Electric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.

Where it stands: Decided as of Mar 19, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Resolution E-5447 (March 19, 2026) approved Advice Letter 7653-E without modification: a non-standard engineering, procurement, and construction agreement under which STACK Infrastructure builds the Ringwood Switching Station approved in Resolution E-5420 and transfers it to PG&E. STACK bears the EPC cost and PG&E's supervision costs. The resolution changes no cost recovery and no refunds; the cost responsibility and refund framework for the 90 MW STACK project sit in Resolution E-5420.

The facts

Regulator
California Public Utilities Commission
Docket number
Resolution E-5447 (Advice Letter 7653-E)
Type
Other
Utility
Pacific Gas & Electric Co.
State
California
Filed
Jul 29, 2025
Status date
Mar 19, 2026
Large-load rules
Yes, for loads of 90 MW or more

Projects served by Pacific Gas & Electric Co.

Related cases and proceedings

In the record

  1. Utility case, Jul 29, 2025. Utility case filed: Electric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc. California Public Utilities Commission, Resolution E-5447 (Advice Letter 7653-E)

Sources

  1. 1
    Resolution E-5447: PG&E Advice Letter 7653-E non-standard EPC agreement for the Ringwood Switching Station (STACK)
    California Public Utilities Commission
    Tier 1 · Resolution E-5447 text (Agenda ID 24035, dated March 19, 2026): caption (Advice Letter 7653-E, filed July 29, 2025); proposed outcome (approves Advice Letter 7653-E and the EPC Agreement with STACK Infrastructure); body (no change to the cost recovery or refund framework addressed in E-5420). · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Electric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.." Last activity 2026-03-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pge-e5447-stack-epc