Project File

NTT Hillsboro data center campus

Hillsboro,Washington County,OregonOperatingFirst public 2020Filing entity: NTT Global Data Centers HI, LLCLast checked Nov 9, 2026

NTTDeveloper and operatorPortland General ElectricElectric utilityNTT Global Data Centers HIOperator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

6 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

NTT Hillsboro data center campus is an operating data center project in Hillsboro, Washington County, Oregon. NTT is named as operator. It was first public in 2020. It was announced at 126 MW.

NTT Hillsboro data center campus is an operating data center project in Hillsboro, Washington County, Oregon. NTT is named as operator. It was announced at 126 MW. All six of the core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Hillsboro, Washington County, Oregon. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

NTT Hillsboro video · 2 min 7 sec

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

126 MWAnnounced capacity
15Public records we have found
1Tax agreement on record
1Backup generators, engines

For homeowners

What this project means if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    State reports list $216.6 million of this campus's property as tax-exempt in tax year 2025-26.

    Comes to the community
  2. Tax breaks

    This campus's company holds enterprise zone exemptions that abated $3.55 million in property taxes in 2025-26.

    Comes to the community
  3. Money for schools and services

    No community payment or fee for this campus is in our records.

    Not known yet
  4. Electricity bill

    Portland General Electric serves this campus, announced at 144 megawatts of critical IT load.

    Comes to the community
  5. Water

    The water provider for this campus is not in our records yet.

    Not known yet
  6. Jobs

    State zone filings report 59 total jobs for this campus's site company in tax year 2025-26.

    Comes from the community
  7. Next door: height, setbacks, noise

    No siting, setback, or noise rule for this campus is in our records yet.

    Not known yet
  8. Your say

    No public vote approved this campus; its land use and tax approvals were administrative decisions.

    How to take part
Aerial view of NTT Hillsboro data center campus in Hillsboro, Washington County, Oregon, captured 2022
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2022Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Washington County, Oregon.See every project on the map

The land, to scale

One football field
47 acres, about 36 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · Court caseCourt case filed: 1000 Friends of Oregon et al. v. City of Hillsboro et al.Circuit Court of the State of Oregon for the County of Washington
  2. · FilingFiled with NTT DATA for NTT Hillsboro data center campus
  3. · FilingFiled with NTT (NTT Group) for NTT Hillsboro data center campus
  4. · DecisionOregon Department of Environmental Quality, Northwest Region: Issued (air permit) for NTT Hillsboro data center campusAddendum R-02 to Permit No. 34-0235-ST-01; Application No. 33100
  5. · FilingFiled with NTT Ltd. for NTT Hillsboro data center campus
  6. · New projectFirst public record of NTT Hillsboro data center campusOperating
  7. · FilingFiled with Oregon Department of Environmental Quality, Northwest Region: air permit for NTT Hillsboro data center campusPermit No. 34-0235-ST-01; Application No. 031135

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Oregon HB 3546: Creates a separate rate class for large energy use facilities

    The act covers large energy use facilities, facilities that use or are able to use 20 megawatts or more and are primarily engaged in providing a service described under code 518210 of the 2022 North American Industry Classification System, as retail electricity consumers; this project has 144 MW on record (IT load), but whether this project is primarily engaged in a service described under NAICS code 518210 and is a retail electricity consumer of an electric company is not on record.

    ““Large energy use facility” means a facility that uses or is able to use 20 megawatts or more and is primarily engaged in providing a service described under code 518210 of the 2022 North American Industry Classification System.” (SECTION 2(1)(d))

    Rule checks: Project is in Oregon; 144 MW on record (it load), threshold 20 MW (SECTION 2(1)(d)). Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Oregon HB 4084: Pauses enterprise zone tax breaks for data center projects

    The measure's data center provisions govern Enterprise Zone Program authorizations and agreements for data center property, and no enterprise zone authorization or application for this project is on record.

    “However, these provisions do not apply to qualified property used in operating a data center. The measure also prohibits the authorization of an eligible business firm with property consisting of a data center project prior to 90 days after the adjournment of the 2027 regular session.” (Committee meeting document 315960, measure summary (Enterprise Zone Program))

    Rule checks: Project is in Oregon. Still to check: who it covers: not checked

Bills and laws in Oregon

Open Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 144.5 MW · Campus emergency generator fleet permitted under Oregon DEQ ACDP 34-0235-ST-01Jan 2020 · generator_capacity
  • 144 MW · Campus total (five buildings, planned)Feb 2020 · it_load
  • 144 MW · Campus as announced (five buildings)Feb 2020 · it_load
  • 126 MW · Campus total (five buildings, planned)Sep 2021 · it_load
  • 126 MW · Campus as restated by NTT Group (2021)Sep 2021 · it_load

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Oregon Department of Environmental Quality, Northwest Region, Permit No. 34-0235-ST-01; Application No. 031135

    Backup generators
    1 engines
    Stated in the filing
    2,600 gallons per year
    Stated in the filing
    39 tons per year
    Stated in the filing
    1,500 kWe
    Stated in the filing
    3,250 kWe
    Stated in the filing
    99 tons per year
    Backup generators
    44 engines
    Generator capacityEstimated
    144.5 MWComputed: 44 x 3,250 kWe + 1 x 1,500 kWe = 144,500 kWe. Every unit rating is stated in the permit; computed under the standing generator-capacity ruling. Backup generator capacity, not IT load.
  • NTT DATA

    Stated in the filing
    216 MW
    Stated in the filing
    354 MW
  • Oregon Department of Environmental Quality, Northwest Region, Addendum R-02 to Permit No. 34-0235-ST-01; Application No. 33100

    Stated in the filing
    90,000 gallons per year
  • NTT (NTT Group)

    Stated in the filing
    47 acres
    Stated in the filing
    126 MW
  • NTT Ltd.

    Stated in the filing
    6 MW
    Buildings
    5
    Floor area
    1,000,000 sq ft
    Stated in the filing
    144 MW
    Stated in the filing
    47 acres
  • Business Oregon (Oregon Business Development Department), data.oregon.gov dataset dw6g-iym3

    Stated in the filing
    $3.6 million
    Stated in the filing
    $216.6 million
    Stated in the filing
    59
    Stated in the filing
    $670.9 million
    Stated in the filing
    37
  • Business Oregon (Oregon Business Development Department), data.oregon.gov dataset 9cc3-52ar

    Stated in the filing
    $172.5 million
    Stated in the filing
    $474.8 million
    Stated in the filing
    38
    Stated in the filing
    38
    Stated in the filing
    $2.9 million
  • Business Oregon (Oregon Business Development Department), data.oregon.gov dataset ecbu-9t3b

    Stated in the filing
    $0
    Stated in the filing
    $0
    Stated in the filing
    $280.5 million

Public records

15 records found so far. 3 kinds of record are still being collected.

See every record

Questions people ask

Where is NTT Hillsboro data center campus?
NTT Hillsboro data center campus is a data center project in Hillsboro, Washington County, Oregon.
Who operates NTT Hillsboro data center campus?
NTT is named as the operator of NTT Hillsboro data center campus.
How big is NTT Hillsboro data center campus?
NTT Hillsboro data center campus was announced at 126 MW of capacity. The site covers 47 acres.
What stage is NTT Hillsboro data center campus?
NTT Hillsboro data center campus is operating. It was first public in 2020.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Standard Air Contaminant Discharge Permit No. 34-0235-ST-01, NTT Global Data Centers HI, LLC, Hillsboro
    Oregon Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    NTT DATA land acquisitions in seven markets (Mesa, Arizona campus announcement)
    NTT DATA
    Tier 4 · Captured 2026-11-08 · Open the source
  3. 3
    Addendum R-02 to Standard ACDP No. 34-0235-ST-01 (NTT Global Data Centers HI, LLC)
    Oregon Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    NTT expands its data center footprint by 20% (2021-09-01)
    NTT Group
    Tier 4 · Captured 2026-11-08 · Open the source
  5. 5
    NTT Ltd. to Expand U.S. Data Center Footprint to Hillsboro, Oregon (Business Wire release, 2020-02-05, republished)
    NTT Ltd.
    Tier 4 · Captured 2026-11-08 · Open the source
  6. 6
    Part A - Enterprise Zone Business Projects - 2026 Exemptions on Qualified Property
    Business Oregon (Oregon Business Development Department), published on data.oregon.gov
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Part A - Enterprise Zone Business Projects - 2025 Exemptions on Qualified Property
    Business Oregon (Oregon Business Development Department), published on data.oregon.gov
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Part A - Enterprise Zone Business Projects - 2024 Exemptions on Qualified Property
    Business Oregon (Oregon Business Development Department), published on data.oregon.gov
    Tier 1 · Captured 2026-11-09 · Open the source
  9. 9
    Petition for Writ of Review and Complaint for Declaratory and Injunctive Relief, 1000 Friends of Oregon et al. v. City of Hillsboro et al., Case No. 26CV30954 (filed 2026-06-22)
    Circuit Court of the State of Oregon for the County of Washington
    Tier 1 · Captured 2026-11-09 · Open the source
  10. 10
    Q&A: Enterprise Zone Agreements with Data Centers in Hillsboro
    City of Hillsboro, Oregon
    Tier 1 · Captured 2026-11-09 · Open the source
  11. 11
    Staff Report No. 5 and attachments: Community Development Code Amendments Case File CDCA-004-26 Data and Energy Storage
    City of Hillsboro Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Resolution No. 2932 (signed copy), data center and battery storage moratorium
    City of Hillsboro, Oregon (CivicWeb host)
    Tier 1 · Captured 2026-11-10 · Open the source
  13. 13
    Joint Petition of Portland General Electric Company and QTS Investment Properties Hillsboro, LLC to Increase Green Tariff Customer Supply Option Capacity (UM 2202)
    Public Utility Commission of Oregon (joint filing of Portland General Electric Company and QTS Investment Properties Hillsboro, LLC)
    Tier 1 · Captured 2026-11-09 · Open the source
  14. 14
    Order No. 21-468, UM 2202 (entered December 20, 2021)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-09 · Open the source
  15. 15
    Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  16. 16
    Order No. 26-154, Investigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I, Docket UM 2377
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    Oregon PUC Approves New Rate Structure to Protect Customers Amid Rapid Data Center Growth
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Cleaner Air Oregon Facility Status map data (August 2026 edition)
    Oregon Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  19. 19
    EPA ICIS facility interest record: NTT -HI1 DATA CENTER, Hillsboro, Oregon
    U.S. Environmental Protection Agency (Envirofacts / ICIS)
    Tier 1 · Captured 2026-11-09 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page