Utility commission
Electric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities
Where it stands: Decided as of Mar 19, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Resolution E-5433 (adopted March 19, 2026, issued March 20, 2026) approved with modification an agreement to energize a new 49 MW data center and computing lab for Sunnyvale Technology Partners LLC (c/o Menlo Equities) at 888 Ross Dr, Sunnyvale, with a 115 kV line extension and substation upgrades; operation date June 2027. Annual refunds are capped at 75 percent of the customer's actual annual net revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution is non-precedential for the Rule 30 proceeding.
The facts
- Regulator
- California Public Utilities Commission
- Docket number
- Resolution E-5433 (Advice Letter 7667-E)
- Type
- Other
- Utility
- Pacific Gas & Electric Co.
- State
- California
- Filed
- Aug 4, 2025
- Status date
- Mar 19, 2026
- Large-load rules
- Yes, for loads of 49 MW or more
Projects served by Pacific Gas & Electric Co.
Related cases and proceedings
- Utility commission · Pending before the commissionPG&E Advice Letter 7919-E: transmission upgrades for GIC San Jose LLC (Tier 3, resolution required)
- Utility commission · DecidedApplication of Southern California Edison Company (U338E) to Establish Marginal Costs, Allocate Revenues, and Design Rates (2024 General Rate Case Phase 2)
- Utility commission · DecidedElectric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.
- Utility commission · DecidedExceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California
- Utility commission · Pending before the commissionApplication of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service
- Court case · PendingImperial Valley Computer Manufacturing, LLC v. City of Imperial, et al.
- Utility commission · DecidedElectric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure
- Utility commission · Pending before the commissionOrder Instituting Rulemaking to Establish Energization Timelines
In the record
- Utility case, Aug 4, 2025. Utility case filed: Electric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities California Public Utilities Commission, Resolution E-5433 (Advice Letter 7667-E)
Sources
- 1Resolution E-5433: PG&E Advice Letter 7667-E exceptional case, Sunnyvale Technology Partners LLC, Sunnyvale
California Public Utilities CommissionTier 1 · Resolution E-5433 text: caption (Advice Letter 7667-E, filed August 4, 2025); date of issuance March 20, 2026; proposed outcome (approves with modification an agreement for a new 49 MW data center and computing lab; refunds limited to 75 percent of net revenues; refund period extended to fifteen years). · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Electric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities." Last activity 2026-03-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pge-e5433-sunnyvale