Project File · Public records
Every public record we have for Microsoft San Jose data center (Alviso)
San Jose, Santa Clara County, CaliforniaUnder constructionFirst public 2017Filing entity: Microsoft CorporationLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
15 of 15 records
2026
Air permitIssuedAug 18, 2026Bay Area Air Quality Management District
Bay Area Air Quality Management District, Air District Application 704043; 84 generators (document numbering: Sources S-7 through S-90)
Authority to Construct issued for the remaining 84 natural gas backup engine generators (SJC03), each abated by a 3-way catalyst system
- Permitted generators:
- 84 generators (remaining SJC03 fleet)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Notice of Determination, SCH 2021020002 (CEQAnet record 2021020002/9)
Utility proceedingPending before the commissionMay 26, 2026California Public Utilities Commission
PG&E Advice Letter 7919-E: transmission upgrades for GIC San Jose LLC (Tier 3, resolution required)
PG&E's Tier 3 Advice Letter 7919-E (May 26, 2026) asks for approval of transmission upgrades for GIC San Jose LLC, which requested transmission-level electric service for a data center at 350 W Trimble Rd, San Jose with a maximum forecasted demand of 97.3 MW. The Q5 WG2 sweep put the estimated transmission upgrade cost at $58,280,000 including ITCC, plus $10,726,000 of special facilities (a new 115 kV switching station and a redundant 115 kV line), with facilities expected operational in the third quarter of 2028. No resolution disposing of the advice letter had been located as of the Q5 sweep, so the matter is rowed as pending.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Advice Letter 7919-E (PG&E, dated May 26, 2026): GIC San Jose LLC requested transmission-level electric service for a data center at 350 W Trimble Rd., San Jose, with a maximum forecasted demand of 97.3 MW. Cost and schedule figures are per the Q5 WG2 notes on the same advice letter.
2025
Public decisionApprovedNov 18, 2025City of San Jose City Council
City of San Jose City Council, Resolution RES2025-394; Council File 25-1211
Master Easements Agreement and Site Works Agreement with Microsoft Corporation and Valley Water for the San Jose-Santa Clara Regional Wastewater Facility adopted (10-0-1; Vice Mayor Foley recused)
- Agreement consideration minimum:
- $9.3 million no less than
- Stated in the filing:
- early fall 2028 data center completion target (council memorandum timeline)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
City Council Minutes, November 18, 2025, item 8.1
Recorded voteNov 18, 2025San Jose City Council
RES2025-394: Master Easements Agreement and Site Works Agreement with Microsoft Corporation and Valley Water (City Council, November 18, 2025)
10 yes, 1 recused. Anthony Tordillos (Councilmember): yes; Bien Doan (Councilmember): yes; David Cohen (Councilmember): yes; Domingo Candelas (Councilmember): yes; George Casey (Councilmember): yes; Matt Mahan (Mayor): yes; Michael Mulcahy (Councilmember): yes; Pamela Campos (Councilmember): yes; Pam Foley (Vice Mayor): recused, financial interest (as stated in the council record); Peter Ortiz (Councilmember): yes; Rosemary Kamei (Councilmember): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
City Council Minutes, November 18, 2025, item 8.1 (motion by Cohen, seconded by Candelas; 10-0-1; Recused: Foley)
Utility proceedingDecidedAug 4, 2025California Public Utilities Commission
Electric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities
Resolution E-5433 (adopted March 19, 2026, issued March 20, 2026) approved with modification an agreement to energize a new 49 MW data center and computing lab for Sunnyvale Technology Partners LLC (c/o Menlo Equities) at 888 Ross Dr, Sunnyvale, with a 115 kV line extension and substation upgrades; operation date June 2027. Annual refunds are capped at 75 percent of the customer's actual annual net revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution is non-precedential for the Rule 30 proceeding.
Resolution E-5433 (Advice Letter 7667-E)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution E-5433 text: caption (Advice Letter 7667-E, filed August 4, 2025); date of issuance March 20, 2026; proposed outcome (approves with modification an agreement for a new 49 MW data center and computing lab; refunds limited to 75 percent of net revenues; refund period extended to fifteen years).
Utility proceedingDecidedJul 29, 2025California Public Utilities Commission
Electric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.
Resolution E-5447 (March 19, 2026) approved Advice Letter 7653-E without modification: a non-standard engineering, procurement, and construction agreement under which STACK Infrastructure builds the Ringwood Switching Station approved in Resolution E-5420 and transfers it to PG&E. STACK bears the EPC cost and PG&E's supervision costs. The resolution changes no cost recovery and no refunds; the cost responsibility and refund framework for the 90 MW STACK project sit in Resolution E-5420.
Resolution E-5447 (Advice Letter 7653-E)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution E-5447 text (Agenda ID 24035, dated March 19, 2026): caption (Advice Letter 7653-E, filed July 29, 2025); proposed outcome (approves Advice Letter 7653-E and the EPC Agreement with STACK Infrastructure); body (no change to the cost recovery or refund framework addressed in E-5420).
Utility proceedingDecidedJul 1, 2025California Public Utilities Commission
Exceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California
Resolution E-5439 (January 15, 2026) approved with modification four agreements to energize a new 90 MW data center for Microsoft Corporation (project SJC02) at 1657 Alviso-Milpitas Rd, San Jose, with 115 kV upgrades at Los Esteros Substation and a new 115 kV line to Microsoft's substation. Microsoft pays all up-front costs and construction is on an actual-cost basis; operation date January 2027. As in the other exceptional cases, annual refunds are capped at 75 percent of the customer's actual annual net transmission revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution is non-precedential for the Rule 30 proceeding.
Resolution E-5439 (Advice Letter 7635-E)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution E-5439 text (Agenda ID 23925, Rev. 1, dated January 15, 2026): caption (Advice Letter 7635-E, filed July 1, 2025); proposed outcome (approves with modification four agreements for a new 90 MW data center; refunds limited to 75 percent of net revenues; refund period to fifteen years).
Utility proceedingDecidedApr 18, 2025California Public Utilities Commission
Electric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure
Resolution E-5420 (adopted October 30, 2025, issued November 7, 2025) approved with modification two agreements to energize a new 90 MW data center for STACK Infrastructure (SI SVY01PG&E, LLC) at 2400 Ringwood Ave, San Jose, including a new 115 kV Ringwood substation; estimated facilities cost $85.9 million including the income tax component of contribution (ITCC). Departing from the standard refund rule, annual refunds are capped at 75 percent of the customer's actual annual net transmission revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution states it is non-precedential for the Rule 30 proceeding (A.24-11-007).
Resolution E-5420 (Advice Letter 7569-E)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution E-5420 text: caption (Advice Letter 7569-E, filed April 18, 2025); proposed outcome (approves with modification two agreements for a new 90 MW data center; refunds limited to 75 percent of net revenues); body (ITCC component; refund period extended to 15 years).
Public decisionApprovedApr 9, 2025City of San Jose Planning Commission
City of San Jose Planning Commission, CP23-016; V24-001; ER20-219
Conditional use permit and parking development exception approved (9-0) for two single-story data center buildings (about 397,205 sq ft), a substation, pump stations, and 224 standby backup generators on 64.59 gross acres; resolutions certifying the CEC Final EIR as responsible agency adopted
- Approved building area:
- 397,205 square feet (approximate, per Planning Commission minutes)
- Trees removed:
- 79 trees
- Site area:
- 64.59 gross acres
- Substation area:
- 98,600 square feet (approximate)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Planning Commission Action Minutes, April 9, 2025, item 5a
Recorded voteApr 9, 2025San Jose Planning Commission
CP23-016 / V24-001: conditional use permit, development exception, and EIR certification for the Microsoft Alviso data center (Planning Commission, April 9, 2025)
9 yes. Anthony Tordillos (Chair): yes; Carlos Rosario (Commissioner): yes; Charles Cantrell (Vice Chair): yes; Dilpreet Bhandal (Commissioner): yes; Justin Lardinois (Commissioner): yes; Louis Barocio (Commissioner): yes; Melissa Bickford (Commissioner): yes; Michael Young (Commissioner): yes; Pierluigi Oliverio (Commissioner): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Planning Commission Action Minutes, April 9, 2025, item 5a (motion by Oliverio, seconded by Cantrell, passed 9-0)
Air permitIssuedApr 3, 2025Bay Area Air Quality Management District
Bay Area Air Quality Management District, Air District Application #31953; Sources S-1 through S-140
Authority to Construct issued under Regulation 2-1-301 for the first 140 natural gas backup generators (SJC02)
- Permitted generators:
- 140 generators (Sources S-1 through S-140)
- Base interruptible program hours cap:
- 459 hours per year per generator
- Reliability testing hours cap:
- 50 hours per year per generator
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Notice of Determination, SCH 2021020002 (CEQAnet record 2021020002/5)
2024
Utility proceedingPending before the commissionNov 21, 2024California Public Utilities Commission
Application of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service
PG&E applied on November 21, 2024 for Electric Rule 30, a tariff for new retail customers taking service at transmission voltage (roughly 50 to 230 kV), a class that previously had no tariff and was served deal by deal through exceptional case resolutions. Decision D.25-07-039 (issued July 28, 2025) partially granted interim implementation: transmission-level customers may take service now if they pay in advance or pay actual costs, and they may voluntarily prefund up to 100 percent of specific transmission network upgrades; new transmission-level customers bear the initial cost of all transmission facilities built for them. Refunds, interest, and repayment of prefunding loans are deferred to the final decision, and repayment is not guaranteed. PG&E's compliance Advice Letter 7671-E was rejected in October 2025 because its prefunding loan did not require the customer to prefund 100 percent of all transmission network upgrades as the decision requires. As filed (not adopted), PG&E proposed a minimum demand charge of 75 percent of contracted peak demand and a 15-year minimum contract term. An ALJ ruling of January 9, 2026 re-established the proceeding schedule on cost allocation; the application remains pending.
A.24-11-007
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
ALJ Ruling Establishing Proceeding Schedule, filed January 9, 2026: procedural background (application filed November 21, 2024) and summary of D.25-07-039 (interim implementation terms; refunds, interest and loan repayment deferred to the final decision). The Advice Letter 7671-E rejection and the as-filed 75 percent minimum demand charge and 15-year term are per the Q5 WG2 notes (Commission disposition letter of November 19, 2025 and party testimony), not from the ruling itself.
2022
Public decisionApprovedJul 14, 2022California Energy Commission
California Energy Commission, Order No. 22-0713-6; Docket 19-SPPE-04; TN 244835/244836
Commission Final Decision in the SPPE proceeding: the backup generating facility qualifies for the small power plant exemption (generating capacity will not exceed 100 MW)
- Backup generator fleet capacity:
- 99 MW (Commission finding)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Commission Final Decision, adopted July 13, 2022, dated July 14, 2022
Public decisionIssuedFeb 2022California Energy Commission
California Energy Commission, Docket 19-SPPE-04; CEC-700-2021-003-F; TN 241977
Final Environmental Impact Report for the San Jose City Backup Generating Facility (SJ2) small power plant exemption application
- Building area:
- 244,676 gross square feet (SJC02)
- Generator unit output:
- 0.45 MW standby output per natural gas generator
- Emergency generators:
- 224 natural gas backup generators
- Total building area:
- 396,914 gross square feet
- Maximum electrical load:
- 99 MW
- Construction workforce peak:
- 215 workers per month (maximum, applicant projection)
- Construction workforce average:
- 108 workers per month (average, applicant projection)
- Water demand potable:
- less than 1 acre-feet per year
- Operations employment projected:
- 100 employees (applicant projection)
- Building area:
- 152,238 gross square feet (SJC03)
- Stated in the filing:
- 2 Tier 4 diesel admin generators (1.25 MW at SJC02, 0.5 MW at SJC03)
- Building count:
- 2 single-story data center buildings (SJC02 and SJC03)
- Water demand total:
- 423 acre-feet per year
- It load:
- 77 MW (8 colos at 9.6 MW)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Final EIR, ch. 3 (project description), docket 19-SPPE-04
No date in the record(rules in force and undated records)
LawsuitDecidedNo date in the recordCalifornia Court of Appeal, Sixth Appellate District
Organizacion Comunidad de Alviso v. City of San Jose (Microsoft Corporation et al., real parties in interest)
Alviso residents sued the City of San Jose over its October 2017 approval of the data center project on this site. The trial court dismissed the suit as filed too late, and the Court of Appeal agreed on February 9, 2021: the group had relied on the city's first notice of determination, which named the wrong applicant, and its amended petition naming Microsoft came after CEQA's 30-day deadline ran from the corrected notice. The court noted the city had failed to mail the corrected notice as CEQA requires, but affirmed the dismissal anyway. Published at 60 Cal.App.5th 783, 275 Cal.Rptr.3d 99.
H046458
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Slip opinion, Appeal No. H046458 (Super. Ct. No. CV321687), filed February 9, 2021
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Notice of Determination: Issuance of an Authority to Construct for Emergency Backup Natural Gas Generators Sources S-1 through S-140 (Air District Application #31953)
Bay Area Air Quality Management District (via CEQAnet, SCH 2021020002)Tier 1 · Captured 2026-11-09 · Open the source - 2Council Memorandum, File 25-1211: Master Easements Agreement and Site Works Agreement with Microsoft Corporation and Valley Water (October 27, 2025)
City of San JoseTier 1 · Captured 2026-11-09 · Open the source - 3City Council Meeting Minutes, Tuesday, November 18, 2025
City of San Jose (City Clerk, via Legistar)Tier 1 · Captured 2026-11-09 · Open the source - 4Notice of Determination: Issuance of Authority to Construct for Eighty-Four Emergency Backup Natural Gas Engine Generators, Sources S-7 through S-90 (Air District Application 704043)
Bay Area Air Quality Management District (via CEQAnet, SCH 2021020002)Tier 1 · Captured 2026-11-09 · Open the source - 5Final Environmental Impact Report, San Jose Data Center / SJ2 (CEC-700-2021-003-F), Docket 19-SPPE-04
California Energy CommissionTier 1 · Captured 2026-11-09 · Open the source - 6San Jose Planning Commission Action Minutes, April 9, 2025 (Microsoft CP23-016 conditional use permit, 1657 Alviso-Milpitas Rd)
City of San JoseTier 1 · Captured 2026-11-08 · Open the source - 7Commission Final Decision, Order No. 22-0713-6, Docket 19-SPPE-04 (San Jose City Backup Generating Facility)
California Energy CommissionTier 1 · Captured 2026-11-09 · Open the source - 8Organizacion Comunidad de Alviso v. City of San Jose, 60 Cal.App.5th 783 (2021), Appeal No. H046458
California Court of Appeal, Sixth Appellate DistrictTier 1 · Captured 2026-11-09 · Open the source - 9Advice 7919-E: Electric Rules 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Upgrades for GIC San Jose LLC
Pacific Gas and Electric Company (CPUC advice letter)Tier 2 · Captured 2026-11-08 · Open the source - 10Resolution E-5447: PG&E Advice Letter 7653-E non-standard EPC agreement for the Ringwood Switching Station (STACK)
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 11Resolution E-5420: PG&E Advice Letter 7569-E exceptional case, STACK Infrastructure (SI SVY01PG&E, LLC), San Jose
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 12Administrative Law Judge's Ruling Setting Schedule on Cost Allocation Issues in A.24-11-007 (PG&E Electric Rule 30)
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 13Resolution E-5433: PG&E Advice Letter 7667-E exceptional case, Sunnyvale Technology Partners LLC, Sunnyvale
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 14Resolution E-5439: PG&E Advice Letter 7635-E exceptional case, Microsoft Corporation SJC02, San Jose
California Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 15Microsoft's data center plan is approved (San Jose, 99 MW maximum load)
San Jose Mercury NewsTier 3 · Captured 2026-11-08 · Open the source - 16Alviso datacenter construction update
Microsoft (Microsoft Local blog)Tier 1 · Captured 2026-11-09 · Open the source - 17HITT Contracting Breaks Ground on Microsoft Alviso Datacenter Campus in San Jose
HITT Contracting Inc.Tier 1 · Captured 2026-11-09 · Open the source - 18California Awards $71.1 million in Tax Credits Projected to Create More Than 5,200 Jobs
California Governor's Office of Business and Economic Development (GO-Biz)Tier 1 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page