Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)

Where it stands: In effect as of Jan 1, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

The standard Washington large service schedule. It applies to loads that have exceeded 999 kW in more than one month of any consecutive 18-month period, and stays applicable until the customer fails to exceed 999 kW for 36 consecutive months. Monthly billing is basic, load size, demand, energy and reactive power charges, adjusted under Schedule 80. Load size is the average of the two greatest non-zero monthly demands in the 12 months ending with the current month; load sizes up to 3,000 kW are Small and above 3,000 kW are Large. Current basic charges run from $1,176.57 per month (secondary, small) to $3,951.23 (primary dedicated facilities and transmission); on-peak demand charges run $8.92 to $11.05 per kW by delivery level. On-peak demand is the greater of the measured on-peak 15-minute maximum or 500 kW. The monthly minimum charge is the sum of the basic, load size and demand charges, unless a contract specifies a higher minimum. The company may require a written contract with a term of not less than one year. Customers over 30,000 kW served from a dedicated substation they site on their own land take the Primary Dedicated Facilities delivery level. Intermittent, partial requirements or highly fluctuating loads are served only by special contract, and partial requirements loads of 1,000 kW and over go to Schedule 47T.

The facts

Regulator
Washington Utilities and Transportation Commission
Docket number
UE-250224
Type
Large load tariff
Utility
PacifiCorp
State
Washington
Status date
Jan 1, 2026
Large-load rules
Yes, for loads of 1 MW or more

Projects served by PacifiCorp

Related cases and proceedings

Sources

  1. 1
    Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
    PacifiCorp d/b/a Pacific Power & Light Company
    Tier 1 · Schedule 48T, Fifth Revision of Sheet No. 48T.1 (Applicable, Monthly Billing, Load Size note; issued 2025-12-23, effective 2026-01-01, Docket No. UE-250224) and Sheets No. 48T.2 and 48T.3 (Time Periods, Minimum Charge, Delivery Service including Primary Dedicated Facilities over 30,000 kW, On-Peak Demand 500 kW floor, Term of Contract; effective 2024-04-03, Docket No. UE-230172) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)." Last activity 2026-01-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pacificorp-wa-sch48t