CaliforniaSenate2025-2026 Regular SessionBill
SB 887: Lets a data center project win CEQA judicial streamlining only if it meets strict energy, water, storage and community-benefit conditions
Official title: California Environmental Quality Act: environmental leadership development projects: data centers: geothermal power plant projects
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Signed into law as of Sep 21, 2026. The official record says: signed into law.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (current stage)
- In effect (not reached)
What it means for a household (draft rating)
Unclear for households. The bill text could not be read from the legislature through this connection.
We rate a bill as helping or costing households only when its own text says who pays or who is exempt. Otherwise it is unclear. This is a draft rating and has not been verified yet.
What it does
Service terms
Applies to: data center projects seeking CEQA environmental leadership status (California)
“The applicant has entered into a legally binding and enforceable community benefits agreement with the lead agency, community-based organizations, or a coalition of community-based organizations and other relevant stakeholders.”
Public Resources Code Sec. 21180(b)(5)(B)(x)
Certification
Applies to: data center projects seeking CEQA environmental leadership status (California)
“A data center project certified by the lead agency that meets the requirements specified in subparagraph (B).”
Public Resources Code Sec. 21180(b)(5)(A)
Certification · threshold 4 hours
Applies to: data center projects seeking CEQA environmental leadership status (California)
“The project includes zero-carbon energy storage of at least four hours at 100 percent of the forecasted peak demand of the data center.”
Public Resources Code Sec. 21180(b)(5)(B)(iii)
Certification · threshold 100 percent
Applies to: data center projects seeking CEQA environmental leadership status (California)
“The project will meet 100 percent of its electricity demand with zero-carbon electricity within five years of initial operations, with 75 percent of the zero-carbon energy resources being newly developed resources.”
Public Resources Code Sec. 21180(b)(5)(B)(viii)
Who it touches (90)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026AVAIO Digital Perseus, Pittsburg Technology Park Phase I
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 99 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon Web Services Gilroy data center
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 98 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Centersquare LAX3 (Los Angeles)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Orange County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Centersquare LAX4 (Los Angeles)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Centersquare LAX5 (Los Angeles)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 17.3 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Colovore SJC01
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Colovore SJC02
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 9 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite LA1 (One Wilshire), Los Angeles
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite LA2, Los Angeles
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite LA3, Los Angeles
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite SV1
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite SV2
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite SV9, Santa Clara
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 34 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite Santa Clara Campus (SV3-SV8)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare SFO1
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 34.5 MW on record (grid connection), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare SFO2
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 43.2 MW on record (grid connection), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare SFO3
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 8.6 MW on record (grid connection), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare SFO4
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 43.1 MW on record (grid connection), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Santa Clara data center (Sequoia, SCV1)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 67.5 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank LAX1 (Los Angeles)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 2 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank SAN1 (San Diego)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 7.2 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank SNA1 (Irvine)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 2.64 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank SNA2 (Irvine)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 8 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank/Goodman LAX2, Vernon
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 32 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty BUR10 (Burbank)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty LAX10 (Los Angeles)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty LAX11 (El Segundo)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty LAX12 (El Segundo)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty Lafayette Data Center, Santa Clara
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 66 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty OAK10 (Oakland)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Alameda County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SC1 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SFO10, San Francisco
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in San Francisco County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SFO12 (365 Main), San Francisco
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in San Francisco County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC10
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC14 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC15 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC16 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC29 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC30 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC31 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC34 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC35 (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC37, Santa Clara
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 48 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026EdgeCore Laurelwood Data Center
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 99 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Element Critical Silicon Valley SV1, Sunnyvale
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 10 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix Corvin Drive Campus
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 3 MW on record (generator capacity), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix Great Oaks South Data Center (SV1)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 99 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix LA4 (Los Angeles)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix LA7 (Los Angeles)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix SV1 (Great Oaks Campus)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix SV10 (Silicon Valley)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix SV11 (Silicon Valley)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix SV18 (Silicon Valley)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Evocative SJC11
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 9 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Evocative SJC3
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 3 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Evocative SJC7
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026GI Partners Bowers Data Center
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 72 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Hurricane Electric Fremont 2
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Alameda County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Link Logistics southeast Sacramento data center (proposed)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 50 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 400 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Menlo Digital Charlotte Drive data center, San Jose
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 99.7 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Menlo Equities 300 Holger Way data center conversion, San Jose
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 20 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft San Jose data center (Alviso)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 99 MW on record (grid connection), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Mission College Data Center
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 78.1 MW on record (generator capacity), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026NTT Sacramento campus (CA1, CA2, CA3)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 52.7 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026NTT Silicon Valley data center (SV1)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 16 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Nautilus Stockton 1 floating data center
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 7 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026NorthTown Park Data Center (GIC San Jose)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 97.3 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime Data Centers Los Angeles (LAX01), Vernon
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 33 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime Data Centers Sacramento campus (SMF01 and SMF02)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 26 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime SJC03 (2215 Martin Avenue)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 9 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime SJC04 (1231 Comstock)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 18 MW on record (generator capacity), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prologis Silver Creek Data Center
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 99 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Sacramento
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Sacramento County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Santa Clara
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Infrastructure SVY02A, Santa Clara
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 48 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK SVY01 campus, San Jose
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 100 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK SVY03A Data Center Campus, Hayward
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 76.6 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Trade Zone Park
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 99 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara I / II (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara III (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara IV (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara V (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Alameda County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara VI (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026T5@Los Angeles (T5@LA), El Segundo
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 16.65 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Data Centers Santa Clara Campus (Santa Clara)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 77 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Santa Clara I campus (CA1)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 77 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Santa Clara II campus (CA2, McLaren)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 75 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Santa Clara III data center (CA3)
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 64 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Walsh Data Center
The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 80 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))
Rule checks: Project is in California. Still to check: who it covers: not checked
Who acted
- Primary sponsorStephen C. PadillaSenate
More from California
- AB 2619 · Signed into lawRequires urban water suppliers to count data center demand in annual water supply assessments
- SB 886 · Signed into lawMakes transmission-level data centers pay for the upgrades their interconnection triggers, with refunds capped and an early termination fee
- SB 1168 · Signed into lawOrders the CPUC to assess rate structures that make data centers pay their share of grid costs and relieve residential ratepayers
- AB 2383 · Signed into lawRequires data center tariffs that make data centers pay societal grid costs and a fair share of generation costs
- AB 2469 · Signed into lawBars local permit approval for a data center unless the applicant files a water supply assessment, water scarcity plan, projected water use and workforce disclosures, and pays for needed water system improvements
- AB 93 · VetoedRequires data centers to report expected and annual water use
Sources
- 1SB 887 (Padilla), CEQA environmental leadership development projects: data centers, chaptered text
California Legislative Information (leginfo.legislature.ca.gov)Tier 1 · Open the source - 2Governor Newsom signs most comprehensive data center laws in the nation (press release, September 21, 2026)
Governor of California (gov.ca.gov)Tier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SB 887: Lets a data center project win CEQA judicial streamlining only if it meets strict energy, water, storage and community-benefit conditions." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/ca-2025-sb-887
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page