Utility commission
Registration of Will-Power UT, LLC as a Large-Scale Generation Provider (Project Aquila, Eagle Mountain)
Where it stands: In effect as of Nov 24, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
Will-Power UT registered under Utah Code 54-26-501 et seq. (S.B. 132, 2025) to build, own, and operate Project Aquila: private generation co-located with a customer industrial property in Eagle Mountain, delivering up to 286 MW through a Closed Private Generation System under Section 54-26-504, separate from Rocky Mountain Power service.
The facts
- Regulator
- Utah Public Service Commission
- Docket number
- 25-2660-01
- Type
- Other
- State
- Utah
- Filed
- Nov 24, 2025
- Status date
- Nov 24, 2025
- Large-load rules
- Yes
Related cases and proceedings
- Utility commission · Pending before the commissionDivision of Public Utilities' Request for an Investigatory Docket Regarding Rocky Mountain Power's Line Extension Policy for Large Loads
- Utility commission · DecidedApplication of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
- Utility commission · In effectProposed Rulemaking Concerning Utah Code Sections 54-26-101 to -901, Large-Scale Electric Service Requirements
In the record
- Utility case, Nov 24, 2025. Utility case filed: Registration of Will-Power UT, LLC as a Large-Scale Generation Provider (Project Aquila, Eagle Mountain) Utah Public Service Commission, 25-2660-01
Sources
- 1Notice of Registration of Will-Power UT, LLC as a Large-Scale Generation Provider, Docket No. 25-2660-01
Utah Public Service CommissionTier 1 · Notice of Registration, PSC Docket 25-2660-01, filed 2025-11-24 · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Registration of Will-Power UT, LLC as a Large-Scale Generation Provider (Project Aquila, Eagle Mountain)." Last activity 2025-11-24. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/up-utah-psc-willpower-registration-25-2660-01