Utility commission
PacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges)
Where it stands: Decided as of Dec 19, 2024
Draft research, not yet verified. Open a source to check any detail.
What it is
Order No. 24-447 set firm, initial requirements for very large load customers, meaning customers over 50,000 kW, so that under- and over-forecasting by very large new customers such as data centers does not shift power and transmission costs to other customers. A Capacity Reservation Charge of $3.68 per kW applies to the shortfall between a customer's actual peak demand and 90 percent of its reserved capacity (a 10 percent buffer). An Excess Demand Charge of three times the capacity reservation charge, $11.04 per kW, applies to demand above reserved capacity, with no buffer. A very large customer may not unilaterally reduce its reserved capacity by more than 50 MW or 10 percent per year, whichever is smaller. The two charges apply to short-term direct access customers but not to customers who have begun their five-year transition period. The charges are carried in Schedule 300. The case also set PacifiCorp's overall Oregon base rates, an increase of about 8.5 percent effective January 1, 2025. No minimum contract term, collateral amount or exit fee was adopted in the large load part of the order as read.
The facts
- Regulator
- Public Utility Commission of Oregon
- Docket number
- UE 433
- Type
- Rate case
- Utility
- PacifiCorp
- State
- Oregon
- Filed
- Feb 14, 2024
- Status date
- Dec 19, 2024
- Large-load rules
- Yes, for loads of 50 MW or more
Projects served by PacifiCorp
- Aligned Data Centers SLC-01 (West Jordan)
- Aligned Data Centers SLC-02 (West Jordan)
- Aligned Data Centers SLC-03 (West Jordan)
- Aligned Data Centers SLC-04 (West Valley City)
- Aligned Salt Lake City Campus (SLC-01, SLC-02, SLC-03)
- Aligned SLC-04
- DataBank Granite Point Campus
- DataBank SLC1
- DataBank SLC1 (Salt Lake City)
- DataBank SLC2 (Salt Lake City)
- DataBank SLC3 (Salt Lake City)
- DataBank SLC4 (Salt Lake City)
Related cases and proceedings
- Utility commission · In effectRocky Mountain Power Electric Service Schedule No. 400, Special Contracts (Wyoming)
- Utility commission · In effectInvestigation into New Load Connection Costs (Advice No. 24-38, revisions to Rule C and Rule I)
- Utility commission · In effectRocky Mountain Power Electric Service Schedule No. 400, Special Contract (Idaho)
- Utility commission · In effectSchedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
- Utility commission · In effectPacifiCorp Advice 23-06, Rule 14 Line Extensions, Tariff WN U-76
- Utility commission · In effectPacifiCorp Advice No. 23-016, Revision of Oregon Rule 13 Line Extension Policy
- Utility commission · DecidedJoint petition of PGE and QTS Investment Properties Hillsboro, LLC to increase Green Tariff Customer Supply Option capacity (GEAR, Schedule 55)
- Court case · SettledCity of The Dalles v. The Oregonian (Google water records)
In the record
- Utility case, Feb 14, 2024. Utility case filed: PacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges) Public Utility Commission of Oregon, UE 433
Sources
- 1PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
Public Utility Commission of OregonTier 1 · OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability) · Open the source - 2Staff Opening Testimony (Staff/100), Docket UE 463
Staff of the Public Utility Commission of OregonTier 1 · OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability) · Open the source - 3Data Center Coalition Opening Testimony of Bieber, Docket UE 463
Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)Tier 1 · OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability) · Open the source - 4Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
Staff of the Public Utility Commission of OregonTier 1 · OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "PacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges)." Last activity 2024-12-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pacificorp-ue433-large-load