Utility commission
Investigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I
Where it stands: In effect as of Jul 8, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Order No. 26-154 (entered May 7, 2026) adopted PGE's Schedule 96 with modifications. Schedule 96 is a separate rate schedule for large nonresidential customers at or above 20 MW whose end use is data processing, created under HB 3546 (2025), the POWER Act. Customers bill transmission and generation demand at no less than 90 percent of contracted capacity; the distribution charge is billed flat at 100 percent of the cost to expand the distribution system; exceedance penalties apply above contracted capacity; minimum contract lengths and exit fees apply under the Large Load Customer Agreement, whose Rule I threshold the order lowered to 20 MW. Schedule 96 customers with 100 MW or more of allocated system capacity pay a surcharge of 1 cent per kWh, with the revenue supporting programs that offset costs for residential and low-income customers. The compliance tariff (Advice No. 26-24) took effect for service on and after July 8, 2026.
The facts
- Regulator
- Public Utility Commission of Oregon
- Docket number
- UM 2377
- Type
- Large load tariff
- Utility
- Portland General Electric Co
- State
- Oregon
- Filed
- Mar 7, 2025
- Status date
- Jul 8, 2026
- Large-load rules
- Yes, for loads of 20 MW or more
Projects served by Portland General Electric Co
Related cases and proceedings
- Utility commission · Pending before the commissionPacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities
- Utility commission · Pending before the commissionAmazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power
- Court case · Pending1000 Friends of Oregon et al. v. City of Hillsboro et al.
- Utility commission · In effectSpecial large customer rate class and Facility Site Evaluation Request process
- Utility commission · In effectInvestigation into New Load Connection Costs (Advice No. 24-38, revisions to Rule C and Rule I)
- Utility commission · In effectSchedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
- Utility commission · DecidedPacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges)
- Utility commission · In effectPacifiCorp Advice No. 23-016, Revision of Oregon Rule 13 Line Extension Policy
In the record
- Utility case, Mar 7, 2025. Utility case filed: Investigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I Public Utility Commission of Oregon, UM 2377
Sources
- 1Order No. 26-154, Investigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I, Docket UM 2377
Public Utility Commission of OregonTier 1 · Order No. 26-154, entered 05/07/2026: caption and disposition (Schedule 96 adopted with modifications); Background (docket opened at the March 7, 2025 Regular Public Meeting); summary of stipulation terms (90 percent of contracted capacity; 1-cent per kWh surcharge at 100 MW or more; Rule I LLCA threshold lowered to 20 MW). Commission release PR-202609 (Schedule 96 created under HB 3546). Compliance tariff effective date July 8, 2026 per the Q5 WG1 notes on Advice No. 26-24. · Open the source - 2Oregon PUC Approves New Rate Structure to Protect Customers Amid Rapid Data Center Growth
Public Utility Commission of OregonTier 1 · Order No. 26-154, entered 05/07/2026: caption and disposition (Schedule 96 adopted with modifications); Background (docket opened at the March 7, 2025 Regular Public Meeting); summary of stipulation terms (90 percent of contracted capacity; 1-cent per kWh surcharge at 100 MW or more; Rule I LLCA threshold lowered to 20 MW). Commission release PR-202609 (Schedule 96 created under HB 3546). Compliance tariff effective date July 8, 2026 per the Q5 WG1 notes on Advice No. 26-24. · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Investigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I." Last activity 2026-07-08. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pge-um2377-schedule96