San Jose, Santa Clara County, CaliforniaUnder constructionFirst public 2017Filing entity: Microsoft CorporationLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

2 of 15 records · showing environmental permits only ·

2026

  • Air permitIssuedAug 18, 2026Bay Area Air Quality Management District

    Bay Area Air Quality Management District, Air District Application 704043; 84 generators (document numbering: Sources S-7 through S-90)

    Authority to Construct issued for the remaining 84 natural gas backup engine generators (SJC03), each abated by a 3-way catalyst system

    Permitted generators:
    84 generators (remaining SJC03 fleet)
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Notice of Determination, SCH 2021020002 (CEQAnet record 2021020002/9)

2025

  • Air permitIssuedApr 3, 2025Bay Area Air Quality Management District

    Bay Area Air Quality Management District, Air District Application #31953; Sources S-1 through S-140

    Authority to Construct issued under Regulation 2-1-301 for the first 140 natural gas backup generators (SJC02)

    Permitted generators:
    140 generators (Sources S-1 through S-140)
    Base interruptible program hours cap:
    459 hours per year per generator
    Reliability testing hours cap:
    50 hours per year per generator
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Notice of Determination, SCH 2021020002 (CEQAnet record 2021020002/5)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Notice of Determination: Issuance of an Authority to Construct for Emergency Backup Natural Gas Generators Sources S-1 through S-140 (Air District Application #31953)
    Bay Area Air Quality Management District (via CEQAnet, SCH 2021020002)
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Council Memorandum, File 25-1211: Master Easements Agreement and Site Works Agreement with Microsoft Corporation and Valley Water (October 27, 2025)
    City of San Jose
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    City Council Meeting Minutes, Tuesday, November 18, 2025
    City of San Jose (City Clerk, via Legistar)
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Notice of Determination: Issuance of Authority to Construct for Eighty-Four Emergency Backup Natural Gas Engine Generators, Sources S-7 through S-90 (Air District Application 704043)
    Bay Area Air Quality Management District (via CEQAnet, SCH 2021020002)
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Final Environmental Impact Report, San Jose Data Center / SJ2 (CEC-700-2021-003-F), Docket 19-SPPE-04
    California Energy Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    San Jose Planning Commission Action Minutes, April 9, 2025 (Microsoft CP23-016 conditional use permit, 1657 Alviso-Milpitas Rd)
    City of San Jose
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Commission Final Decision, Order No. 22-0713-6, Docket 19-SPPE-04 (San Jose City Backup Generating Facility)
    California Energy Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Organizacion Comunidad de Alviso v. City of San Jose, 60 Cal.App.5th 783 (2021), Appeal No. H046458
    California Court of Appeal, Sixth Appellate District
    Tier 1 · Captured 2026-11-09 · Open the source
  9. 9
    Advice 7919-E: Electric Rules 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Upgrades for GIC San Jose LLC
    Pacific Gas and Electric Company (CPUC advice letter)
    Tier 2 · Captured 2026-11-08 · Open the source
  10. 10
    Resolution E-5447: PG&E Advice Letter 7653-E non-standard EPC agreement for the Ringwood Switching Station (STACK)
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    Resolution E-5420: PG&E Advice Letter 7569-E exceptional case, STACK Infrastructure (SI SVY01PG&E, LLC), San Jose
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Administrative Law Judge's Ruling Setting Schedule on Cost Allocation Issues in A.24-11-007 (PG&E Electric Rule 30)
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  13. 13
    Resolution E-5433: PG&E Advice Letter 7667-E exceptional case, Sunnyvale Technology Partners LLC, Sunnyvale
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  14. 14
    Resolution E-5439: PG&E Advice Letter 7635-E exceptional case, Microsoft Corporation SJC02, San Jose
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  15. 15
    Microsoft's data center plan is approved (San Jose, 99 MW maximum load)
    San Jose Mercury News
    Tier 3 · Captured 2026-11-08 · Open the source
  16. 16
    Alviso datacenter construction update
    Microsoft (Microsoft Local blog)
    Tier 1 · Captured 2026-11-09 · Open the source
  17. 17
    HITT Contracting Breaks Ground on Microsoft Alviso Datacenter Campus in San Jose
    HITT Contracting Inc.
    Tier 1 · Captured 2026-11-09 · Open the source
  18. 18
    California Awards $71.1 million in Tax Credits Projected to Create More Than 5,200 Jobs
    California Governor's Office of Business and Economic Development (GO-Biz)
    Tier 1 · Captured 2026-11-09 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page