Utility commission
Amazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power
Where it stands: Pending before the commission as of Aug 19, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Service complaint, not a tariff case, and it sets no rates or tariff terms. Amazon Data Services alleges in six claims that PacifiCorp failed to provide service it contracted to provide to four new ADS data center campuses in PacifiCorp’s exclusive service territory; the sixth claim asks, in the alternative, for removal of PacifiCorp’s exclusive service rights over those campuses under the Territory Allocation Law, ORS 758.400 to 758.480. The service terms are under protective order and no MW figure is public. An ALJ ruling on February 19, 2026 denied PacifiCorp’s partial motion to dismiss; the parties’ August 19, 2026 joint status report says settlement negotiations are ongoing. The UE 463 stipulation carves these campuses out of its New LEUF definition and leaves their status to this complaint proceeding.
The facts
- Regulator
- Public Utility Commission of Oregon
- Docket number
- UM 2410
- Type
- Other
- Utility
- PacifiCorp
- State
- Oregon
- Filed
- Oct 30, 2025
- Status date
- Aug 19, 2026
- Large-load rules
- Yes
Projects served by PacifiCorp
- Aligned Data Centers SLC-01 (West Jordan)
- Aligned Data Centers SLC-02 (West Jordan)
- Aligned Data Centers SLC-03 (West Jordan)
- Aligned Data Centers SLC-04 (West Valley City)
- Aligned Salt Lake City Campus (SLC-01, SLC-02, SLC-03)
- Aligned SLC-04
- DataBank Granite Point Campus
- DataBank SLC1
- DataBank SLC1 (Salt Lake City)
- DataBank SLC2 (Salt Lake City)
- DataBank SLC3 (Salt Lake City)
- DataBank SLC4 (Salt Lake City)
Related cases and proceedings
- Utility commission · Pending before the commissionPacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities
- Utility commission · In effectInvestigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I
- Court case · Pending1000 Friends of Oregon et al. v. City of Hillsboro et al.
- Utility commission · In effectSpecial large customer rate class and Facility Site Evaluation Request process
- Utility commission · Pending before the commissionDivision of Public Utilities' Request for an Investigatory Docket Regarding Rocky Mountain Power's Line Extension Policy for Large Loads
- Utility commission · DecidedApplication of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
- Utility commission · In effectProposed Rulemaking Concerning Utah Code Sections 54-26-101 to -901, Large-Scale Electric Service Requirements
- Utility commission · In effectSchedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
In the record
- Utility case, Oct 30, 2025. Utility case filed: Amazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power Public Utility Commission of Oregon, UM 2410
Sources
- 1ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
Public Utility Commission of OregonTier 1 · ALJ Ruling, 2026-02-19, Introduction (complaint filed October 30, 2025; four campuses; six claims); Third Joint Status Report, 2026-08-19 (settlement negotiations ongoing, next report due September 18, 2026) · Open the source - 2Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
Public Utility Commission of OregonTier 1 · ALJ Ruling, 2026-02-19, Introduction (complaint filed October 30, 2025; four campuses; six claims); Third Joint Status Report, 2026-08-19 (settlement negotiations ongoing, next report due September 18, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Amazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power." Last activity 2026-08-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pacificorp-um2410-ads-complaint