Utility commission

Order Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,216

Where it stands: Pending before the commission as of Jun 18, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Order instituting a section 206 proceeding: preliminary finding that the operator's tariff appears unjust and unreasonable because it lacks terms for large loads (the orders' working definition: a new commercial or industrial customer with peak demand of 50 MW or more, interconnected above 69 kV, not part of a co-location arrangement). Response deadline extended to November 16, 2026 (SPP: November 20, 2026) per FERC's Office of Public Participation; the proceeding is still open.

The facts

Regulator
Federal Energy Regulatory Commission
Docket number
EL26-69-000
Type
Other
Place
Federal
Filed
Jun 18, 2026
Status date
Jun 18, 2026
Large-load rules
Yes, for loads of 50 MW or more

Related cases and proceedings

In the record

  1. Utility case, Jun 18, 2026. Utility case filed: Order Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,216 Federal Energy Regulatory Commission, EL26-69-000

Sources

  1. 1
    Major Orders & Regulations (June 18, 2026 large load show cause orders, EL26-67 to EL26-72)
    Federal Energy Regulatory Commission
    Tier 1 · FERC Major Orders and Regulations index, June 18, 2026: EL26-69-000, 195 FERC para. 61,216; response deadlines per FERC Office of Public Participation explainer · Open the source
  2. 2
    Cost Transparency and Customer Protection Initiatives in FERC's June 2026 Show Cause Orders for Large Load Interconnections
    Federal Energy Regulatory Commission, Office of Public Participation
    Tier 1 · FERC Major Orders and Regulations index, June 18, 2026: EL26-69-000, 195 FERC para. 61,216; response deadlines per FERC Office of Public Participation explainer · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Order Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,216." Last activity 2026-06-18. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-ferc-el26-69-nyiso