2 of 23 records · showing environmental permits only ·
2016
Air permitIssuedNov 1, 2016Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, Registration No. 74086
Issued; stationary source permit to construct and operate emergency diesel engine generator sets; supersedes the permit dated April 1, 2016
- Backup generators:
- 10 emergency diesel engine gen-sets to be constructed under the November 1, 2016 permit (MTU 16V4000G83, 2,250 ekW each)
- Backup generators:
- 29 emergency diesel engine gen-sets permitted before November 1, 2016 and carried into this permit (28 MTU 16V4000G83 at 2,250 ekW each, plus 1 MTU house gen-set at 750 ekW)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Transmittal letter, November 1, 2016, and attached permit cover sheet: CyrusOne Loudoun Tech Center, 21111 Ridgetop Circle, Sterling, VA 20166, Registration No. 74086, approved November 1, 2016; DEQ issued-permits list row: CyrusOne Loudoun Tech Center, 74086, 11/01/2016, Article 6 mNSR, Loudoun County
Air permitReplaced by a later filingApr 1, 2016Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, Registration No. 74086
Issued; stationary source permit to construct and operate emergency diesel engine generator sets; superseded by the permit dated November 1, 2016
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Equipment List (p. 3) and transmittal letter of the November 1, 2016 permit for Registration No. 74086: the November permit supersedes the permit dated April 1, 2016, and its Equipment List carries the April permit's units (28 MTU 16V4000G83 at 2,250 ekW each plus one MTU 12V2000G85 TB house unit at 750 ekW); DEQ issued-permits list row: CyrusOne Loudoun Tech Center, 74086, 04/01/2016, Article 6 mNSR, Loudoun County
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Planning Commission Public Hearing Staff Report, SPEX-2016-0003, Cyrus One Loudoun Tech Center (May 24, 2016)
Loudoun County Department of Planning and ZoningTier 1 · Captured 2026-11-09 · Open the source - 2
- 3Board of Supervisors Business Meeting Information Item I-3, Briefing Item: Land Development Applications, June 15, 2016 Public Hearing (June 7, 2016)
Loudoun County Board of SupervisorsTier 1 · Captured 2026-11-09 · Open the source - 4Board of Supervisors Public Hearing, June 15, 2016, hearing video and captions (Granicus clip 4531)
Loudoun County Board of SupervisorsTier 1 · Captured 2026-11-09 · Open the source - 5Stationary Source Permit to Construct and Operate, CyrusOne Loudoun Tech Center, Registration No. 74086 (November 1, 2016)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 6Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 7Loudoun County Zoning Ordinance (official text, eReader)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 8Land Use Considerations (county data center page)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 9Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Captured 2026-11-07 · Open the source - 10SCC Issues Order on DEV Biennial Review 2025
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 11Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
Virginia Electric and Power CompanyTier 1 · Captured 2026-11-07 · Open the source - 12How the SCC Rider T1 Decision Protects Ratepayers
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 13Order for Notice and Hearing, Case No. PUR-2026-00056
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 14Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
Loudoun County Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 15Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 16Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Captured 2026-11-09 · Open the source - 17Board of Supervisors Business Meeting Minutes, March 18, 2025
Loudoun CountyTier 1 · Captured 2026-11-07 · Open the source - 18Loudoun County Board of Equalization 2025 Annual Report
Loudoun County Board of EqualizationTier 1 · Captured 2026-11-09 · Open the source - 19CyrusOne's New Data Center - Where Hyper Cloud Scale Meets Hyper Data Center Speed (Sterling II completion, 30 MW)
CyrusOne Inc. (Business Wire)Tier 4 · Captured 2026-11-08 · Open the source - 20CyrusOne Announces New Leadership in Northern Virginia to Support Public Sector Growth (8 data centers, 1.9M sq ft, Sterling campus)
CyrusOne Inc. (Business Wire)Tier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page