Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego

San Diego,San Diego County,CaliforniaProposedFirst public 2026Filing entity: Manchester/Edgemoor LLC (Manchester Financial Group and Edgemoor Infrastructure & Real Estate)Last checked Nov 8, 2026

Manchester Financial GroupDeveloperEdgemoor Infrastructure & Real EstateDeveloperSDG&EElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego is a proposed data center project in San Diego, San Diego County, California. Manchester Financial Group is named as developer. It was first public in 2026. It was announced at 400 MW.

Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego is a proposed data center project in San Diego, San Diego County, California. Manchester Financial Group is named as developer. It was announced at 400 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in San Diego, San Diego County, California. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

400 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows San Diego County, California.See every project on the map

The land, to scale

One football field
70.3 acres, about 53 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San DiegoProposed

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California AB 1577: Requires data centers of 10 MW or more to report facility, energy, water-cooling and PUE data to the Energy Commission

    The act requires the owner or operator of a data center with an electrical capacity of 10 megawatts or more in California to submit facility and energy information to the Energy Commission, and excludes publicly funded research, public safety, publicly funded national security, publicly owned, and utility facilities; this project has 400 MW announced on record, but whether this proposed facility on a Navy campus is a publicly owned or publicly funded national security facility excluded from the section is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    ““Data center” does not include a facility with an electrical capacity of less than 10 megawatts.” (Public Resources Code Sec. 25302.10(a)(2)(B))

    Rule checks: Project is in California; 400 MW on record (announced), threshold 10 MW (Public Resources Code Sec. 25302.10(a)(2)(B)). Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California AB 2383: Requires data center tariffs that make data centers pay societal grid costs and a fair share of generation costs

    The act requires electrical corporations to file transmission, distribution, and generation service tariffs for participating customers, data centers tariffed under the article, with a generation tariff threshold the commission will set at no more than 25 megawatts; this project has 400 MW announced on record, but whether this project is a participating customer tariffed under the article, and its peak demand against the threshold the commission will set, is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “The commission may not set a minimum peak electricity demand threshold that exceeds 25 megawatts.” (Public Utilities Code Sec. 945.5(c))

    Rule checks: Project is in California; 400 MW on record (announced), threshold 25 MW (Public Utilities Code Sec. 945.5(c)). Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California AB 2469: Bars local permit approval for a data center unless the applicant files a water supply assessment, water scarcity plan, projected water use and workforce disclosures, and pays for needed water system improvements

    The act bars a city or county from approving a permit for the construction, or an expansion that increases the maximum peak water use, of a data center unless the applicant provides a water supply assessment and other disclosures and assumes the full cost of required water infrastructure improvements; this project has 400 MW announced on record, but whether this project applies for such a construction or expansion permit is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Notwithstanding any other law, a city, county, or city and county shall not approve a discretionary or ministerial permit or other entitlement that would result in the construction, or expansion that increases the maximum peak water use, of a data center unless all of the following conditions are satisfied:” (Government Code Sec. 65964.7(b))

    Rule checks: Project is in California. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California AB 2619: Requires urban water suppliers to count data center demand in annual water supply assessments

    The act requires a person who owns or operates a data center in California, of any size class, to provide water use estimates to its water supplier before applying for an initial business license and to report water use on initial and renewal business license applications; this project has 400 MW announced on record, but whether this project's owner or operator applies for an initial or renewal business license for this facility is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Prior to applying to a city for an initial business license, equivalent instrument, or permit, a person who owns or operates a data center shall provide its water supplier, under penalty of perjury, a good faith estimate of the expected water use, the anticipated source of water, and the data center’s projected water use volume for the maximum day, maximum month, and average year.” (Business and Professions Code Sec. 16000.4(b)(1))

    Rule checks: Project is in California. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California SB 1168: Orders the CPUC to assess rate structures that make data centers pay their share of grid costs and relieve residential ratepayers

    The act directs the Public Utilities Commission, as part of a new or existing proceeding, to assess rate structures that ensure data centers pay their reasonable share of transmission and distribution costs and their proportionate share of load increases and procurements needed to reliably serve their loads; this project has 400 MW announced on record, but whether this project's costs and load are within a rate structure the commission assesses under this article is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Ensure data centers pay their reasonable share of costs associated with transmission and distribution needs, regardless of whether the data centers interconnect at the transmission or distribution level.” (Public Utilities Code Sec. 901(a))

    Rule checks: Project is in California. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California SB 57: Orders a state study of data center costs for other customers

    The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 400 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.

    “The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))

    Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California SB 886: Makes transmission-level data centers pay for the upgrades their interconnection triggers, with refunds capped and an early termination fee

    The act's transmission interconnection tariff section applies only to a data center that enters into a new interconnection agreement to receive retail electric service at the transmission level on or after January 1, 2027; this project has 400 MW announced on record, but whether this project enters into such an agreement on or after that date is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “This section shall only apply to a data center that enters into a new interconnection agreement to receive retail electric service at the transmission level on or after January 1, 2027.” (Public Utilities Code Sec. 945.3(d))

    Rule checks: Project is in California. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California SB 887: Lets a data center project win CEQA judicial streamlining only if it meets strict energy, water, storage and community-benefit conditions

    The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 400 MW announced on record, but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))

    Rule checks: Project is in California. Still to check: who it covers: not checked

Bills and laws in California

All 19 in Bill Watch

Who's involved

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego?
    Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego is a data center project in San Diego, San Diego County, California.
    Who is developing Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego?
    Manchester Financial Group is named as the developer of Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego.
    How big is Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego?
    Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego was announced at 400 MW of capacity. The site covers 70.3 acres.
    What stage is Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego?
    Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego is proposed. It was first public in 2026.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Billionaire Developer's Secretive San Diego AI Data Center Pitch Exposes Trump Ties, Housing Questions And 99-Year Navy Land Deal
      SanDiegoVille (reporting Voice of San Diego's October 15, 2026 investigation)
      Tier 3 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page