Utility commission
Commission-led workshop series and policy statement on large load interconnections and tariffs
Where it stands: Pending before the commission as of Apr 7, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Policy docket, not a rate case. The Commission opened it proactively because Washington’s electric investor-owned utilities have not yet brought on significant large load customers. It will develop principles and policies for large loads seeking service and interconnection, ending in a policy statement with guidance on ratepayer protections and risk mitigation. Scope is electric IOU operations only; water and other public infrastructure effects are expressly excluded. The notice’s questions cover the large load definition, direct and indirect interconnection costs, forecasting frameworks and ratepayer protection mechanisms. No threshold is adopted: the notice asks how large load should be defined, and notes only as context that the failed HB 2515 defined emerging large energy use facilities as over 20 MW and the federal Northwest Power Act defines New Large Single Loads as 10 average MW or more in 12 months.
The facts
- Regulator
- Washington Utilities and Transportation Commission
- Docket number
- UE-260162
- Type
- Other
- State
- Washington
- Filed
- Apr 7, 2026
- Status date
- Apr 7, 2026
- Large-load rules
- Yes
Related cases and proceedings
- Utility commission · In effectSchedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
- Utility commission · In effectPacifiCorp Advice 23-06, Rule 14 Line Extensions, Tariff WN U-76
In the record
- Utility case, Apr 7, 2026. Utility case filed: Commission-led workshop series and policy statement on large load interconnections and tariffs Washington Utilities and Transportation Commission, UE-260162
Sources
- 1Notice of Hybrid Technical Conference, Docket UE-260162 (large load interconnections and tariffs)
Washington Utilities and Transportation CommissionTier 1 · Notice of Hybrid Technical Conference, service date April 7, 2026, opening paragraphs and Background (docket opened April 7, 2026; policy statement planned; IOUs have not yet brought on significant large loads) and footnote 6 (the unadopted definitions) · Open the source - 2UTC to host technical conference on large energy loads, April 27
Washington Utilities and Transportation CommissionTier 1 · Notice of Hybrid Technical Conference, service date April 7, 2026, opening paragraphs and Background (docket opened April 7, 2026; policy statement planned; IOUs have not yet brought on significant large loads) and footnote 6 (the unadopted definitions) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Commission-led workshop series and policy statement on large load interconnections and tariffs." Last activity 2026-04-07. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-utc-ue260162-large-load-policy