Project File
NSA Utah Data Center
Bluffdale,Salt Lake County,UtahOperatingFirst public 2011Filing entity: National Security AgencyLast checked Nov 8, 2026
USACEBuilderNSAEnd user and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
NSA Utah Data Center is an operating data center project in Bluffdale, Salt Lake County, Utah. NSA is named as operator. It was first public in 2011. No site capacity figure is published for this project.
NSA Utah Data Center is an operating data center project in Bluffdale, Salt Lake County, Utah. NSA is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Bluffdale, Salt Lake County, Utah. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · New projectFirst public record of NSA Utah Data CenterOperating
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 507: Limits local incentives for large data centers outside development zones
The act covers large load data centers that are not located within a regionally significant development zone, for which a county or municipality may not offer an incentive, except project areas and agreements predating May 6, 2027; this project has no capacity figure on record, but whether this project is a large load data center, whether it is located within such a zone, and whether a county or municipality offered it an incentive is not on record.
“Except as provided in Subsection (1)(b), a county or municipality may not offer an incentive for a large load data center that is not located within a zone.” (Utah Code Sec. 63N-3a-402(1)(a))
Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 76: Requires data centers to report water use before and after building
The act covers large data centers, facilities with an annual water withdrawal of 75 acre feet per year or more whose buildings total at least 10,000 square feet; this project has no capacity figure on record, but the project's annual water withdrawal and its building area is not on record.
“"Large data center" means a facility with an annual water withdrawal of 75 acre feet per year or more that: (i) houses a group of networked server computers in one physical location to disseminate, manage, and store data and information as the primary service of the facility; (ii) consists of one or more buildings that in total equals or exceeds 10,000 square feet;” (Utah Code Sec. 73-5-8.3(1)(d), as enacted by H.B. 76, Section 2)
Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah SB 132: Sets cost and service rules for electric loads over 100 megawatts
The act covers large-scale service requests to a qualified electric utility, for new service expected to reach a cumulative demand of 100 megawatts or greater within five years, or added service expected to raise a customer's total by 100 megawatts or greater within five years; this project has no capacity figure on record, but whether this project has submitted a large-scale service request and its expected demand within five years of the requested start date is not on record.
“"Large-scale service request" means a request submitted to a qualified electric utility for: (a) new electric service that is expected to reach a cumulative demand of 100 megawatts or greater within five years of the requested initial start date; or (b) additional electric service that is expected to increase a customer's total service level by 100 megawatts or greater within five years of the requested start date for the additional electric service.” (Definitions enacting Utah Code Title 54, Chapter 26, S.B. 132 enrolled text)
Rule checks: Project is in Utah. Still to check: size: unknown, dates: not checked, who it covers: not checked
Bills and laws in Utah
- HB 76 · In effect · May 6, 2026Requires data centers to report water use before and after building
- HB 507 · Signed into law · Mar 25, 2026Limits local incentives for large data centers outside development zones
- SB 132 · In effect · May 7, 2025Sets cost and service rules for electric loads over 100 megawatts
Who's involved
Public records
12 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Pending before the commission · Sep 16, 2026PacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities
- Utility commission · Pending before the commission · Aug 19, 2026Amazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power
- Utility commission · Pending before the commission · Apr 28, 2026Division of Public Utilities' Request for an Investigatory Docket Regarding Rocky Mountain Power's Line Extension Policy for Large Loads
- Utility commission · Decided · Mar 19, 2026Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
- Utility commission · In effect · Jan 1, 2026Proposed Rulemaking Concerning Utah Code Sections 54-26-101 to -901, Large-Scale Electric Service Requirements
- Utility commission · In effect · Jan 1, 2026Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
- Utility commission · In effect · Jun 1, 2025Rocky Mountain Power Electric Service Schedule No. 400, Special Contracts (Wyoming)
- Utility commission · In effect · Feb 1, 2025Rocky Mountain Power Electric Service Schedule No. 400, Special Contract (Idaho)
Questions people ask
- Where is NSA Utah Data Center?
- NSA Utah Data Center is a data center project in Bluffdale, Salt Lake County, Utah.
- Who operates NSA Utah Data Center?
- NSA is named as the operator of NSA Utah Data Center.
- What stage is NSA Utah Data Center?
- NSA Utah Data Center is operating. It was first public in 2011.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
PacifiCorp d/b/a Pacific Power & Light CompanyTier 1 · Captured 2026-11-08 · Open the source - 2Settlement Stipulation, Docket No. 26-035-05, Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
Public Service Commission of Utah (filing by Rocky Mountain Power with the Division of Public Utilities and the Office of Consumer Services)Tier 1 · Captured 2026-11-08 · Open the source - 3Notice of Decisions on UAE motion and approval of the Settlement Stipulation, Docket No. 26-035-05
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 4Rocky Mountain Power advances Utah's Operation Gigawatt through landmark energy agreement
Rocky Mountain Power (PacifiCorp)Tier 4 · Captured 2026-11-08 · Open the source - 5Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 6Rocky Mountain Power Idaho Electric Service Schedule No. 400, Special Contract (I.P.U.C. No. 1, Thirteenth Revision of Sheet No. 400.1)
Rocky Mountain Power (PacifiCorp)Tier 1 · Captured 2026-11-08 · Open the source - 7Final Order No. 35277, Case No. PAC-E-21-07 (Rocky Mountain Power Idaho rate case)
Idaho Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 8Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 9Rocky Mountain Power Wyoming Electric Service Schedule No. 400, Special Contracts (P.S.C. Wyoming No. 19, Original Sheets 400-1 to 400-3)
Rocky Mountain Power (PacifiCorp)Tier 1 · Captured 2026-11-08 · Open the source - 10Public notice of Rocky Mountain Power application to establish Tariff Schedule 400, Special Contracts, Docket No. 20000-602-ET-21 (legal notice as published July 13, 2021)
Wyoming Public Service Commission (notice published in the Kemmerer Gazette)Tier 1 · Captured 2026-11-08 · Open the source - 11PacifiCorp Reply Testimony of Craig M. Eller, Oregon Docket No. UE 463, Exhibit PAC/200
PacifiCorpTier 1 · Captured 2026-11-08 · Open the source - 12Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 13Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
Utah State LegislatureTier 1 · Captured 2026-11-08 · Open the source - 14Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
Utah State LegislatureTier 1 · Captured 2026-11-08 · Open the source - 15PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 16Staff Opening Testimony (Staff/100), Docket UE 463
Staff of the Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 17Data Center Coalition Opening Testimony of Bieber, Docket UE 463
Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)Tier 1 · Captured 2026-11-08 · Open the source - 18Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
Staff of the Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 19Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
PacifiCorp d/b/a Pacific PowerTier 1 · Captured 2026-11-08 · Open the source - 20UTC Case Docket Detail Page, Docket UE-231037 (PacifiCorp, Advice 23-06)
Washington Utilities and Transportation CommissionTier 1 · Captured 2026-11-08 · Open the source - 21PacifiCorp Advice 23-06 cover letter and Rule 14 tariff sheets, Docket UE-231037
PacifiCorp d/b/a Pacific Power & Light Company (filed with the Washington Utilities and Transportation Commission)Tier 1 · Captured 2026-11-08 · Open the source - 22Alliance of Western Energy Consumers filing in Docket No. UE 463
Public Utility Commission of OregonTier 1 · Captured 2026-11-07 · Open the source - 23PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
Public Utility Commission of OregonTier 1 · Captured 2026-11-07 · Open the source - 24Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source - 25ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 26Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source - 27Groundbreaking Ceremony Held for $1.2 Billion Utah Data Center
National Security AgencyTier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page