What it is

Implements Oregon House Bill 3546 (2025), which requires a separate classification and tariff for large energy use facilities. A Large Energy Use Facility is a customer primarily engaged in data processing (NAICS 518210) with a load, or reserved capacity, of 20,000 kW or more, that had not contracted for service before June 16, 2025. Each facility signs a negotiated agreement under Schedule 401, subject to Commission approval, with a minimum term of 10 years and a maximum of 30 years including any ramp period, a minimum payment tied to Contract Demand, credit, deposit, and security requirements, and an exit fee set in the individual agreement. A stipulation filed September 16, 2026 by PacifiCorp, Commission Staff, the Citizens’ Utility Board and the Environmental Intervenors (the Data Center Coalition opposes it; AWEC, Amazon Data Services and Vitesse do not) would settle the case on these terms: a New LEUF is a facility that had not contracted before June 16, 2025, or whose contract requires $10 million or more of new transmission, distribution or generation investment after that date; an existing LEUF that raises contract demand by 10 MW or more without meeting that definition triggers a study filing in this docket; LEUF Agreements are filed within 45 days of execution, with 90 days for Commission review of a standard agreement and 180 days for a non-conforming one; network upgrades are paid upfront by the LEUF under Rule 13; the application fee is $25,000, nonrefundable; the exit fee covers the net book value of company-funded infrastructure, the net cost of customer-specific power and tolling agreements, a Reservation Charge for the rest of the contract, and removal costs, with a pro-rata refund if a new large customer takes the capacity within three years, and collateral is sized to the exit fee and reassessed every two years; and LEUFs over 100 MW pay a Community Energy Benefits Charge of 1 cent per kWh. Within 60 days after the UE 470 rate effective date PacifiCorp must file a new rate class for LEUFs not subject to Schedule 401.

The facts

Regulator
Public Utility Commission of Oregon
Docket number
UE 463
Type
Large load tariff
Utility
PacifiCorp
State
Oregon
Filed
Oct 2, 2025
Status date
Sep 16, 2026
Large-load rules
Yes, for loads of 20 MW or more

Projects served by PacifiCorp

Related cases and proceedings

In the record

  1. Utility case, Oct 2, 2025. Utility case filed: PacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities Public Utility Commission of Oregon, UE 463

Sources

  1. 1
    Alliance of Western Energy Consumers filing in Docket No. UE 463
    Public Utility Commission of Oregon
    Tier 1 · AWEC filing, 2026-03-03 (October 2, 2025 filing of Advice No. 25-015; HB 3546 purpose; conversion to UE 463); PacifiCorp surrebuttal testimony, 2026-07-28, and Exhibit PAC/301, Revised Schedule 401 (term, minimum payment, security, exit fee) · Open the source
  2. 2
    PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
    Public Utility Commission of Oregon
    Tier 1 · AWEC filing, 2026-03-03 (October 2, 2025 filing of Advice No. 25-015; HB 3546 purpose; conversion to UE 463); PacifiCorp surrebuttal testimony, 2026-07-28, and Exhibit PAC/301, Revised Schedule 401 (term, minimum payment, security, exit fee) · Open the source
  3. 3
    Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
    Public Utility Commission of Oregon
    Tier 1 · AWEC filing, 2026-03-03 (October 2, 2025 filing of Advice No. 25-015; HB 3546 purpose; conversion to UE 463); PacifiCorp surrebuttal testimony, 2026-07-28, and Exhibit PAC/301, Revised Schedule 401 (term, minimum payment, security, exit fee); Stipulation, filed 2026-09-16, paragraphs 1-3 (parties and DCC opposition), 15 ($10 million test), 16 (10 MW study trigger), 19-20 (filing and review), 21 (agreement terms, upfront network upgrades, exit fee), 23 ($25,000 fee), 24 and 31 (10 to 30 year term), 25 (new rate class), 26 (Community Energy Benefits Charge), 29 (collateral) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "PacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities." Last activity 2026-09-16. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pacificorp-sch401