Skip to content

Project File · Public records

Every public record we have for CyrusOne Sterling campus (Northern Virginia)

Loudoun County, VirginiaOperatingFirst public 2016Last checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

2 of 23 records · showing environmental permits only ·

2016

  • Air permitIssuedNov 1, 2016Virginia Department of Environmental Quality

    Virginia Department of Environmental Quality, Registration No. 74086

    Issued; stationary source permit to construct and operate emergency diesel engine generator sets; supersedes the permit dated April 1, 2016

    Backup generators:
    10 emergency diesel engine gen-sets to be constructed under the November 1, 2016 permit (MTU 16V4000G83, 2,250 ekW each)
    Backup generators:
    29 emergency diesel engine gen-sets permitted before November 1, 2016 and carried into this permit (28 MTU 16V4000G83 at 2,250 ekW each, plus 1 MTU house gen-set at 750 ekW)
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Transmittal letter, November 1, 2016, and attached permit cover sheet: CyrusOne Loudoun Tech Center, 21111 Ridgetop Circle, Sterling, VA 20166, Registration No. 74086, approved November 1, 2016; DEQ issued-permits list row: CyrusOne Loudoun Tech Center, 74086, 11/01/2016, Article 6 mNSR, Loudoun County

  • Air permitReplaced by a later filingApr 1, 2016Virginia Department of Environmental Quality

    Virginia Department of Environmental Quality, Registration No. 74086

    Issued; stationary source permit to construct and operate emergency diesel engine generator sets; superseded by the permit dated November 1, 2016

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Equipment List (p. 3) and transmittal letter of the November 1, 2016 permit for Registration No. 74086: the November permit supersedes the permit dated April 1, 2016, and its Equipment List carries the April permit's units (28 MTU 16V4000G83 at 2,250 ekW each plus one MTU 12V2000G85 TB house unit at 750 ekW); DEQ issued-permits list row: CyrusOne Loudoun Tech Center, 74086, 04/01/2016, Article 6 mNSR, Loudoun County

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Planning Commission Public Hearing Staff Report, SPEX-2016-0003, Cyrus One Loudoun Tech Center (May 24, 2016)
    Loudoun County Department of Planning and Zoning
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Capital Improvement Plan 2024-2033
    Loudoun Water
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Board of Supervisors Business Meeting Information Item I-3, Briefing Item: Land Development Applications, June 15, 2016 Public Hearing (June 7, 2016)
    Loudoun County Board of Supervisors
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Board of Supervisors Public Hearing, June 15, 2016, hearing video and captions (Granicus clip 4531)
    Loudoun County Board of Supervisors
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Stationary Source Permit to Construct and Operate, CyrusOne Loudoun Tech Center, Registration No. 74086 (November 1, 2016)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Issued Air Permits for Data Centers (list as of January 29, 2026)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Loudoun County Zoning Ordinance (official text, eReader)
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  8. 8
    Land Use Considerations (county data center page)
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  9. 9
    Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
    Dominion Energy Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  10. 10
    SCC Issues Order on DEV Biennial Review 2025
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-07 · Open the source
  11. 11
    Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
    Virginia Electric and Power Company
    Tier 1 · Captured 2026-11-07 · Open the source
  12. 12
    How the SCC Rider T1 Decision Protects Ratepayers
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  13. 13
    Order for Notice and Hearing, Case No. PUR-2026-00056
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  14. 14
    Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
    Loudoun County Planning Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  15. 15
    Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
    Loudoun County
    Tier 1 · Captured 2026-11-09 · Open the source
  16. 16
    Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
    Virginia Commission on Local Government (Department of Housing and Community Development)
    Tier 1 · Captured 2026-11-09 · Open the source
  17. 17
    Board of Supervisors Business Meeting Minutes, March 18, 2025
    Loudoun County
    Tier 1 · Captured 2026-11-07 · Open the source
  18. 18
    Loudoun County Board of Equalization 2025 Annual Report
    Loudoun County Board of Equalization
    Tier 1 · Captured 2026-11-09 · Open the source
  19. 19
    CyrusOne's New Data Center - Where Hyper Cloud Scale Meets Hyper Data Center Speed (Sterling II completion, 30 MW)
    CyrusOne Inc. (Business Wire)
    Tier 4 · Captured 2026-11-08 · Open the source
  20. 20
    CyrusOne Announces New Leadership in Northern Virginia to Support Public Sector Growth (8 data centers, 1.9M sq ft, Sterling campus)
    CyrusOne Inc. (Business Wire)
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page