Grid load growth by state

How much new electric load utilities and grid operators say is coming, state by state. Each figure is the publisher's own number for its own territory, printed as stated, with the date it was stated and the year it looks out to. Our article on grid load growth tells the national story behind these rows.

Utilities, grid operators, and public agencies publish how much new electric load they expect, mostly driven by data centers, and this page gathers every such figure in our record: 110 figures from 44 publishers, covering 27 states and 22 figures for multi-state territories and systems, out of the 50 states and the District of Columbia where we track data center projects. Each figure is printed as its publisher states it, with the date it was stated and the year it looks out to. The figures are never added together: each covers its own territory and its own years, and the territories overlap, so a single total would count the same expected load more than once.

Multi-state territories and systems

Figures whose territory covers more than one state, printed under the territory as the publisher states it. They are not split among the states they cover, because the publisher does not split them.

  • Alliant Energy

    Alliant Energy service territory (Iowa and Wisconsin)

    Figure: 3,400 MW, signed agreements

    Stated: October 29, 2026

    Looks out to: Not stated

    “Alliant Energy's utilities Interstate Power and Light Company (IPL) and Wisconsin Power and Light Company (WPL) have 3.4 gigawatts of contracted demand from data centers.”

  • Bonneville Power Administration balancing area

    Pacific Northwest (BPA transmission service area)

    Figure: 18,000 MW, load requests

    Stated: June 30, 2025

    Looks out to: Not stated

    “of BPA's 24 GW load request, about 18 GW is for data centers alone.”

  • Duke Energy

    Duke Energy Carolinas and Duke Energy Progress service territories, North Carolina and South Carolina

    Figure: 5,610 MW, load requests

    Stated: November 2025

    Looks out to: Not stated

    “the latest update includes 38 projects in the queue and a peak demand of 5,610 MW”

  • Duke Energy

    Duke Energy Carolinas and Duke Energy Progress service territories, North Carolina and South Carolina

    Figure: 37,000 MW, load requests

    Stated: October 8, 2025

    Looks out to: Not stated

    “data centers account for 80% of the projected energy demand”

  • Duke Energy

    Duke Energy Carolinas and Duke Energy Progress service territories, Carolinas

    Figure: 8,000 MW, forecast added load

    Stated: October 6, 2026

    Looks out to: 2035

    “The company now forecasts 8 gigawatts of large customer demand in the Carolinas by 2035 and is using that forecast to justify 9.7 gigawatts of new gas plants.”

  • Evergy

    Evergy service territory, Kansas and Missouri

    Figure: 2,500 MW, signed agreements

    Stated: August 6, 2026

    Looks out to: Not stated

    “These five ESAs include steady-state peak load of approximately 2.5 GW.”

  • MISO

    MISO footprint

    Figure: 34,000 MW, forecast peak load

    Stated: May 13, 2026

    Looks out to: 2046

    “Data centers: Largest contributor to incremental growth, with energy use increasing from about 10 TWh today to 266 TWh by 2046 (up 257 TWh). Peak demand expands sharply, rising from 1 GW to approximately 34 GW.”

  • MISO

    MISO footprint

    Figure: 184,000 MW, forecast peak load

    Stated: May 13, 2026

    Looks out to: 2046

    “MISO projects coincident peak load to grow from 124 GW in 2026 to 184 GW by 2046, representing a compound annual growth rate (CAGR) of approximately 2.0%.”

  • NYISO

    New York State

    Figure: 14,000 MW, load requests

    Stated: September 2026

    Looks out to: Not stated

    “As of September 2026, the NYISO had 53 projects requesting to interconnect to the New York system for a combined total of over 14,000 MW of proposed large loads.”

  • NYISO

    New York State

    Figure: 2,717 MW, forecast added load

    Stated: October 28, 2026

    Looks out to: 2036

    “Of the 2,717 MW of large loads assumed to be in service by 2036 in the baseline demand forecast, 1,741 MW are computational loads and 976 MW are other industrial loads.”

  • PacifiCorp

    PacifiCorp system (six states; scenario)

    Figure: 7,500 MW, forecast added load

    Stated: July 29, 2025

    Looks out to: 2045

    “the 2025 IRP includes a high data center load forecast scenario, which indicates an approximate 7.5 GW of additional system resources that could be needed to meet increased demand by 2045.”

  • PJM

    PJM region (13 states and the District of Columbia, including all of New Jersey)

    Figure: 222,000 MW, forecast peak load

    Stated: January 2026

    Looks out to: 2036

    “In absolute terms, the forecast projects the region's summer peak demand rising from approximately 154,000 megawatts today to more than 222,000 megawatts by 2036 and more than 253,000 megawatts by 2046, an increase of nearly 100,000 megawatts within 20 years.”

  • PJM

    PJM footprint

    Figure: 30,000 MW, forecast peak load

    Stated: November 2, 2026

    Looks out to: 2030

    “PJM data center demand reaches 30 GW by 2030 and 82 GW by 2047, concentrated in Dominion and AEP”

  • PJM

    PJM footprint

    Figure: 82,000 MW, forecast peak load

    Stated: November 2, 2026

    Looks out to: 2047

    “PJM data center demand reaches 30 GW by 2030 and 82 GW by 2047, concentrated in Dominion and AEP”

  • PJM

    PJM RTO footprint (includes the ComEd zone in northern Illinois)

    Figure: 209,923 MW, forecast peak load

    Stated: January 24, 2025

    Looks out to: 2035

    “Summer peak is forecasted to be 209,923 MW in 2035, a 10-year increase of 55,779 MW”

  • PJM Interconnection

    PJM footprint (13 states and the District of Columbia, including Pennsylvania)

    Figure: 30,000 MW, forecast added load

    Stated: January 2025

    Looks out to: 2030

    “electricity demand from data center growth is projected to grow up to ~30 GW between 2025 and 2030”

  • PJM Interconnection

    PJM footprint (13 states and the District of Columbia, including Pennsylvania)

    Figure: 220,000 MW, forecast peak load

    Stated: January 2025

    Looks out to: 2040

    “PJM's summer peak usage will climb by about 70 GW, to 220 GW, over the next 15 years”

  • TVA

    Tennessee Valley Authority service area (seven-state Tennessee Valley region)

    Figure: 32,000 MW, forecast added load

    Stated: August 20, 2026

    Looks out to: 2040

    “Between now and 2040, the IRP suggests that the region will need 11 to 32 gigawatts of additional generation capacity”

  • TVA

    Tennessee Valley Authority service area (seven-state Tennessee Valley region)

    Figure: 11,000 MW, forecast added load

    Stated: August 20, 2026

    Looks out to: 2040

    “Between now and 2040, the IRP suggests that the region will need 11 to 32 gigawatts of additional generation capacity”

  • TVA

    Tennessee Valley Authority service area (seven-state Tennessee Valley region)

    Figure: 42,160 MW, forecast peak load

    Stated: August 20, 2026

    Looks out to: 2040

    “2040 High Growth scenario seasonal peak demand forecasts: Winter 41,694 MW, Summer 42,160 MW”

  • TVA

    Tennessee Valley Authority service area (seven-state Tennessee Valley region)

    Figure: 36,972 MW, forecast peak load

    Stated: August 20, 2026

    Looks out to: 2040

    “2040 Reference scenario seasonal peak demand forecasts: Winter 36,486 MW, Summer 36,972 MW (2026 comparison: Winter 33,014 MW, Summer 32,776 MW)”

  • Xcel Energy

    Minnesota and the Dakotas (Xcel Energy service territory)

    Figure: 1,300 MW, forecast added load

    Stated: January 10, 2025

    Looks out to: 2032

    “Xcel anticipates supplying data centers with 1,300 megawatts in Minnesota and the Dakotas over the next seven years”

Proceedings for these publishers

Commission proceedings for the publishers above, joined on the record's own keys. Each one sets or reviews the terms a very large customer signs under.

How to read these figures

The five kinds of figure are stages and measures, not one scale. Load requests are what customers have asked a utility to serve; signed agreements are load under contract; connected load is already drawing power. Forecast added load and forecast peak load are the publisher's own projections for a stated year, and a projection is not a result.

No figure here is added to another. A grid operator's forecast covers the same ground as the forecasts of the utilities inside its footprint, and two publishers describing the same territory in different years are not describing two loads. Each row stands on its own, with its publisher, its territory, and its date.

The record covers 27 states with a figure keyed to the state, plus 22 figures for multi-state territories and systems, out of the 50 states and the District of Columbia where we track projects. A state with no group here is a state whose utilities and grid operators have published no figure we have found.

Every figure is draft research: traced to the publisher's own testimony, filing, or release by an AI research agent and not yet through verification. Each receipt says so, and names the exact place in the document the figure comes from.

The commitment side of the same record

A request is not a commitment, and a forecast is not an outcome. Of the 110 figures on this page, 16 are signed agreements: load a customer has contracted for, in 9 states and the multi-state territories. The terms those customers sign under are set in commission proceedings: we track 191 proceedings about very large loads, and 108 have been decided or are in effect. The decided terms typically require the customer to sign a minimum contract of 10 to 20 years and pay for at least 70 to 90 percent of its contracted demand every month whether it uses it or not. Each state group above lists the proceedings joined to its publishers; the full list is on the dockets page.

Of the 191 proceedings we track, 108 have been decided or are in effect. The dockets page lists every one, with its status and its terms.

This page sits under What it means for locals. Its sibling page, residential electricity prices, keeps the same kind of record for what households actually paid. The megawatts to homes calculator turns a figure on this page into household terms, and courts and dockets lists the proceedings behind the terms. The projects behind the load are ranked on largest projects by announced capacity, and the record's other rankings sit on lists from the record.

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

    Loudoun County's 128 data centers paid $684.8 million in equipment tax in fiscal 2024, at the full county rate. The record, from the county's books.

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

    Per SpaceX's Form 424B4, xAI Colossus 2 in Memphis runs two clusters online: about 110,000 GB200 processors at about 210 MW, and 110,000 GB300 processors at 220 MW, 430 MW in total.

Questions people ask

What is the largest load figure in the record?
The largest single request figure in the record is 242,999 MW from ERCOT, stated April 15, 2026. The largest signed agreement figure is 17,861 MW from AEP Ohio, stated February 12, 2026. Each is one publisher's figure for its own territory, printed with its source on its row above.
Why is there no national total?
Because the figures overlap. A grid operator's forecast covers the same ground as the forecasts of the utilities inside its footprint, and two publishers looking at the same territory in different years are not two loads. Adding the figures on this page would count the same expected load several times over, so the page prints each figure on its own row, with its publisher, its territory, and its date, and adds none of them together.
What is the difference between requests, signed agreements, and connected load?
They are stages of the same path. A request is load a customer has asked a utility to serve; most requests never become projects. A signed agreement is load under contract, with the terms a commission proceeding set. Connected load is load already drawing power. A forecast is the publisher's own projection of where its peak or its added load lands in a stated year: a projection, not a result.
Does every state have a figure here?
No. The record holds a figure keyed to 27 states; we track projects in 50 states and the District of Columbia. A state with no group on this page is a state whose utilities and grid operators have published no figure we have found, or one covered only inside a multi-state territory figure, which sits in the last group on this page under the territory's own name.

Sources

  1. 1
    Alliant Energy announces third quarter 2026 results and 2027 guidance
    Alliant Energy
    Tier 4 · Open the source
  2. 2
    Interview: Bonneville Power Administration executives discuss new projects being connected to grid in next two years
    New Project Media
    Tier 3 · Open the source
  3. 3
    Analyzing Duke Energy's 2025/26 Proposed Carbon Plan
    NC Sustainable Energy Association
    Tier 2 · Open the source
  4. 4
    North Carolina Energy Policy Task Force Interim Report
    North Carolina Energy Policy Task Force (Office of the Governor)
    Tier 1 · Open the source
  5. 5
    Walmart Asks North Carolina to Reopen Comments on Duke's 150 MW Data Center Tariff Deal, Negotiated Without It
    mgrid.org
    Tier 3 · Open the source
  6. 6
    Evergy Q2 2026 Earnings Call Transcript (August 6, 2026)
    Evergy, Inc. (call transcript republished)
    Tier 2 · Open the source
  7. 7
    MISO Long-Term Load Forecast Whitepaper (April 2026 Long-Term Load Forecast)
    Midcontinent Independent System Operator
  8. 8
    2026 Reliability Needs Assessment, draft redline for the October 28, 2026 Operating Committee / Management Committee meeting
    New York Independent System Operator
  9. 9
    Opening Comments of the NW Energy Coalition and MCAT on PacifiCorp's 2025 Integrated Resource Plan, OPUC Docket LC 85
    NW Energy Coalition and Mobilizing Climate Action Together
    Tier 2 · Open the source
  10. 10
    Load Forecasting (PJM Learning Center)
    PJM Interconnection
    Tier 1 · Open the source
  11. 11
    Charles River Associates Review of Data Center Forecast (PJM Load Analysis Subcommittee, November 2, 2026)
    PJM Interconnection
  12. 12
    2025 PJM Long Term Load Forecast Report
    PJM Interconnection
    Tier 1 · Open the source
  13. 13
    Planning: PJM Planning Prepares for Burgeoning Electricity Demand (PJM Annual Report 2025)
    PJM Interconnection
    Tier 1 · Open the source
  14. 14
    TVA Board Protects Consumers, Strengthens Reliability Amid Rising Power Demand
    Tennessee Valley Authority
    Tier 1 · Open the source
  15. 15
    2026 Integrated Resource Plan - Volume 1 (Final)
    Tennessee Valley Authority
    Tier 1 · Open the source
  16. 16
    Concern Over Power Demands of Crop of Minn. Data Centers
    Government Technology (Minnesota Star Tribune, Tribune Content Agency)
    Tier 3 · Open the source

Back to What it means for locals