Skip to content

Project File

Google Stonewall Business Park, Loudoun County

Leesburg,Loudoun County,VirginiaOperatingFirst public 2019Filing entity: Hayden Technologies LLCLast checked Nov 9, 2026

GoogleDeveloper and operatorAESOther role

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

6 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Google Stonewall Business Park, Loudoun County is an operating data center project in Leesburg, Loudoun County, Virginia. Google is named as operator. It was first public in 2019. No site capacity figure is published for this project.

Google Stonewall Business Park, Loudoun County is an operating data center project in Leesburg, Loudoun County, Virginia. Google is named as operator. No site capacity figure is published for this project. All six of the core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Leesburg, Loudoun County, Virginia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

23Public records we have found

For homeowners

What this project means if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    Data center equipment paid $684.8 million in Loudoun County property tax in fiscal 2024.

    Comes to the community
  2. Tax breaks

    The county gives no property tax break in our records, but Virginia exempts qualifying data center equipment from state sales tax through 2035.

    Goes both ways
  3. Money for schools and services

    The county reports data centers supplied 38 percent of its general fund revenue.

    Comes to the community
  4. Electricity bill

    The average Dominion home paid $157.75 a month in 2025, up from $122.88 in 2016, not adjusted for inflation.

    Not known yet
  5. Water

    Loudoun Water serves the unincorporated county, where this campus sits; campus water use is not published.

    Comes from the community
  6. Jobs

    Job counts for this campus are not in our records yet.

    Not known yet
  7. Next door: height, setbacks, noise

    County rules put data center buildings 200 feet from home lots and cap noise at 55 decibels at homes.

    Local rule
  8. Your say

    Supervisors voted in public on March 18, 2025 to end by-right data centers in most zoning districts.

    How to take part

Newswire for Loudoun County

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Loudoun County, Virginia.See every project on the map

The land, to scale

One football field
57.87 acres, about 44 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionVirginia Department of Environmental Quality: Issued (Article 6 minor New Source Review) (air permit) for Google Stonewall Business Park, Loudoun CountyRegistration No. 74163, permit action 74163-9
  2. · New projectFirst public record of Google Stonewall Business Park, Loudoun CountyOperating

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia HB 30: Budget act item taxing data center electricity at 1.1 cents per kWh

    The budget item taxes every data center operator on electricity consumed at each data center from July 1, 2026 to July 1, 2028 and defines a data center to include equipment for the transformation, transmission, distribution, or management of at least one megawatt of electrical power and cooling; this project is an operating data center in Virginia with a capacity figure over one megawatt on record, so every condition the text sets is met by a fact on record.

    “"Data center" means a facility whose primary services are to centralize the storage, management, and processing of digital data and is used to house (i) computer and network systems, including associated components such as servers, network equipment and appliances, telecommunications, and data storage systems; (ii) systems for monitoring and managing infrastructure performance; (iii) equipment used for the transformation, transmission, distribution, or management of at least one megawatt of capacity of electrical power and cooling, including substations, uninterruptible power supply systems, all electrical plant equipment, and associated air handlers; (iv) Internet-related equipment and services; (v) data communications connections; (vi) environmental controls; (vii) fire protection systems; and (viii) security systems and services. “Data center" does not include a facility whose primary function is to facilitate the provision of internet access service, a communication service as defined in § 58.1-647, or any combination thereof.” (Item 3-5.24, paragraph A.2 (HB 30, Chapter 1, Part 3))

    Rule checks: Project is in Virginia. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia HB 496: Requires monthly water use reports for data centers

    The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia with a DEQ air permit on record, so it falls in the reporting category the text sets.

    “Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (Chapter 623), § 62.1-44.38 C)

    Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia SB 553: Requires monthly water use reports for data centers

    The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia with a DEQ air permit on record, so it falls in the reporting category the text sets.

    “Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (conference substitute 26109885D, as passed), § 62.1-44.38 C)

    Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 1393: Shifts grid costs to the largest electricity customers

    The bill directs Dominion Energy Virginia to propose allocating capacity procurement and distribution infrastructure costs to its customer class with a contracted or measured demand of 25 megawatts or greater and an average load factor of 75 percent or greater, in rate proceedings commencing after January 1, 2027 and before July 1, 2033; this project is served by Dominion Energy Virginia on record, but its contracted or measured demand and its average annual load factor are not on record.

    “Dominion Energy Virginia to propose to the Commission, in any proceeding to determine rates for generation and distribution services commencing after January 1, 2027, and before July 1, 2033, that certain costs related to capacity procurement requirements and distribution infrastructure investments are allocated to the utility's customer class approved to serve customers with a contracted or measured electric demand of 25 megawatts or greater and an anticipated or measured average annual electric load factor of 75 percent or greater” (LIS bill-details page for HB 1393 (2026), Summary)

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 153: Requires site assessments before local approval of large data centers

    The act covers new high energy use facilities, facilities an applicant reasonably anticipates at the time of filing a rezoning, special exception, or special use permit application will require 100 megawatts or more of electrical power from a retail electric utility, which require a site assessment before local approval; this project has 390.5 MW on record (generator capacity), but whether this project is a new facility seeking such a local approval and the electrical power anticipated for it at filing is not on record.

    “"high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.” (Va. Code Sec. 15.2-2209.4 A)

    Rule checks: Project is in Virginia. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 323: Directs a state study of data center waste heat

    The act directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth, convene a work group, and report by September 1, 2026; it sets no project-level condition on an individual data center, and whether this project's waste heat is within the work group's scope is not on record.

    “Directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth by making certain findings and recommendations and convening a work group to provide expertise, assistance, and feedback on the Department's efforts.” (LIS bill-details page for HB 323 (2026), Summary As Passed)

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 507: Sets Tier 4 generator emission limits in data center air permits

    The section bars the Department of Environmental Quality from issuing a data center permit on an application submitted on or after July 1, 2026 unless the emission limit for each gen-set is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set; this project has a DEQ air permit on record issued before July 1, 2026, but the submission date of any permit application on or after July 1, 2026 is not on record.

    “For any application submitted for a data center on or after July 1, 2026, for a permit issued by the Department pursuant to this chapter, including coverage under any general permit, the Department shall not issue such permit unless the emission limit for each gen-set established by such permit is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set.” (Va. Code Sec. 10.1-1322.6(B) (2026, c. 397))

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia SB 94: Requires site assessments before local approval of large data centers

    The section's site assessment duty turns on the electrical power a facility is anticipated to require from its retail electric utility, and no such figure is on record for this campus; its on-record capacity is a 390.5 MW standby generator fleet, which does not measure power drawn from the utility.

    “"high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.” (Chapter 568 (2026 Acts of Assembly), new Code of Virginia section 15.2-2209.4, subsection A)

    Rule checks: Project is in Virginia. Still to check: size: unknown, who it covers: not checked

Bills and laws in Virginia

All 29 in Bill Watch

Who's involved

  • Developer and operatorGoogle
  • Other roleAES

Power

Capacity, as announced or filed

  • 81.25 MW · Stonewall campus generator fleet, Group 3 (non-emergency power blocks)Apr 2025 · generator_capacity
  • 258.5 MW · Stonewall campus generator fleet, Group 1 (emergency)Apr 2025 · generator_capacity
  • 390.5 MW · Stonewall campus generator fleet totalApr 2025 · generator_capacity
  • 50.75 MW · Stonewall campus generator fleet, Group 2 (emergency)Apr 2025 · generator_capacity

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • U.S. Army Corps of Engineers, Norfolk District, NAO-2010-01543

    Stated in the filing
    57.87 acres (site parcel, Stonewall Business Park, south of Leesburg)
    Stated in the filing
    0.77 acre PFO wetlands, 0.27 acre PEM wetlands, 860 linear feet of stream beds proposed permanent impacts

Public records

23 records found so far. 5 kinds of record are still being collected.

See every record

Questions people ask

Where is Google Stonewall Business Park, Loudoun County?
Google Stonewall Business Park, Loudoun County is a data center project in Leesburg, Loudoun County, Virginia.
Who operates Google Stonewall Business Park, Loudoun County?
Google is named as the operator of Google Stonewall Business Park, Loudoun County.
How big is Google Stonewall Business Park, Loudoun County?
The site covers 57.87 acres.
What stage is Google Stonewall Business Park, Loudoun County?
Google Stonewall Business Park, Loudoun County is operating. It was first public in 2019.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Public Notice NAO-2010-01543, Hayden Technologies LLC, Stonewall Business Park (Sections 404/401 joint application)
    U.S. Army Corps of Engineers, Norfolk District
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Issued Air Permits for Data Centers (list as of January 29, 2026)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Loudoun County Zoning Ordinance (official text, eReader)
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  4. 4
    Land Use Considerations (county data center page)
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  5. 5
    Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
    Dominion Energy Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  6. 6
    SCC Issues Order on DEV Biennial Review 2025
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-07 · Open the source
  7. 7
    Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
    Virginia Electric and Power Company
    Tier 1 · Captured 2026-11-07 · Open the source
  8. 8
    How the SCC Rider T1 Decision Protects Ratepayers
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Order for Notice and Hearing, Case No. PUR-2026-00056
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  10. 10
    Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
    Loudoun County Planning Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  11. 11
    Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
    Loudoun County
    Tier 1 · Captured 2026-11-09 · Open the source
  12. 12
    Town Council Meeting, March 14, 2023: agenda and official webcast captions
    Town of Leesburg, Virginia (Granicus webcast archive)
    Tier 1 · Captured 2026-11-09 · Open the source
  13. 13
    Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
    Virginia Commission on Local Government (Department of Housing and Community Development)
    Tier 1 · Captured 2026-11-09 · Open the source
  14. 14
    Town Council Meeting, February 27, 2024: agenda and official webcast captions
    Town of Leesburg, Virginia (Granicus webcast archive)
    Tier 1 · Captured 2026-11-09 · Open the source
  15. 15
    Leesburg Town Council Approves Voluntary Settlement Agreement Related to Compass Creek Annexation
    Town of Leesburg, Virginia
    Tier 1 · Captured 2026-11-09 · Open the source
  16. 16
    Board of Supervisors Business Meeting Minutes, March 18, 2025
    Loudoun County
    Tier 1 · Captured 2026-11-07 · Open the source
  17. 17
    Loudoun County Board of Equalization 2025 Annual Report
    Loudoun County Board of Equalization
    Tier 1 · Captured 2026-11-09 · Open the source
  18. 18
    Google Data Centers - A Global Leader Expands in Virginia (event listing)
    Loudoun County Economic Development
    Tier 1 · Captured 2026-11-07 · Open the source
  19. 19
    Google 2026 Environmental Report
    Google
    Tier 4 · Captured 2026-11-08 · Open the source
  20. 20
    Google Data Centers: Locations
    Google
    Tier 4 · Captured 2026-11-09 · Open the source
  21. 21
    FY 2026 Proposed Budget
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  22. 22
    FY 2027 Proposed Budget, Executive Summary
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  23. 23
    Code of Virginia, Section 58.1-609.3, subdivision 18 (data center sales and use tax exemption)
    Virginia Legislative Information System
    Tier 1 · Captured 2026-11-08 · Open the source
  24. 24
    Data Center Retail Sales & Use Tax Exemption
    Virginia Economic Development Partnership
    Tier 1 · Captured 2026-11-08 · Open the source
  25. 25
    FY 2026 Proposed Budget Presentation
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  26. 26
    EIA Form 861 2025, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-07 · Open the source
  27. 27
    EIA Form 861 2016, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-07 · Open the source
  28. 28
    Capital Improvement Plan 2024-2033
    Loudoun Water
    Tier 1 · Captured 2026-11-08 · Open the source
  29. 29
    Stationary Source Permit to Construct and Operate, Hayden Technologies LLC, Registration No. 74163 (minor New Source Review permit action 74163-9), April 30, 2025
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  30. 30
    AES to provide carbon-free power for Google's Loudoun data centers
    Virginia Business
    Tier 3 · Captured 2026-11-07 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page