DataBank SLC2 (Salt Lake City)

Bluffdale,Salt Lake County,UtahOperatingFirst public 2026Last checked Nov 11, 2026

DataBankOperator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

6 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

DataBank SLC2 (Salt Lake City) is an operating data center project in Bluffdale, Salt Lake County, Utah. DataBank is named as operator. It was first public in 2026. It was announced at 3.25 MW.

DataBank SLC2 (Salt Lake City) is an operating data center project in Bluffdale, Salt Lake County, Utah. DataBank is named as operator. It was announced at 3.25 MW. All six of the core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Bluffdale, Salt Lake County, Utah. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

3 MWAnnounced capacity
12Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Site-level positionPin placed from the position we have on file, inside Salt Lake County, Utah.See every project on the map

Timeline

  1. · New projectFirst public record of DataBank SLC2 (Salt Lake City)Operating

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 507: Limits local incentives for large data centers outside development zones

    The act covers large load data centers that are not located within a regionally significant development zone, for which a county or municipality may not offer an incentive, except project areas and agreements predating May 6, 2027; this project has 3.25 MW announced on record, but whether this project is a large load data center, whether it is located within such a zone, and whether a county or municipality offered it an incentive is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Except as provided in Subsection (1)(b), a county or municipality may not offer an incentive for a large load data center that is not located within a zone.” (Utah Code Sec. 63N-3a-402(1)(a))

    Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 76: Requires data centers to report water use before and after building

    The act covers large data centers, facilities with an annual water withdrawal of 75 acre feet per year or more whose buildings total at least 10,000 square feet; this project has 3.25 MW announced on record, but the project's annual water withdrawal and its building area is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “"Large data center" means a facility with an annual water withdrawal of 75 acre feet per year or more that: (i) houses a group of networked server computers in one physical location to disseminate, manage, and store data and information as the primary service of the facility; (ii) consists of one or more buildings that in total equals or exceeds 10,000 square feet;” (Utah Code Sec. 73-5-8.3(1)(d), as enacted by H.B. 76, Section 2)

    Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked

Bills and laws in Utah

Open Bill Watch

Who's involved

Public records

12 records found so far. 8 kinds of record are still being collected.

See every record

All 12 court cases and commission dockets for this project

Questions people ask

Where is DataBank SLC2 (Salt Lake City)?
DataBank SLC2 (Salt Lake City) is a data center project in Bluffdale, Salt Lake County, Utah.
Who operates DataBank SLC2 (Salt Lake City)?
DataBank is named as the operator of DataBank SLC2 (Salt Lake City).
How big is DataBank SLC2 (Salt Lake City)?
DataBank SLC2 (Salt Lake City) was announced at 3.25 MW of capacity.
What stage is DataBank SLC2 (Salt Lake City)?
DataBank SLC2 (Salt Lake City) is operating. It was first public in 2026.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
    PacifiCorp d/b/a Pacific Power & Light Company
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Settlement Stipulation, Docket No. 26-035-05, Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
    Public Service Commission of Utah (filing by Rocky Mountain Power with the Division of Public Utilities and the Office of Consumer Services)
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Notice of Decisions on UAE motion and approval of the Settlement Stipulation, Docket No. 26-035-05
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Rocky Mountain Power advances Utah's Operation Gigawatt through landmark energy agreement
    Rocky Mountain Power (PacifiCorp)
    Tier 4 · Captured 2026-11-08 · Open the source
  5. 5
    Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  6. 6
    Rocky Mountain Power Idaho Electric Service Schedule No. 400, Special Contract (I.P.U.C. No. 1, Thirteenth Revision of Sheet No. 400.1)
    Rocky Mountain Power (PacifiCorp)
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Final Order No. 35277, Case No. PAC-E-21-07 (Rocky Mountain Power Idaho rate case)
    Idaho Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  8. 8
    Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Rocky Mountain Power Wyoming Electric Service Schedule No. 400, Special Contracts (P.S.C. Wyoming No. 19, Original Sheets 400-1 to 400-3)
    Rocky Mountain Power (PacifiCorp)
    Tier 1 · Captured 2026-11-08 · Open the source
  10. 10
    Public notice of Rocky Mountain Power application to establish Tariff Schedule 400, Special Contracts, Docket No. 20000-602-ET-21 (legal notice as published July 13, 2021)
    Wyoming Public Service Commission (notice published in the Kemmerer Gazette)
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    PacifiCorp Reply Testimony of Craig M. Eller, Oregon Docket No. UE 463, Exhibit PAC/200
    PacifiCorp
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  13. 13
    Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
    Utah State Legislature
    Tier 1 · Captured 2026-11-08 · Open the source
  14. 14
    Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
    Utah State Legislature
    Tier 1 · Captured 2026-11-08 · Open the source
  15. 15
    PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  16. 16
    Staff Opening Testimony (Staff/100), Docket UE 463
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    Data Center Coalition Opening Testimony of Bieber, Docket UE 463
    Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
    PacifiCorp d/b/a Pacific Power
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    UTC Case Docket Detail Page, Docket UE-231037 (PacifiCorp, Advice 23-06)
    Washington Utilities and Transportation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  21. 21
    PacifiCorp Advice 23-06 cover letter and Rule 14 tariff sheets, Docket UE-231037
    PacifiCorp d/b/a Pacific Power & Light Company (filed with the Washington Utilities and Transportation Commission)
    Tier 1 · Captured 2026-11-08 · Open the source
  22. 22
    Alliance of Western Energy Consumers filing in Docket No. UE 463
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-07 · Open the source
  23. 23
    PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-07 · Open the source
  24. 24
    Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source
  25. 25
    ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy
  26. 26
    Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source
  27. 27
    DataBank data center locations (operator’s own list)
    DataBank
    Tier 2 · Captured 2026-11-10 · Open the source · Archived copy
  28. 28
    Salt Lake City Data Centers (DataBank market page)
    DataBank
    Tier 4 · Captured 2026-11-09 · Open the source
  29. 29
    EIA Form 861, Service Territory file, 2025 (final)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy
  30. 30
    U.S. Census Geocoder (batch geographies endpoint)
    U.S. Census Bureau
    Tier 1 · Captured 2026-11-11 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page