Utility commission
Order Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,215
Where it stands: Pending before the commission as of Jun 18, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Order instituting a section 206 proceeding: preliminary finding that the operator's tariff appears unjust and unreasonable because it lacks terms for large loads (the orders' working definition: a new commercial or industrial customer with peak demand of 50 MW or more, interconnected above 69 kV, not part of a co-location arrangement). Response deadline extended to November 16, 2026 (SPP: November 20, 2026) per FERC's Office of Public Participation; the proceeding is still open.
The facts
- Regulator
- Federal Energy Regulatory Commission
- Docket number
- EL26-72-000
- Type
- Other
- Place
- Federal
- Filed
- Jun 18, 2026
- Status date
- Jun 18, 2026
- Large-load rules
- Yes, for loads of 50 MW or more
Related cases and proceedings
- Utility commission · Pending before the commissionOrder Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,211
- Utility commission · Pending before the commissionOrder Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,212
- Utility commission · Pending before the commissionOrder Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,213
- Utility commission · Pending before the commissionOrder Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,214
- Utility commission · Pending before the commissionOrder Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,216
- Utility commission · Pending before the commissionOrder Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating With Other Proceedings (co-located load arrangements, PJM)
In the record
- Utility case, Jun 18, 2026. Utility case filed: Order Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,215 Federal Energy Regulatory Commission, EL26-72-000
Sources
- 1Major Orders & Regulations (June 18, 2026 large load show cause orders, EL26-67 to EL26-72)
Federal Energy Regulatory CommissionTier 1 · FERC Major Orders and Regulations index, June 18, 2026: EL26-72-000, 195 FERC para. 61,215; response deadlines per FERC Office of Public Participation explainer · Open the source - 2Cost Transparency and Customer Protection Initiatives in FERC's June 2026 Show Cause Orders for Large Load Interconnections
Federal Energy Regulatory Commission, Office of Public ParticipationTier 1 · FERC Major Orders and Regulations index, June 18, 2026: EL26-72-000, 195 FERC para. 61,215; response deadlines per FERC Office of Public Participation explainer · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Order Instituting Proceeding Under Section 206 of the Federal Power Act (large load tariff terms), 195 FERC para. 61,215." Last activity 2026-06-18. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-ferc-el26-72-iso-ne