Proposed Rulemaking Concerning Utah Code Sections 54-26-101 to -901, Large-Scale Electric Service Requirements

Where it stands: In effect as of Jan 1, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Rulemaking that implements Senate Bill 132 (2025), codified at Utah Code Title 54, Chapter 26. The resulting rule, Utah Admin. Code R746-318, governs Commission approval of large load contracts: a large-scale service request is new service expected to reach a cumulative demand of 100 MW or greater within five years, or added service increasing a customer's total by 100 MW or greater within five years. An application for approval of a large load contract must be filed within 15 business days of execution, and the Commission approves or disapproves within 60 days. Before approval the Commission must find that the large load customer bears all just and reasonable incremental costs of the service and that existing ratepayers do not bear costs attributable to the large load. A contract with the qualified electric utility must allocate all large load incremental costs to the customer, require financial security sufficient to cover the customer's obligations, specify interconnection and delivery points, contracted capacity, term, and backup arrangements, identify the incremental generation resources used, address long-term operation and maintenance costs for large load facilities, and provide curtailment if demand exceeds contractually supported demand. The initial rule, effective January 1, 2026, does not set the large load flexible tariff directed by Utah Code 54-26-701 and does not decide transmission cost allocation; the Commission consolidated this docket with Docket No. 24-035-43, is surveying large load and flexible tariffs in other states, and expects to give flexible tariff guidance before the end of 2026, with stakeholder rule amendments due June 16, 2026.

The facts

Regulator
Public Service Commission of Utah
Docket number
25-R318-01
Type
Interconnection rule
Utility
PacifiCorp
State
Utah
Status date
Jan 1, 2026
Large-load rules
Yes, for loads of 100 MW or more

Projects served by PacifiCorp

Related cases and proceedings

Sources

  1. 1
    Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
    Public Service Commission of Utah
    Tier 1 · Notice of Comment Period, 2026-04-28, paragraphs 2 to 4 (R746-318 implemented at the beginning of this year; flexible tariff guidance before the end of 2026; amendments due 2026-06-16); CRA guidance memorandum, 2025-10-17 (rules to be published 2025-10-31, intended effective 2026-01-01; flexible tariff and cost allocation not addressed); Utah Code 54-26-101 (100 MW definitions) and 54-26-301 (contract requirements) · Open the source
  2. 2
    Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
    Public Service Commission of Utah
    Tier 1 · Notice of Comment Period, 2026-04-28, paragraphs 2 to 4 (R746-318 implemented at the beginning of this year; flexible tariff guidance before the end of 2026; amendments due 2026-06-16); CRA guidance memorandum, 2025-10-17 (rules to be published 2025-10-31, intended effective 2026-01-01; flexible tariff and cost allocation not addressed); Utah Code 54-26-101 (100 MW definitions) and 54-26-301 (contract requirements) · Open the source
  3. 3
    Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
    Utah State Legislature
    Tier 1 · Notice of Comment Period, 2026-04-28, paragraphs 2 to 4 (R746-318 implemented at the beginning of this year; flexible tariff guidance before the end of 2026; amendments due 2026-06-16); CRA guidance memorandum, 2025-10-17 (rules to be published 2025-10-31, intended effective 2026-01-01; flexible tariff and cost allocation not addressed); Utah Code 54-26-101 (100 MW definitions) and 54-26-301 (contract requirements) · Open the source
  4. 4
    Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
    Utah State Legislature
    Tier 1 · Notice of Comment Period, 2026-04-28, paragraphs 2 to 4 (R746-318 implemented at the beginning of this year; flexible tariff guidance before the end of 2026; amendments due 2026-06-16); CRA guidance memorandum, 2025-10-17 (rules to be published 2025-10-31, intended effective 2026-01-01; flexible tariff and cost allocation not addressed); Utah Code 54-26-101 (100 MW definitions) and 54-26-301 (contract requirements) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Proposed Rulemaking Concerning Utah Code Sections 54-26-101 to -901, Large-Scale Electric Service Requirements." Last activity 2026-01-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pacificorp-ut-25r31801