Project File
Rowan Percheron data center campus
Boardman,Morrow County,OregonApprovedFirst public 2023Filing entity: Rowan Percheron, LLCLast checked Nov 8, 2026
RowanDeveloperPacifiCorpElectric utility
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Rowan Percheron data center campus is an approved data center project in Boardman, Morrow County, Oregon. Rowan is named as developer. It was first public in 2023. No site capacity figure is published for this project.
Rowan Percheron data center campus is an approved data center project in Boardman, Morrow County, Oregon. Rowan is named as developer. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Boardman, Morrow County, Oregon. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Rowan Percheron data center campusApproved
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Oregon HB 3546: Creates a separate rate class for large energy use facilities
The act covers large energy use facilities, facilities that use or are able to use 20 megawatts or more and are primarily engaged in providing a service described under code 518210 of the 2022 North American Industry Classification System, as retail electricity consumers; this project has no capacity figure on record, but whether this project is primarily engaged in a service described under NAICS code 518210 and is a retail electricity consumer of an electric company is not on record.
““Large energy use facility” means a facility that uses or is able to use 20 megawatts or more and is primarily engaged in providing a service described under code 518210 of the 2022 North American Industry Classification System.” (SECTION 2(1)(d))
Rule checks: Project is in Oregon. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Oregon HB 4084: Pauses enterprise zone tax breaks for data center projects
The act covers eligible business firms seeking enterprise zone authorization under ORS 285C.140 for property consisting of a data center project, which the act bars from authorization until 90 days after the 2027 regular session adjourns, and data center property, whose enterprise zone exemption period the act bars from extension; this project has no capacity figure on record, but whether this project has sought or holds an enterprise zone authorization or extension agreement for data center property is not on record. Status part: the bill's status (enacted) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other provision of law, an eligible business firm may not be authorized under ORS 285C.140 with respect to property consisting of a data center project before the date that is 90 days following the date on which the 2027 regular session of the Legislative Assembly adjourns sine die.” (Enrolled HB 4084, Section 11b)
Rule checks: Project is in Oregon. Still to check: who it covers: not checked
Bills and laws in Oregon
- HB 4084 · Signed into law · Jun 5, 2026Pauses enterprise zone tax breaks for data center projects
- HB 3698 · Died or failed · Jun 27, 2025Requires data centers to report water and electricity use quarterly
- SB 553 · Died or failed · Jun 27, 2025Requires a state study of data center power usage
- HB 3546 · Signed into law · Jun 16, 2025Creates a separate rate class for large energy use facilities
Who's involved
- DeveloperRowan
- Electric utilityPacifiCorp
Public records
12 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Pending before the commission · Sep 16, 2026PacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities
- Utility commission · Pending before the commission · Aug 19, 2026Amazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power
- Utility commission · Pending before the commission · Apr 28, 2026Division of Public Utilities' Request for an Investigatory Docket Regarding Rocky Mountain Power's Line Extension Policy for Large Loads
- Utility commission · Decided · Mar 19, 2026Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
- Utility commission · In effect · Jan 1, 2026Proposed Rulemaking Concerning Utah Code Sections 54-26-101 to -901, Large-Scale Electric Service Requirements
- Utility commission · In effect · Jan 1, 2026Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
- Utility commission · In effect · Jun 1, 2025Rocky Mountain Power Electric Service Schedule No. 400, Special Contracts (Wyoming)
- Utility commission · In effect · Feb 1, 2025Rocky Mountain Power Electric Service Schedule No. 400, Special Contract (Idaho)
Questions people ask
- Where is Rowan Percheron data center campus?
- Rowan Percheron data center campus is a data center project in Boardman, Morrow County, Oregon.
- Who is developing Rowan Percheron data center campus?
- Rowan is named as the developer of Rowan Percheron data center campus.
- How big is Rowan Percheron data center campus?
- The site covers 274 acres.
- What stage is Rowan Percheron data center campus?
- Rowan Percheron data center campus is approved. It was first public in 2023.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
PacifiCorp d/b/a Pacific Power & Light CompanyTier 1 · Captured 2026-11-08 · Open the source - 2Settlement Stipulation, Docket No. 26-035-05, Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
Public Service Commission of Utah (filing by Rocky Mountain Power with the Division of Public Utilities and the Office of Consumer Services)Tier 1 · Captured 2026-11-08 · Open the source - 3Notice of Decisions on UAE motion and approval of the Settlement Stipulation, Docket No. 26-035-05
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 4Rocky Mountain Power advances Utah's Operation Gigawatt through landmark energy agreement
Rocky Mountain Power (PacifiCorp)Tier 4 · Captured 2026-11-08 · Open the source - 5Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 6Rocky Mountain Power Idaho Electric Service Schedule No. 400, Special Contract (I.P.U.C. No. 1, Thirteenth Revision of Sheet No. 400.1)
Rocky Mountain Power (PacifiCorp)Tier 1 · Captured 2026-11-08 · Open the source - 7Final Order No. 35277, Case No. PAC-E-21-07 (Rocky Mountain Power Idaho rate case)
Idaho Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 8Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 9Rocky Mountain Power Wyoming Electric Service Schedule No. 400, Special Contracts (P.S.C. Wyoming No. 19, Original Sheets 400-1 to 400-3)
Rocky Mountain Power (PacifiCorp)Tier 1 · Captured 2026-11-08 · Open the source - 10Public notice of Rocky Mountain Power application to establish Tariff Schedule 400, Special Contracts, Docket No. 20000-602-ET-21 (legal notice as published July 13, 2021)
Wyoming Public Service Commission (notice published in the Kemmerer Gazette)Tier 1 · Captured 2026-11-08 · Open the source - 11PacifiCorp Reply Testimony of Craig M. Eller, Oregon Docket No. UE 463, Exhibit PAC/200
PacifiCorpTier 1 · Captured 2026-11-08 · Open the source - 12Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 13Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
Utah State LegislatureTier 1 · Captured 2026-11-08 · Open the source - 14Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
Utah State LegislatureTier 1 · Captured 2026-11-08 · Open the source - 15PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 16Staff Opening Testimony (Staff/100), Docket UE 463
Staff of the Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 17Data Center Coalition Opening Testimony of Bieber, Docket UE 463
Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)Tier 1 · Captured 2026-11-08 · Open the source - 18Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
Staff of the Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 19Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
PacifiCorp d/b/a Pacific PowerTier 1 · Captured 2026-11-08 · Open the source - 20UTC Case Docket Detail Page, Docket UE-231037 (PacifiCorp, Advice 23-06)
Washington Utilities and Transportation CommissionTier 1 · Captured 2026-11-08 · Open the source - 21PacifiCorp Advice 23-06 cover letter and Rule 14 tariff sheets, Docket UE-231037
PacifiCorp d/b/a Pacific Power & Light Company (filed with the Washington Utilities and Transportation Commission)Tier 1 · Captured 2026-11-08 · Open the source - 22Alliance of Western Energy Consumers filing in Docket No. UE 463
Public Utility Commission of OregonTier 1 · Captured 2026-11-07 · Open the source - 23PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
Public Utility Commission of OregonTier 1 · Captured 2026-11-07 · Open the source - 24Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source - 25ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 26Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source - 27Rowan Percheron, LLC, Draft Findings of Fact, AC-145-23, AC(Z)-146-22, AZM-147-23 (pre-hearing submittal, June 26, 2023)
Morrow County, OregonTier 1 · Captured 2026-11-08 · Open the source - 28Minutes of the Public Meeting of the Morrow County Planning Commission, July 25, 2023
Morrow County, OregonTier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page