Application of Southern California Edison Company (U338E) to Establish Marginal Costs, Allocate Revenues, and Design Rates (2024 General Rate Case Phase 2)

Where it stands: Decided as of Apr 30, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

SCE's 2024 general rate case Phase 2 set marginal costs, revenue allocation, and rate design, including the Large Power Rate Group Rate Design Settlement Agreement, one of nine settlements the decision approves. The decision is the rate design backdrop for SCE's largest customers, including data centers taking service on Schedule TOU-8 (demand above 500 kW). Implementing changes run through Advice Letter 5897-E (and supplement 5897-E-A) from October 1, 2026: Critical Peak Pricing becomes opt-in rather than the default, and a new Option DD for storage customers starts. The proposed decision (mailed March 20, 2026) states the decision closes the proceeding; the final decision is D.26-04-033.

The facts

Regulator
California Public Utilities Commission
Docket number
A.24-03-019
Type
Rate case
Utility
Southern California Edison Co
State
California
Filed
Mar 29, 2024
Status date
Apr 30, 2026
Large-load rules
Yes

Related cases and proceedings

In the record

  1. Utility case, Mar 29, 2024. Utility case filed: Application of Southern California Edison Company (U338E) to Establish Marginal Costs, Allocate Revenues, and Design Rates (2024 General Rate Case Phase 2) California Public Utilities Commission, A.24-03-019

Sources

  1. 1
    Proposed Decision in A.24-03-019 (SCE General Rate Case Phase 2: marginal costs, revenue allocation, and rate design)
    California Public Utilities Commission
    Tier 1 · Proposed Decision of ALJ Poirier, mailed March 20, 2026 (Agenda ID 24101): summary approving nine settlement agreements including the Large Power Rate Group Rate Design Settlement Agreement; section 3.1.7 (Large Power Group Rate Design Settlement Agreement); the proceeding is closed. Adoption of the final decision (D.26-04-033) on April 30, 2026 and the October 1, 2026 Advice Letter 5897-E implementation are per secondary reporting and the Q5 WG2 notes; the final decision document itself was not opened in this pass. · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Southern California Edison Company (U338E) to Establish Marginal Costs, Allocate Revenues, and Design Rates (2024 General Rate Case Phase 2)." Last activity 2026-04-30. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-sce-grc-phase2-2024