CaliforniaSenate2023-2024 Regular SessionBill
SB 1298: Would have let the Energy Commission exempt data center backup generation plants up to 150 MW from powerplant certification; died in the Assembly
Official title: Certification of thermal powerplants: data centers
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Died or failed as of Sep 4, 2024. The official record says: Died in Assembly.
- Filed (done)
- In committee (not reached)
- Passed one chamber (not reached)
- Passed both chambers (not reached)
- Signed into law (not reached)
- In effect (not reached)
- Died or failed (current stage)
What it does
Reporting duty
Applies to: exemption applicants, to the Energy Commission (California)
“The applicant provides a report to the commission on the expected energy use of the facility, including, but not limited to, energy intensities, peak factors, load profiles, and other related information.”
Public Resources Code Sec. 25541(b)(1)(G), as it would have been amended
Exemption · threshold 150 MW
Applies to: backup generation facilities for data centers (California)
“Thermal powerplants with a generating capacity of up to 150 megawatts, subject to all of the following conditions: (A) The facility is used solely as a backup generation facility for a data center. (B) The facility is located on the customer side of the meter and is not interconnected to the distribution system.”
Public Resources Code Sec. 25541(b)(1), as it would have been amended
Who it touches
No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.
Other projects we track in California (90), not affected
- Amazon Web Services Gilroy data centerUnder construction
- AVAIO Digital Perseus, Pittsburg Technology Park Phase IApproved
- Centersquare LAX3 (Los Angeles)Operating
- Centersquare LAX4 (Los Angeles)Operating
- Centersquare LAX5 (Los Angeles)Operating
- Colovore SJC01Operating
- Colovore SJC02Operating
- CoreSite LA1 (One Wilshire), Los AngelesOperating
- CoreSite LA2, Los AngelesOperating
- CoreSite LA3, Los AngelesOperating
- CoreSite Santa Clara Campus (SV3-SV8)Operating
- CoreSite SV1Operating
- CoreSite SV2Operating
- CoreSite SV9, Santa ClaraOperating
- Csquare SFO1Operating
- Csquare SFO2Operating
- Csquare SFO3Operating
- Csquare SFO4Operating
- CyrusOne Santa Clara data center (Sequoia, SCV1)Operating
- DataBank/Goodman LAX2, VernonUnder construction
- DataBank LAX1 (Los Angeles)Operating
- DataBank SAN1 (San Diego)Operating
- DataBank SNA1 (Irvine)Operating
- DataBank SNA2 (Irvine)Operating
- Digital Realty BUR10 (Burbank)Operating
- Digital Realty Lafayette Data Center, Santa ClaraApproved
- Digital Realty LAX10 (Los Angeles)Operating
- Digital Realty LAX11 (El Segundo)Operating
- Digital Realty LAX12 (El Segundo)Operating
- Digital Realty OAK10 (Oakland)Operating
- Digital Realty SC1 (Santa Clara)Operating
- Digital Realty SFO10, San FranciscoOperating
- Digital Realty SFO12 (365 Main), San FranciscoOperating
- Digital Realty SJC10Operating
- Digital Realty SJC14 (Santa Clara)Operating
- Digital Realty SJC15 (Santa Clara)Operating
- Digital Realty SJC16 (Santa Clara)Operating
- Digital Realty SJC29 (Santa Clara)Operating
- Digital Realty SJC30 (Santa Clara)Operating
- Digital Realty SJC31 (Santa Clara)Operating
- Digital Realty SJC34 (Santa Clara)Operating
- Digital Realty SJC35 (Santa Clara)Operating
- Digital Realty SJC37, Santa ClaraUnder construction
- EdgeCore Laurelwood Data CenterUnder construction
- Element Critical Silicon Valley SV1, SunnyvaleOperating
- Equinix Corvin Drive CampusOperating
- Equinix Great Oaks South Data Center (SV1)Under construction
- Equinix LA4 (Los Angeles)Operating
- Equinix LA7 (Los Angeles)Operating
- Equinix SV10 (Silicon Valley)Operating
- Equinix SV11 (Silicon Valley)Operating
- Equinix SV18 (Silicon Valley)Operating
- Equinix SV1 (Great Oaks Campus)Operating
- Evocative SJC11Operating
- Evocative SJC3Operating
- Evocative SJC7Operating
- GI Partners Bowers Data CenterApproved
- Hurricane Electric Fremont 2Operating
- Link Logistics southeast Sacramento data center (proposed)Proposed
- Manchester/Edgemoor NAVWAR Old Town Campus data center concept, San DiegoProposed
- Menlo Digital Charlotte Drive data center, San JoseIn permitting
- Menlo Equities 300 Holger Way data center conversion, San JoseApproved
- Microsoft San Jose data center (Alviso)Under construction
- Mission College Data CenterStage not known
- Nautilus Stockton 1 floating data centerOperating
- NorthTown Park Data Center (GIC San Jose)In permitting
- NTT Sacramento campus (CA1, CA2, CA3)Operating
- NTT Silicon Valley data center (SV1)Operating
- Prime Data Centers Los Angeles (LAX01), VernonOperating
- Prime Data Centers Sacramento campus (SMF01 and SMF02)Expanding
- Prime SJC03 (2215 Martin Avenue)Proposed
- Prime SJC04 (1231 Comstock)Approved
- Prologis Silver Creek Data CenterIn permitting
- QTS SacramentoOperating
- QTS Santa ClaraOperating
- STACK Infrastructure SVY02A, Santa ClaraUnder construction
- STACK SVY01 campus, San JoseExpanding
- STACK SVY03A Data Center Campus, HaywardApproved
- STACK Trade Zone ParkUnder construction
- Stream Data Centers Santa Clara I / II (Santa Clara)Operating
- Stream Data Centers Santa Clara III (Santa Clara)Operating
- Stream Data Centers Santa Clara IV (Santa Clara)Operating
- Stream Data Centers Santa Clara VI (Santa Clara)Operating
- Stream Data Centers Santa Clara V (Santa Clara)Operating
- T5@Los Angeles (T5@LA), El SegundoOperating
- Vantage Data Centers Santa Clara Campus (Santa Clara)Operating
- Vantage Santa Clara I campus (CA1)Operating
- Vantage Santa Clara II campus (CA2, McLaren)Operating
- Vantage Santa Clara III data center (CA3)Under construction
- Walsh Data CenterStage not known
Who acted
- Primary sponsorDave CorteseSenate
More from California
- AB 2469 · Signed into lawBars local permit approval for a data center unless the applicant files a water supply assessment, water scarcity plan, projected water use and workforce disclosures, and pays for needed water system improvements
- AB 93 · VetoedRequires data centers to report expected and annual water use
- SB 57 · Signed into lawOrders a state study of data center costs for other customers
Sources
- 1SB 1298 (Cortese, 2023-2024), Certification of thermal powerplants: data centers, bill text
California Legislative Information (leginfo.legislature.ca.gov)Tier 1 · Open the source - 2Senator Cortese's statement on the passage of SB 1298 (September 4, 2024)
California State Senate, Senator Dave Cortese (sd15.senate.ca.gov)Tier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SB 1298: Would have let the Energy Commission exempt data center backup generation plants up to 150 MW from powerplant certification; died in the Assembly." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/ca-2023-sb-1298
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page