Skip to content

Utility commission

PacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges)

Where it stands: Decided as of Dec 19, 2024

Draft research, not yet verified. Open a source to check any detail.

What it is

Order No. 24-447 set firm, initial requirements for very large load customers, meaning customers over 50,000 kW, so that under- and over-forecasting by very large new customers such as data centers does not shift power and transmission costs to other customers. A Capacity Reservation Charge of $3.68 per kW applies to the shortfall between a customer's actual peak demand and 90 percent of its reserved capacity (a 10 percent buffer). An Excess Demand Charge of three times the capacity reservation charge, $11.04 per kW, applies to demand above reserved capacity, with no buffer. A very large customer may not unilaterally reduce its reserved capacity by more than 50 MW or 10 percent per year, whichever is smaller. The two charges apply to short-term direct access customers but not to customers who have begun their five-year transition period. The charges are carried in Schedule 300. The case also set PacifiCorp's overall Oregon base rates, an increase of about 8.5 percent effective January 1, 2025. No minimum contract term, collateral amount or exit fee was adopted in the large load part of the order as read.

The facts

Regulator
Public Utility Commission of Oregon
Docket number
UE 433
Type
Rate case
Utility
PacifiCorp
State
Oregon
Filed
Feb 14, 2024
Status date
Dec 19, 2024
Large-load rules
Yes, for loads of 50 MW or more

Projects served by PacifiCorp

Related cases and proceedings

In the record

  1. Utility case, Feb 14, 2024. Utility case filed: PacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges) Public Utility Commission of Oregon, UE 433

Sources

  1. 1
    PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
    Public Utility Commission of Oregon
    Tier 1 · OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability) · Open the source
  2. 2
    Staff Opening Testimony (Staff/100), Docket UE 463
    Staff of the Public Utility Commission of Oregon
    Tier 1 · OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability) · Open the source
  3. 3
    Data Center Coalition Opening Testimony of Bieber, Docket UE 463
    Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)
    Tier 1 · OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability) · Open the source
  4. 4
    Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
    Staff of the Public Utility Commission of Oregon
    Tier 1 · OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "PacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges)." Last activity 2024-12-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pacificorp-ue433-large-load