Special large customer rate class and Facility Site Evaluation Request process

Where it stands: In effect as of May 29, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

The District's elected Board sets its rates; the Oregon Public Utility Commission does not, and Oregon's HB 3546 does not reach the District. A special large customer rate class, set up over ten years ago, bills large customers on a monthly cost-of-service formula rate so they cover the infrastructure costs they cause, checked by regular cost of service analyses. New service starts with a six-step Facility Site Evaluation Request process for applications above 480 volts and 1 MW; loads over 5 MW must complete an Electric Service Agreement and a Service Deposit Agreement. The process does not guarantee service under existing rate schedules.

The facts

Regulator
Board of Directors, Northern Wasco County People's Utility District
Type
Other
Utility
Northern Wasco County PUD
State
Oregon
Status date
May 29, 2026
Large-load rules
Yes, for loads of 5 MW or more

Projects served by Northern Wasco County PUD

Related cases and proceedings

Sources

  1. 1
    Northern Wasco County PUD presentation to the Governor's Data Center Advisory Committee
    Northern Wasco County People's Utility District
    Tier 1 · District presentation to the Governor's Data Center Advisory Committee, 2026-05-29 (FSER steps and thresholds; formula rate; no cross-subsidization); District growth statement (special rate class set up over ten years ago) · Open the source
  2. 2
    Preparing for the Future: Northern Wasco County PUD's Commitment to Smart and Equitable Growth
    Northern Wasco County People's Utility District
    Tier 1 · District presentation to the Governor's Data Center Advisory Committee, 2026-05-29 (FSER steps and thresholds; formula rate; no cross-subsidization); District growth statement (special rate class set up over ten years ago) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Special large customer rate class and Facility Site Evaluation Request process." Last activity 2026-05-29. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-nwasco-fser