OregonHouse of Representatives83rd Legislative Assembly, 2026 Regular SessionBill
HB 4084: Pauses enterprise zone tax breaks for data center projects
Official title: Relating to economic development; prescribing an effective date
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Signed into law as of Jun 5, 2026. The official record says: enacted.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (current stage)
- In effect (not reached)
What it means for a household (draft rating)
Helps households. The act bars enterprise zone property tax exemption extensions for property used in operating a data center.
"the exemption period may not be extended under this section for qualified property used in operating a data center"Section 9, ORS 285C.160(1)(b), enrolled text
We rate a bill as helping or costing households only when its own text says who pays or who is exempt. Otherwise it is unclear. This is a draft rating and has not been verified yet.
What it does
Effective date
“SECTION 17. This 2026 Act takes effect on the 91st day after the date on which the 2026 regular session of the Eighty-third Legislative Assembly adjourns sine die.”
Enrolled HB 4084, Section 17
Service terms
Applies to: projects seeking fast track permitting
“(c) The Governor shall review each application forwarded by the council and the Regional Solutions Program and determine whether to approve the application. (d) The Governor may not approve an application if there are 15 projects currently in progress under the fast track permitting program.”
Enrolled HB 4084, Section 2(3)(c)-(d)
Service terms · threshold 100000000 USD
Applies to: projects seeking fast track permitting
“(2) The council shall establish eligibility criteria for the fast track permitting program. The criteria must require a project to: (a)(A) Exceed $100 million in capital investment, if the project is located within the urban growth boundary of a metropolitan service district organized under ORS chapter 268; (B) Exceed $50 million in capital investment, if the project is not located within the urban growth boundary of a metropolitan service district organized under ORS chapter 268 or within a nonurban county as described in ORS 653.026; or (C) Exceed $25 million in capital investment, if the project is located within a nonurban county as described in ORS 653.026; (b) Require more than one regulatory approval from one state agency, or more than one regulatory approval from more than one state agency; (c) Advance job creation or growth in gross domestic product through a target industry cluster, as defined by the Oregon Business Development Department by rule; (d) Meet readiness criteria established by the council; (e) Demonstrate land use compatibility; (f) Not require renewals of existing permits; and (g) Meet other requirements established by the council.”
Enrolled HB 4084, Section 2(2)
Who it touches (29)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Aligned Data Centers Hillsboro campus (PDX-01, PDX-02)
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has 120 MW on record (grid connection), but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon (AWS) Arlington land purchases
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon (AWS) Boardman data centers
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon (AWS) Boardman west campus (Bombing Range Road)
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon (AWS) Hermiston data centers
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon (AWS) Threemile Canyon Farms purchase, Boardman
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Apple Prineville Data Center
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Cogent Portland Data Center
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Crane Data Centers Portland Metro Campus
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has 100 MW announced on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty Hillsboro Schaaf Street Campus
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty PDX10 (NetApp build-to-suit), Hillsboro
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026EdgeConneX Portland campus (POR01 to POR03), Hillsboro
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has 30 MW announced on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Flexential Hillsboro campus
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has 36 MW on record (not stated), but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google The Dalles data center campus
The measure's data center provisions govern Enterprise Zone Program authorizations and agreements for data center property, and no enterprise zone authorization or application for this project is on record; its on-record tax agreements are under the Strategic Investment Program.
“However, these provisions do not apply to qualified property used in operating a data center. The measure also prohibits the authorization of an eligible business firm with property consisting of a data center project prior to 90 days after the adjournment of the 2027 regular session.” (Committee meeting document 315960, measure summary (Enterprise Zone Program))
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026H5 Data Centers Portland
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Meta Prineville Data Center
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026NTT Hillsboro data center campus
The measure's data center provisions govern Enterprise Zone Program authorizations and agreements for data center property, and no enterprise zone authorization or application for this project is on record.
“However, these provisions do not apply to qualified property used in operating a data center. The measure also prohibits the authorization of an eligible business firm with property consisting of a data center project prior to 90 days after the adjournment of the 2027 regular session.” (Committee meeting document 315960, measure summary (Enterprise Zone Program))
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Opus Interactive Hillsboro
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has 24 MW announced on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Pittock Block
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has 7 MW on record (generator capacity), but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Proposed data center at the former Hynix plant (Eugene)
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Hillsboro 3 (Hillsboro; listed as in development)
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Hillsboro data center campus
The measure's data center provisions govern Enterprise Zone Program authorizations and agreements for data center property, and no enterprise zone authorization or application for this project is on record.
“However, these provisions do not apply to qualified property used in operating a data center. The measure also prohibits the authorization of an eligible business firm with property consisting of a data center project prior to 90 days after the adjournment of the 2027 regular session.” (Committee meeting document 315960, measure summary (Enterprise Zone Program))
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Rowan Percheron data center campus
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Infrastructure POR01 (Portland)
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Infrastructure POR02 (Portland)
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Infrastructure POR03 (Portland)
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Infrastructure Portland campus (POR03), Hillsboro
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has 230 MW on record (not stated), but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Sabey Data Centers SDC Umatilla
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Verrus Oakline at Mill Creek data center campus
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
Who acted
- RequesterTina Kotek
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- · HouseFirst reading. Referred to Speaker's desk.Stage: In committee
- · HouseReferred to Economic Development, Small Business, and Trade with subsequent referral to Revenue, then Ways and Means.
- · HousePublic Hearing held.
- · HousePublic Hearing and Work Session held.
- · HouseRecommendation: Do pass with amendments, be printed A-Engrossed, and be referred to Revenue by prior reference, then be referred to Ways and Means by prior reference.
- · HouseReferred to Revenue by prior reference and then Ways and Means .
- · HousePublic Hearing held.
- · HouseWork Session held.
- · HouseRecommendation: Do pass with amendments, be printed B-Engrossed, and be referred to Ways and Means by prior reference.
- · HouseReferred to Ways and Means by prior reference.
- · HouseAssigned to Subcommittee On Capital Construction.
- · HousePublic Hearing and Work Session held.
- · HouseReturned to Full Committee.
- · HouseWork Session held.
- · HouseRecommendation: Do pass with amendments and be printed C-Engrossed.
- · HouseSecond reading.
- · HouseThird reading. Carried by Nguyen D. Passed. Ayes, 50; Nays, 5--Bunch, Cate, Reschke, Smith G, Yunker; Excused, 4--Hartman, Levy B, Scharf, Valderrama; Excused for Business of the House, 1--McIntire.Stage: Passed one chamber
- · SenateFirst reading. Referred to President's desk.
- · SenateReferred to Ways and Means.
- · SenateRecommendation: Do pass the C-Eng. bill.
- · SenateSecond reading.
- · SenateThird reading. Carried by Meek. Passed. Ayes, 21; Nays, 8--Campos, Gelser Blouin, Golden, Linthicum, Pham, Prozanski, Robinson, Sollman; Excused, 1--Hayden.Stage: Passed both chambers
- · SenatePham, granted unanimous consent to change vote to nay.
- · SenateVote explanation(s) filed by Sollman.
- · HouseSpeaker signed.
- · SenatePresident signed.
- · HouseGovernor signed.Stage: Signed into law
- · HouseChapter 50, (2026 Laws): Effective date June 5, 2026.Stage: In effect
More from Oregon
- SB 553 · Died or failedRequires a state study of data center power usage
- HB 3698 · Died or failedRequires data centers to report water and electricity use quarterly
- HB 3546 · Signed into lawCreates a separate rate class for large energy use facilities
Sources
- 1HB 4084 (2026), Fiscal Impact Statement
Oregon Legislative Information System (olis.oregonlegislature.gov)Tier 1 · Open the source - 2Enrolled House Bill 4084 (83rd Oregon Legislative Assembly, 2026 regular session)
Oregon Legislative Information SystemTier 1 · Open the source - 3HB 4084 (2026), measure overview
Oregon Legislative Information System (olis.oregonlegislature.gov)Tier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "HB 4084: Pauses enterprise zone tax breaks for data center projects." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/or-83-hb-4084
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page