Utility commission
Electric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.
Where it stands: Decided as of Mar 19, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Resolution E-5447 (March 19, 2026) approved Advice Letter 7653-E without modification: a non-standard engineering, procurement, and construction agreement under which STACK Infrastructure builds the Ringwood Switching Station approved in Resolution E-5420 and transfers it to PG&E. STACK bears the EPC cost and PG&E's supervision costs. The resolution changes no cost recovery and no refunds; the cost responsibility and refund framework for the 90 MW STACK project sit in Resolution E-5420.
The facts
- Regulator
- California Public Utilities Commission
- Docket number
- Resolution E-5447 (Advice Letter 7653-E)
- Type
- Other
- Utility
- Pacific Gas & Electric Co.
- State
- California
- Filed
- Jul 29, 2025
- Status date
- Mar 19, 2026
- Large-load rules
- Yes, for loads of 90 MW or more
Projects served by Pacific Gas & Electric Co.
Related cases and proceedings
- Utility commission · Pending before the commissionPG&E Advice Letter 7919-E: transmission upgrades for GIC San Jose LLC (Tier 3, resolution required)
- Utility commission · DecidedApplication of Southern California Edison Company (U338E) to Establish Marginal Costs, Allocate Revenues, and Design Rates (2024 General Rate Case Phase 2)
- Utility commission · DecidedElectric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities
- Utility commission · DecidedExceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California
- Utility commission · Pending before the commissionApplication of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service
- Court case · PendingImperial Valley Computer Manufacturing, LLC v. City of Imperial, et al.
- Utility commission · DecidedElectric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure
- Utility commission · Pending before the commissionOrder Instituting Rulemaking to Establish Energization Timelines
In the record
- Utility case, Jul 29, 2025. Utility case filed: Electric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc. California Public Utilities Commission, Resolution E-5447 (Advice Letter 7653-E)
Sources
- 1Resolution E-5447: PG&E Advice Letter 7653-E non-standard EPC agreement for the Ringwood Switching Station (STACK)
California Public Utilities CommissionTier 1 · Resolution E-5447 text (Agenda ID 24035, dated March 19, 2026): caption (Advice Letter 7653-E, filed July 29, 2025); proposed outcome (approves Advice Letter 7653-E and the EPC Agreement with STACK Infrastructure); body (no change to the cost recovery or refund framework addressed in E-5420). · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Electric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.." Last activity 2026-03-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pge-e5447-stack-epc