at 350 W Trimble Rd., San Jose, with a maximum forecasted demand of 97.3 MW. Cost and schedule figures are per the Q5 WG2 notes on the same advice letter. · Open the source
Report an error or send a tip on this page