Project File
CyrusOne Sterling campus (Northern Virginia)
Loudoun County,VirginiaOperatingFirst public 2016Last checked Nov 9, 2026
CyrusOneDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: City or address
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
CyrusOne Sterling campus (Northern Virginia) is an operating data center project in Loudoun County, Virginia. CyrusOne is named as operator. It was first public in 2016. No site capacity figure is published for this project.
CyrusOne Sterling campus (Northern Virginia) is an operating data center project in Loudoun County, Virginia. CyrusOne is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Loudoun County, Virginia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
- Property tax
Data center equipment paid $684.8 million in Loudoun County property tax in fiscal 2024.
Comes to the community - Tax breaks
Virginia exempts qualifying data center equipment from state sales tax through 2035; the county adds no break in our records.
Goes both ways - Money for schools and services
No community payment or fee for this campus is in our records.
Not known yet - Electricity bill
The average Dominion home paid $157.75 a month in 2025, up from $122.88 in 2016, not adjusted for inflation.
Not known yet - Water
The water provider for this campus is not in our records yet.
Not known yet - Jobs
Job counts for this campus are not in our records yet.
Not known yet - Next door: height, setbacks, noise
County rules put data center buildings 200 feet from home lots and cap noise at 55 decibels at homes.
Local rule - Your say
Supervisors voted in public on March 18, 2025 to end by-right data centers in most zoning districts.
How to take part
Newswire for Loudoun County
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · DecisionVirginia Department of Environmental Quality: Issued; stationary source permit to construct and operate emergency diesel engine generator sets; supersedes the permit dated April 1, 2016 (air permit) for CyrusOne Sterling campus (Northern Virginia)Registration No. 74086
- · FilingFiled with Virginia Department of Environmental Quality: air permit for CyrusOne Sterling campus (Northern Virginia)Registration No. 74086
- · New projectFirst public record of CyrusOne Sterling campus (Northern Virginia)Operating
- · DecisionLoudoun County: Approved the special exception to raise floor-area ratio for CyrusOne Sterling campus (Northern Virginia)SPEX-2016-0003
- · DecisionLoudoun County: Approved site plan for the existing and proposed facilities on site for CyrusOne Sterling campus (Northern Virginia)STPL-2016-0010
- · DecisionVirginia Department of Environmental Quality: Issued; stationary source permit to construct and operate emergency diesel engine generator sets; superseded by the permit dated November 1, 2016 (air permit) for CyrusOne Sterling campus (Northern Virginia)Registration No. 74086
- · FilingFiled with Loudoun County for CyrusOne Sterling campus (Northern Virginia)SPEX-2016-0003
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia HB 30: Budget act item taxing data center electricity at 1.1 cents per kWh
The budget item taxes every data center operator on electricity consumed at each data center from July 1, 2026 to July 1, 2028 and defines a data center to include equipment for the transformation, transmission, distribution, or management of at least one megawatt of electrical power and cooling; this project is an operating data center in Virginia with a capacity figure over one megawatt on record, so every condition the text sets is met by a fact on record.
“"Data center" means a facility whose primary services are to centralize the storage, management, and processing of digital data and is used to house (i) computer and network systems, including associated components such as servers, network equipment and appliances, telecommunications, and data storage systems; (ii) systems for monitoring and managing infrastructure performance; (iii) equipment used for the transformation, transmission, distribution, or management of at least one megawatt of capacity of electrical power and cooling, including substations, uninterruptible power supply systems, all electrical plant equipment, and associated air handlers; (iv) Internet-related equipment and services; (v) data communications connections; (vi) environmental controls; (vii) fire protection systems; and (viii) security systems and services. “Data center" does not include a facility whose primary function is to facilitate the provision of internet access service, a communication service as defined in § 58.1-647, or any combination thereof.” (Item 3-5.24, paragraph A.2 (HB 30, Chapter 1, Part 3))
Rule checks: Project is in Virginia; 30 MW on record (it load), threshold 1 MW (Item 3-5.24, paragraph A.2 (HB 30, Chapter 1, Part 3)). Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia HB 496: Requires monthly water use reports for data centers
The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia with a DEQ air permit on record, so it falls in the reporting category the text sets.
“Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (Chapter 623), § 62.1-44.38 C)
Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia SB 553: Requires monthly water use reports for data centers
The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia with a DEQ air permit on record, so it falls in the reporting category the text sets.
“Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (conference substitute 26109885D, as passed), § 62.1-44.38 C)
Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 1393: Shifts grid costs to the largest electricity customers
The bill directs Dominion Energy Virginia to propose allocating capacity procurement and distribution infrastructure costs to its customer class with a contracted or measured demand of 25 megawatts or greater and an average load factor of 75 percent or greater, in rate proceedings commencing after January 1, 2027 and before July 1, 2033; this project is served by Dominion Energy Virginia on record, but its contracted or measured demand and its average annual load factor are not on record.
“Dominion Energy Virginia to propose to the Commission, in any proceeding to determine rates for generation and distribution services commencing after January 1, 2027, and before July 1, 2033, that certain costs related to capacity procurement requirements and distribution infrastructure investments are allocated to the utility's customer class approved to serve customers with a contracted or measured electric demand of 25 megawatts or greater and an anticipated or measured average annual electric load factor of 75 percent or greater” (LIS bill-details page for HB 1393 (2026), Summary)
Rule checks: Project is in Virginia. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 323: Directs a state study of data center waste heat
The act directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth, convene a work group, and report by September 1, 2026; it sets no project-level condition on an individual data center, and whether this project's waste heat is within the work group's scope is not on record.
“Directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth by making certain findings and recommendations and convening a work group to provide expertise, assistance, and feedback on the Department's efforts.” (LIS bill-details page for HB 323 (2026), Summary As Passed)
Rule checks: Project is in Virginia. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 507: Sets Tier 4 generator emission limits in data center air permits
The section bars the Department of Environmental Quality from issuing a data center permit on an application submitted on or after July 1, 2026 unless the emission limit for each gen-set is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set; this project has a DEQ air permit on record issued before July 1, 2026, but the submission date of any permit application on or after July 1, 2026 is not on record.
“For any application submitted for a data center on or after July 1, 2026, for a permit issued by the Department pursuant to this chapter, including coverage under any general permit, the Department shall not issue such permit unless the emission limit for each gen-set established by such permit is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set.” (Va. Code Sec. 10.1-1322.6(B) (2026, c. 397))
Rule checks: Project is in Virginia. Still to check: who it covers: not checked
Bills and laws in Virginia
- HB 2027 · Died or failedRequires a state certificate to operate large power users
- HB 2578 · Died or failedAdds clean energy conditions to the data center tax break
- SB 843 · Filed · Oct 9, 2026Bars new data center approvals statewide for three years
- EO 22 · In effect · Sep 18, 2026Sets Virginia data center standards and bans secret project agreements
- HB 30 · In effect · Jul 1, 2026Budget act item taxing data center electricity at 1.1 cents per kWh
- HB 1393 · Signed into law · May 14, 2026Shifts grid costs to the largest electricity customers
Who's involved
- Developer and operatorCyrusOne
Power
Capacity, as announced or filed
- 30 MW · Phase 2 (Sterling II)Jun 2016 · it_load
From the filings
Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.
Loudoun County, SPEX-2016-0003
- Stated in the filing
- 499,720 square feet (total building floor area the special exception would allow, up from the existing 362111 square feet)
- Stated in the filing
- public water and sewer utility service stated for the property in the County staff analysis (service provider not named in that sentence)
- Stated in the filing
- 14.34 acres (subject property, Tax Map /81///8////16/, PIN 030-39-2674)
Virginia Department of Environmental Quality, Registration No. 74086
- Backup generators
- 10 emergency diesel engine gen-sets to be constructed under the November 1, 2016 permit (MTU 16V4000G83, 2,250 ekW each)
- Backup generators
- 29 emergency diesel engine gen-sets permitted before November 1, 2016 and carried into this permit (28 MTU 16V4000G83 at 2,250 ekW each, plus 1 MTU house gen-set at 750 ekW)
Public records
23 records found so far. 5 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Pending before the commission · Aug 25, 2026Supplemental proceeding for Dominion Energy Virginia proposed amendments to its line extension policy (direct connect transmission facilities for large load customers)
- Utility commission · Decided · May 1, 2026Application of Virginia Electric and Power Company for approval of a rate adjustment clause (Rider T1) pursuant to Section 56-585.1 A 4 of the Code of Virginia
- Utility commission · Pending before the commission · Feb 19, 2026Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards
- Utility commission · Decided · Nov 25, 2025Application of Virginia Electric and Power Company for a 2025 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
- Utility commission · Decided · Feb 28, 2024Application of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
Questions people ask
- Where is CyrusOne Sterling campus (Northern Virginia)?
- CyrusOne Sterling campus (Northern Virginia) is a data center project in Loudoun County, Virginia.
- Who operates CyrusOne Sterling campus (Northern Virginia)?
- CyrusOne is named as the operator of CyrusOne Sterling campus (Northern Virginia).
- What stage is CyrusOne Sterling campus (Northern Virginia)?
- CyrusOne Sterling campus (Northern Virginia) is operating. It was first public in 2016.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Planning Commission Public Hearing Staff Report, SPEX-2016-0003, Cyrus One Loudoun Tech Center (May 24, 2016)
Loudoun County Department of Planning and ZoningTier 1 · Captured 2026-11-09 · Open the source - 2
- 3Board of Supervisors Business Meeting Information Item I-3, Briefing Item: Land Development Applications, June 15, 2016 Public Hearing (June 7, 2016)
Loudoun County Board of SupervisorsTier 1 · Captured 2026-11-09 · Open the source - 4Board of Supervisors Public Hearing, June 15, 2016, hearing video and captions (Granicus clip 4531)
Loudoun County Board of SupervisorsTier 1 · Captured 2026-11-09 · Open the source - 5Stationary Source Permit to Construct and Operate, CyrusOne Loudoun Tech Center, Registration No. 74086 (November 1, 2016)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 6Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 7Loudoun County Zoning Ordinance (official text, eReader)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 8Land Use Considerations (county data center page)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 9Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Captured 2026-11-07 · Open the source - 10SCC Issues Order on DEV Biennial Review 2025
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 11Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
Virginia Electric and Power CompanyTier 1 · Captured 2026-11-07 · Open the source - 12How the SCC Rider T1 Decision Protects Ratepayers
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 13Order for Notice and Hearing, Case No. PUR-2026-00056
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 14Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
Loudoun County Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 15Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 16Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Captured 2026-11-09 · Open the source - 17Board of Supervisors Business Meeting Minutes, March 18, 2025
Loudoun CountyTier 1 · Captured 2026-11-07 · Open the source - 18Loudoun County Board of Equalization 2025 Annual Report
Loudoun County Board of EqualizationTier 1 · Captured 2026-11-09 · Open the source - 19CyrusOne's New Data Center - Where Hyper Cloud Scale Meets Hyper Data Center Speed (Sterling II completion, 30 MW)
CyrusOne Inc. (Business Wire)Tier 4 · Captured 2026-11-08 · Open the source - 20CyrusOne Announces New Leadership in Northern Virginia to Support Public Sector Growth (8 data centers, 1.9M sq ft, Sterling campus)
CyrusOne Inc. (Business Wire)Tier 4 · Captured 2026-11-08 · Open the source - 21
- 22FY 2027 Proposed Budget, Executive Summary
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 23Code of Virginia, Section 58.1-609.3, subdivision 18 (data center sales and use tax exemption)
Virginia Legislative Information SystemTier 1 · Captured 2026-11-08 · Open the source - 24Data Center Retail Sales & Use Tax Exemption
Virginia Economic Development PartnershipTier 1 · Captured 2026-11-08 · Open the source - 25EIA Form 861 2025, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source - 26EIA Form 861 2016, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page