CaliforniaSenate2025-2026 Regular SessionBill
SB 57: Orders a state study of data center costs for other customers
Official title: Electrical corporations: data centers: report (Ratepayer and Technological Innovation Protection Act)
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Signed into law as of Oct 11, 2025. The official record says: signed into law.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (current stage)
- In effect (not reached)
What it does
Study or report
Applies to: the Public Utilities Commission, on data center load cost shifts (California)
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.”
Public Utilities Code Sec. 913.22(a)
Sunset
Applies to: Public Utilities Code Sec. 913.22 (California)
Ends: 2031-01-01.
“Pursuant to Section 10231.5 of the Government Code, this section is repealed on January 1, 2031.”
Public Utilities Code Sec. 913.22(c)
Reporting duty
Applies to: the Public Utilities Commission (California)
Ends: 2027-01-01.
“The commission shall submit an assessment completed pursuant to this section to the relevant policy committees of the Legislature and publicly post a copy of the assessment on the commission’s internet website on or before January 1, 2027.”
Public Utilities Code Sec. 913.22(b)
Who it touches (90)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026AVAIO Digital Perseus, Pittsburg Technology Park Phase I
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 99 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon Web Services Gilroy data center
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 63.1 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Centersquare LAX3 (Los Angeles)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Orange County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Centersquare LAX4 (Los Angeles)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Centersquare LAX5 (Los Angeles)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 17.3 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Colovore SJC01
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Colovore SJC02
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 9 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite LA1 (One Wilshire), Los Angeles
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite LA2, Los Angeles
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite LA3, Los Angeles
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite SV1
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite SV2
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite SV9, Santa Clara
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 34 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite Santa Clara Campus (SV3-SV8)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare SFO1
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 34.5 MW on record (grid connection), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare SFO2
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 43.2 MW on record (grid connection), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare SFO3
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 8.6 MW on record (grid connection), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Csquare SFO4
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 43.1 MW on record (grid connection), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Santa Clara data center (Sequoia, SCV1)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 96.5 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank LAX1 (Los Angeles)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 2 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank SAN1 (San Diego)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 7.2 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank SNA1 (Irvine)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 2.64 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank SNA2 (Irvine)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 8 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank/Goodman LAX2, Vernon
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 32 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty BUR10 (Burbank)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty LAX10 (Los Angeles)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty LAX11 (El Segundo)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty LAX12 (El Segundo)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty Lafayette Data Center, Santa Clara
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 99.8 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty OAK10 (Oakland)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Alameda County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SC1 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SFO10, San Francisco
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in San Francisco County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SFO12 (365 Main), San Francisco
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in San Francisco County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC10
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC14 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC15 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC16 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC29 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC30 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC31 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC34 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC35 (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty SJC37, Santa Clara
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 48 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026EdgeCore Laurelwood Data Center
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 99 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Element Critical Silicon Valley SV1, Sunnyvale
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 15 MW on record (grid connection), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix Corvin Drive Campus
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 3 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix Great Oaks South Data Center (SV1)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 118.5 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix LA4 (Los Angeles)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix LA7 (Los Angeles)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Los Angeles County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix SV1 (Great Oaks Campus)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix SV10 (Silicon Valley)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix SV11 (Silicon Valley)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix SV18 (Silicon Valley)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Evocative SJC11
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 6 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Evocative SJC3
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 2 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Evocative SJC7
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026GI Partners Bowers Data Center
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 72 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Hurricane Electric Fremont 2
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Link Logistics southeast Sacramento data center (proposed)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 50 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San Diego
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 400 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Menlo Digital Charlotte Drive data center, San Jose
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 99.7 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Menlo Equities 300 Holger Way data center conversion, San Jose
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 20 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft San Jose data center (Alviso)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 100.8 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Mission College Data Center
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 78.1 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026NTT Sacramento campus (CA1, CA2, CA3)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 52.7 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026NTT Silicon Valley data center (SV1)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 16 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Nautilus Stockton 1 floating data center
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 7 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026NorthTown Park Data Center (GIC San Jose)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 97.3 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime Data Centers Los Angeles (LAX01), Vernon
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 33 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime Data Centers Sacramento campus (SMF01 and SMF02)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 26 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime SJC03 (2215 Martin Avenue)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 9 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime SJC04 (1231 Comstock)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 18 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prologis Silver Creek Data Center
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 99 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Sacramento
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Sacramento County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Santa Clara
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Infrastructure SVY02A, Santa Clara
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 48 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK SVY01 campus, San Jose
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 100 MW on record (not stated), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK SVY03A Data Center Campus, Hayward
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 76.6 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Trade Zone Park
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 99 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara I / II (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara III (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara IV (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara V (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Alameda County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Santa Clara VI (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project is an operating data center in Santa Clara County, California, with no capacity figure on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026T5@Los Angeles (T5@LA), El Segundo
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 16.65 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Data Centers Santa Clara Campus (Santa Clara)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 77 MW announced on record, but whether this project is a new load from a data center served by an electrical corporation is not on record. Status part: the bill's status (signed into law, Chapter 647, Statutes of 2025) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Santa Clara I campus (CA1)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 77 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Santa Clara II campus (CA2, McLaren)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 99.8 MW on record (grid connection), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Santa Clara III data center (CA3)
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 64 MW on record (IT load), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Walsh Data Center
The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 98 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.
“The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))
Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked
Who acted
- CosponsorHenry I. SternSenate
- CosponsorJerry McNerneySenate
- Primary sponsorStephen C. PadillaSenate
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- · SenateIntroduced. Read first time. To Com. on RLS. for assignment. To print.Stage: Filed
- · SenateFrom printer. May be acted upon on or after February 8.
- · SenateReferred to Com. on E., U & C.Stage: In committee
- · SenateFrom committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U & C.
- · SenateSet for hearing April 7.
- · SenateFrom committee with author's amendments. Read second time and amended. Re-referred to Com. on E., U & C.
- · SenateFrom committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 12. Noes 3. Page 681.) (April 7).
- · SenateRead second time and amended. Re-referred to Com. on APPR.
- · SenateSet for hearing April 28.
- · SenateApril 28 hearing: Placed on APPR. suspense file.
- · SenateSet for hearing May 23.
- · SenateFrom committee: Do pass. (Ayes 5. Noes 0. Page 1189.) (May 23).
- · SenateRead second time. Ordered to third reading.
- · SenateRead third time. Passed. (Ayes 25. Noes 9. Page 1308.) Ordered to the Assembly.Stage: Passed one chamber
- · AssemblyIn Assembly. Read first time. Held at Desk.
- · AssemblyReferred to Com. on U. & E.Stage: In committee
- · AssemblyJune 25 hearing postponed by committee.
- · AssemblyFrom committee with author's amendments. Read second time and amended. Re-referred to Com. on U. & E.
- · AssemblyFrom committee: Do pass as amended and re-refer to Com. on APPR. (Ayes 13. Noes 4.) (July 9).
- · AssemblyRead second time and amended. Re-referred to Com. on APPR.
- · AssemblyAugust 20 set for first hearing. Placed on APPR. suspense file.
- · AssemblyFrom committee: Do pass as amended. (Ayes 10. Noes 4.) (August 29).
- · AssemblyRead second time and amended. Ordered to second reading.
- · AssemblyRead second time. Ordered to third reading.
- · AssemblyRead third time. Passed. (Ayes 57. Noes 18. Page 3358.) Ordered to the Senate.Stage: Passed both chambers
- · SenateIn Senate. Concurrence in Assembly amendments pending.
- · SenateAssembly amendments concurred in. (Ayes 29. Noes 8. Page 3022.) Ordered to engrossing and enrolling.
- · SenateEnrolled
- Enrolled and presented to the Governor at 2 p.m.
- Approved by the Governor.Stage: Signed into law
- Chaptered by Secretary of State. Chapter 647, Statutes of 2025.
More from California
- AB 2383 · Signed into lawRequires data center tariffs that make data centers pay societal grid costs and a fair share of generation costs
- AB 2469 · Signed into lawBars local permit approval for a data center unless the applicant files a water supply assessment, water scarcity plan, projected water use and workforce disclosures, and pays for needed water system improvements
- AB 93 · VetoedRequires data centers to report expected and annual water use
- SB 1298 · Died or failedWould have let the Energy Commission exempt data center backup generation plants up to 150 MW from powerplant certification; died in the Assembly
Sources
- 1SB 57 (2025-2026), chaptered text, Chapter 647
California Legislative Information (leginfo.legislature.ca.gov)Tier 1 · Open the source - 2SB 57 (Padilla), Chapter 647 (2025), chaptered text
California Legislative Information (leginfo.legislature.ca.gov)Tier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SB 57: Orders a state study of data center costs for other customers." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/ca-2025-sb-57
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page