Showing one project: Microsoft San Jose data center (Alviso)

9 events

  1. Filing

    Filed with California Energy Commission for Microsoft San Jose data center (Alviso)

    Order No. 22-0713-6; Docket 19-SPPE-04; TN 244835/244836

  2. Filing

    Filed with California Energy Commission for Microsoft San Jose data center (Alviso)

    Docket 19-SPPE-04; CEC-700-2021-003-F; TN 241977

  3. New project

    First public record of Microsoft San Jose data center (Alviso)

    Under construction

Sources on this page

  1. 1
    Notice of Determination: Issuance of Authority to Construct for Eighty-Four Emergency Backup Natural Gas Engine Generators, Sources S-7 through S-90 (Air District Application 704043)
    Bay Area Air Quality Management District (via CEQAnet, SCH 2021020002)
    Tier 1 · Open the source
  2. 2
    City Council Meeting Minutes, Tuesday, November 18, 2025
    City of San Jose (City Clerk, via Legistar)
    Tier 1 · Open the source
  3. 3
    San Jose Planning Commission Action Minutes, April 9, 2025 (Microsoft CP23-016 conditional use permit, 1657 Alviso-Milpitas Rd)
    City of San Jose
    Tier 1 · Open the source
  4. 4
    Notice of Determination: Issuance of an Authority to Construct for Emergency Backup Natural Gas Generators Sources S-1 through S-140 (Air District Application #31953)
    Bay Area Air Quality Management District (via CEQAnet, SCH 2021020002)
    Tier 1 · Open the source
  5. 5
    Commission Final Decision, Order No. 22-0713-6, Docket 19-SPPE-04 (San Jose City Backup Generating Facility)
    California Energy Commission
    Tier 1 · Open the source
  6. 6
    Final Environmental Impact Report, San Jose Data Center / SJ2 (CEC-700-2021-003-F), Docket 19-SPPE-04
    California Energy Commission
    Tier 1 · Open the source
  7. 7
    Microsoft's data center plan is approved (San Jose, 99 MW maximum load)
    San Jose Mercury News
    Tier 3 · Open the source
  8. 8
    Council Memorandum, File 25-1211: Master Easements Agreement and Site Works Agreement with Microsoft Corporation and Valley Water (October 27, 2025)
    City of San Jose
    Tier 1 · Open the source
  9. 9
    Organizacion Comunidad de Alviso v. City of San Jose, 60 Cal.App.5th 783 (2021), Appeal No. H046458
    California Court of Appeal, Sixth Appellate District
    Tier 1 · Open the source
  10. 10
    Alviso datacenter construction update
    Microsoft (Microsoft Local blog)
    Tier 1 · Open the source
  11. 11
    HITT Contracting Breaks Ground on Microsoft Alviso Datacenter Campus in San Jose
    HITT Contracting Inc.
    Tier 1 · Open the source
  12. 12
    California Awards $71.1 million in Tax Credits Projected to Create More Than 5,200 Jobs
    California Governor's Office of Business and Economic Development (GO-Biz)
    Tier 1 · Open the source