Project File · Public records

Every public record we have for NSA Utah Data Center

Bluffdale, Salt Lake County, UtahOperatingFirst public 2011Filing entity: National Security AgencyLast checked Nov 8, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

12 of 12 records

2026

  • Utility proceedingDecidedFeb 10, 2026Public Service Commission of Utah

    Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer

    The first large load service contract approved under Utah's large load act (Utah Code Title 54, Chapter 26) and Utah Admin. Code R746-318-201, for a customer at 100 MW or greater; the customer's name and the contract's charge amounts are highly confidential in the public record. The approving settlement, among Rocky Mountain Power, the Division of Public Utilities, and the Office of Consumer Services, stipulates an accounting treatment designed so the contract results in no net cost increases to other Utah customers: the customer's coincident peak loads and energy are removed from the system energy and system generation allocation factors; system net power costs are reduced each hour by the customer's actual hourly energy use valued at the average CAISO Extended Day-Ahead Market locational marginal price near the load; all costs of the new resources and interim market purchases used to serve the customer are excluded from system cost of service and net power costs; and after the contract ends, none of those resource costs may enter cost of service without a separate Commission proceeding. The statutory approval findings are that the customer bears all just and reasonable incremental costs and existing ratepayers bear none of the costs attributable to the large load.

    26-035-05

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Settlement Stipulation, 2026-03-13, paragraphs 3 (filed 2026-02-10; first contract under the Act; 100 MW or greater) and 12 to 14 (accounting treatment; no net cost increase; post-term exclusion); Notice of Decisions, 2026-03-19 (stipulation approved at the March 17, 2026 hearing; explanatory orders to follow)

2025

  • Utility proceedingPending before the commissionOct 30, 2025Public Utility Commission of Oregon

    Amazon Data Services, Inc. v. PacifiCorp d/b/a Pacific Power

    Service complaint, not a tariff case, and it sets no rates or tariff terms. Amazon Data Services alleges in six claims that PacifiCorp failed to provide service it contracted to provide to four new ADS data center campuses in PacifiCorp’s exclusive service territory; the sixth claim asks, in the alternative, for removal of PacifiCorp’s exclusive service rights over those campuses under the Territory Allocation Law, ORS 758.400 to 758.480. The service terms are under protective order and no MW figure is public. An ALJ ruling on February 19, 2026 denied PacifiCorp’s partial motion to dismiss; the parties’ August 19, 2026 joint status report says settlement negotiations are ongoing. The UE 463 stipulation carves these campuses out of its New LEUF definition and leaves their status to this complaint proceeding.

    UM 2410

    Draft research, not yet verifiedLast checked Nov 11, 2026
    Where it says this

    ALJ Ruling, 2026-02-19, Introduction (complaint filed October 30, 2025; four campuses; six claims); Third Joint Status Report, 2026-08-19 (settlement negotiations ongoing, next report due September 18, 2026)

  • Utility proceedingPending before the commissionOct 2, 2025Public Utility Commission of Oregon

    PacifiCorp Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities

    Implements Oregon House Bill 3546 (2025), which requires a separate classification and tariff for large energy use facilities. A Large Energy Use Facility is a customer primarily engaged in data processing (NAICS 518210) with a load, or reserved capacity, of 20,000 kW or more, that had not contracted for service before June 16, 2025. Each facility signs a negotiated agreement under Schedule 401, subject to Commission approval, with a minimum term of 10 years and a maximum of 30 years including any ramp period, a minimum payment tied to Contract Demand, credit, deposit, and security requirements, and an exit fee set in the individual agreement. A stipulation filed September 16, 2026 by PacifiCorp, Commission Staff, the Citizens’ Utility Board and the Environmental Intervenors (the Data Center Coalition opposes it; AWEC, Amazon Data Services and Vitesse do not) would settle the case on these terms: a New LEUF is a facility that had not contracted before June 16, 2025, or whose contract requires $10 million or more of new transmission, distribution or generation investment after that date; an existing LEUF that raises contract demand by 10 MW or more without meeting that definition triggers a study filing in this docket; LEUF Agreements are filed within 45 days of execution, with 90 days for Commission review of a standard agreement and 180 days for a non-conforming one; network upgrades are paid upfront by the LEUF under Rule 13; the application fee is $25,000, nonrefundable; the exit fee covers the net book value of company-funded infrastructure, the net cost of customer-specific power and tolling agreements, a Reservation Charge for the rest of the contract, and removal costs, with a pro-rata refund if a new large customer takes the capacity within three years, and collateral is sized to the exit fee and reassessed every two years; and LEUFs over 100 MW pay a Community Energy Benefits Charge of 1 cent per kWh. Within 60 days after the UE 470 rate effective date PacifiCorp must file a new rate class for LEUFs not subject to Schedule 401.

    UE 463

    Draft research, not yet verifiedLast checked Nov 11, 2026
    Where it says this

    AWEC filing, 2026-03-03 (October 2, 2025 filing of Advice No. 25-015; HB 3546 purpose; conversion to UE 463); PacifiCorp surrebuttal testimony, 2026-07-28, and Exhibit PAC/301, Revised Schedule 401 (term, minimum payment, security, exit fee); Stipulation, filed 2026-09-16, paragraphs 1-3 (parties and DCC opposition), 15 ($10 million test), 16 (10 MW study trigger), 19-20 (filing and review), 21 (agreement terms, upfront network upgrades, exit fee), 23 ($25,000 fee), 24 and 31 (10 to 30 year term), 25 (new rate class), 26 (Community Energy Benefits Charge), 29 (collateral)

2024

  • Utility proceedingDecidedFeb 14, 2024Public Utility Commission of Oregon

    PacifiCorp Request for a General Rate Revision (2024 general rate case, very large customer charges)

    Order No. 24-447 set firm, initial requirements for very large load customers, meaning customers over 50,000 kW, so that under- and over-forecasting by very large new customers such as data centers does not shift power and transmission costs to other customers. A Capacity Reservation Charge of $3.68 per kW applies to the shortfall between a customer's actual peak demand and 90 percent of its reserved capacity (a 10 percent buffer). An Excess Demand Charge of three times the capacity reservation charge, $11.04 per kW, applies to demand above reserved capacity, with no buffer. A very large customer may not unilaterally reduce its reserved capacity by more than 50 MW or 10 percent per year, whichever is smaller. The two charges apply to short-term direct access customers but not to customers who have begun their five-year transition period. The charges are carried in Schedule 300. The case also set PacifiCorp's overall Oregon base rates, an increase of about 8.5 percent effective January 1, 2025. No minimum contract term, collateral amount or exit fee was adopted in the large load part of the order as read.

    UE 433

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    OPUC release of 2024-12-19 (UE 433 decision; Large Loads item); UE 463 Staff/100 testimony of 2026-05-14 citing Order No. 24-447 at 92 and 98 ($3.68 per kW, 10 percent buffer, three times excess charge); UE 430 Staff Report of 2025-04-04 summarizing the seven UE 433 issues (in excess of 50 MW; reduction limit of 50 MW or 10 percent per year; direct access applicability)

2023

  • Utility proceedingIn effectDec 21, 2023Washington Utilities and Transportation Commission

    PacifiCorp Advice 23-06, Rule 14 Line Extensions, Tariff WN U-76

    Rule 14 of Tariff WN U-76 sets PacifiCorp's Washington line extension allowances. As revised, the Extension Allowance for a nonresidential customer requiring 25,000 kW or more, or taking service at or above 46,000 volts, is limited to the cost of the metering equipment necessary to measure the customer's usage. Customers over 1,000 kW and under 25,000 kW keep the allowance formula in Rule 14 section III.B.2. PacifiCorp told the Commission the change creates uniformity with its other states, where transmission voltage customers already receive only the metering allowance, and that Oregon, Utah and Wyoming had approved similar large load limits. The Commission allowed the filing at its February 22, 2024 open meeting; it took effect February 23, 2024 and the docket is Closed. The filing states no minimum demand charge, contract term, collateral or exit fee.

    UE-231037

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    UTC docket detail page for UE-231037 (Advice 23-06; filed 12/21/2023; effective 02/23/2024; Allowed 02/22/2024; Closed); Advice 23-06 cover letter of 2023-12-21 and Rule 14 sections III.A and III.B.3 (25,000 kW or greater)

  • Utility proceedingIn effectAug 17, 2023Public Utility Commission of Oregon

    PacifiCorp Advice No. 23-016, Revision of Oregon Rule 13 Line Extension Policy

    Oregon Rule 13 sets PacifiCorp's line extension allowances. As revised, a customer requiring 25,000 kW or more receives no extension allowance above the cost of the metering equipment needed to measure its usage. Before the revision, an applicant over 1,000 kW taking delivery at secondary or primary voltage received an allowance based on the estimated annual revenue the applicant would generate. The Commission first approved Advice No. 23-016 subject to refund on September 25, 2023, then affirmed it on December 13, 2023 and ended the investigation and refund exposure. The same order directed PacifiCorp to change the long-run incremental cost study in its next general rate case so distribution voltage customers larger than 25,000 kW are not overallocated distribution and substation costs. The order states no minimum demand charge, contract term, collateral or exit fee.

    UE 424

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Order No. 23-472 (entered 2023-12-13), Staff Report section (Advice No. 23-016 filed 2023-08-17, docketed as ADV 1534; 25,000 kW allowance limit; September 25, 2023 interim approval under Order No. 23-344; LRIC study direction)

No date in the record(rules in force and undated records)

  • Utility proceedingIn effectNo date in the recordWashington Utilities and Transportation Commission

    Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)

    The standard Washington large service schedule. It applies to loads that have exceeded 999 kW in more than one month of any consecutive 18-month period, and stays applicable until the customer fails to exceed 999 kW for 36 consecutive months. Monthly billing is basic, load size, demand, energy and reactive power charges, adjusted under Schedule 80. Load size is the average of the two greatest non-zero monthly demands in the 12 months ending with the current month; load sizes up to 3,000 kW are Small and above 3,000 kW are Large. Current basic charges run from $1,176.57 per month (secondary, small) to $3,951.23 (primary dedicated facilities and transmission); on-peak demand charges run $8.92 to $11.05 per kW by delivery level. On-peak demand is the greater of the measured on-peak 15-minute maximum or 500 kW. The monthly minimum charge is the sum of the basic, load size and demand charges, unless a contract specifies a higher minimum. The company may require a written contract with a term of not less than one year. Customers over 30,000 kW served from a dedicated substation they site on their own land take the Primary Dedicated Facilities delivery level. Intermittent, partial requirements or highly fluctuating loads are served only by special contract, and partial requirements loads of 1,000 kW and over go to Schedule 47T.

    UE-250224

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Schedule 48T, Fifth Revision of Sheet No. 48T.1 (Applicable, Monthly Billing, Load Size note; issued 2025-12-23, effective 2026-01-01, Docket No. UE-250224) and Sheets No. 48T.2 and 48T.3 (Time Periods, Minimum Charge, Delivery Service including Primary Dedicated Facilities over 30,000 kW, On-Peak Demand 500 kW floor, Term of Contract; effective 2024-04-03, Docket No. UE-230172)

  • Utility proceedingPending before the commissionNo date in the recordPublic Service Commission of Utah

    Division of Public Utilities' Request for an Investigatory Docket Regarding Rocky Mountain Power's Line Extension Policy for Large Loads

    Investigatory docket into Rocky Mountain Power's line extension policy as it applies to large loads: what a large load customer must pay up front, and on what terms, for the facilities built to connect it. The Commission consolidated the docket with the SB 132 rulemaking, Docket No. 25-R318-01, held a scheduling conference on April 14, 2026, and is treating the contract reviews already running under Utah Admin. Code R746-318 as context for whether the rule and the line extension policy should change. No amended policy or order setting line extension terms for large loads had issued at the last document opened; the Commission solicited proposed amendments by June 16, 2026.

    24-035-43

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Notice of Comment Period, 2026-04-28, caption and paragraphs 1 to 4 (consolidated dockets; April 14, 2026 scheduling conference; investigation and survey under way)

  • Utility proceedingIn effectNo date in the recordIdaho Public Utilities Commission

    Rocky Mountain Power Electric Service Schedule No. 400, Special Contract (Idaho)

    A single-customer special contract schedule, not a generally available large load tariff. The sheet covers firm and interruptible retail service for all service required on the customer's premises, for a customer contracting for not less than 150,000 kW as of May 18, 2006, on the terms of the Electric Service Agreement between the customer and the Company as approved by the Commission. Published charges on the current sheet: firm energy 39.220 mills per kWh, firm demand $18.40 per kW, customer charge $1,834 per billing period; interruptible energy at the same mills rate with the demand charge reduced by an interruptible credit; excess reactive charge $0.96 per kVAR; replacement energy at an adjusted index price. All other contract terms sit in the individual Electric Service Agreement, which the sheet does not reproduce.

    PAC-E-24-04

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Schedule No. 400, Thirteenth Revision of Sheet No. 400.1 (purpose; availability at not less than 150,000 kW as of May 18, 2006; monthly charges), submitted under Case No. PAC-E-24-04, issued 2025-02-13, effective 2025-02-01; Final Order No. 35277 in Case No. PAC-E-21-07 (Contract, Schedule 400 listed among the schedules; a new Electric Service Agreement between Bayer and the Company in the conforming tariffs)

  • Utility proceedingIn effectNo date in the recordWyoming Public Service Commission

    Rocky Mountain Power Electric Service Schedule No. 400, Special Contracts (Wyoming)

    The Wyoming vehicle for large and special-contract service, under Wyo. Stat. 37-3-116. A customer qualifies with a minimum electric service load of 10,000 kW (delivery points in Wyoming may be aggregated under one entity) and must either show unique circumstances or characteristics of load, or a viable and competitive alternative energy source or business location. Every contract needs Commission approval before it takes effect. Contract terms must be expected to produce revenue exceeding the expected cost of serving the customer's projected use, must not obligate other customers for any investment or any direct, indirect, or reasonably assigned costs of serving the customer (power supply, transmission, distribution, and administrative costs included), and must provide benefits to other customers without imposing added current or future costs. The customer must agree to rates covering the cost of its service during the term and to reasonably contribute to fixed cost recovery, must provide adequate credit assurances, and pays a nonrefundable $5,000 application fee. Minimum contract standards: an initial term of at least three years, at least nine months written notice for any voluntary cancellation, and a significant consequence for material breach. The company keeps any profit or loss from a special contract, reports to the Commission at least once every three years on impacts to other customers, and contract terms may be kept confidential under the Commission's process.

    20000-671-ER-24

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Schedule 400, Sheets 400-1 to 400-3 (eligibility at 10,000 kW; Conditions of Service 1 to 10, including revenue over cost, no obligation of other customers, three-year minimum term, nine-month cancellation notice, credit assurances, $5,000 fee, triennial report); footer, Dkt. No. 20000-671-ER-24, issued 2025-07-16, effective 2025-06-01

  • Utility proceedingIn effectNo date in the recordPublic Service Commission of Utah

    Proposed Rulemaking Concerning Utah Code Sections 54-26-101 to -901, Large-Scale Electric Service Requirements

    Rulemaking that implements Senate Bill 132 (2025), codified at Utah Code Title 54, Chapter 26. The resulting rule, Utah Admin. Code R746-318, governs Commission approval of large load contracts: a large-scale service request is new service expected to reach a cumulative demand of 100 MW or greater within five years, or added service increasing a customer's total by 100 MW or greater within five years. An application for approval of a large load contract must be filed within 15 business days of execution, and the Commission approves or disapproves within 60 days. Before approval the Commission must find that the large load customer bears all just and reasonable incremental costs of the service and that existing ratepayers do not bear costs attributable to the large load. A contract with the qualified electric utility must allocate all large load incremental costs to the customer, require financial security sufficient to cover the customer's obligations, specify interconnection and delivery points, contracted capacity, term, and backup arrangements, identify the incremental generation resources used, address long-term operation and maintenance costs for large load facilities, and provide curtailment if demand exceeds contractually supported demand. The initial rule, effective January 1, 2026, does not set the large load flexible tariff directed by Utah Code 54-26-701 and does not decide transmission cost allocation; the Commission consolidated this docket with Docket No. 24-035-43, is surveying large load and flexible tariffs in other states, and expects to give flexible tariff guidance before the end of 2026, with stakeholder rule amendments due June 16, 2026.

    25-R318-01

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Notice of Comment Period, 2026-04-28, paragraphs 2 to 4 (R746-318 implemented at the beginning of this year; flexible tariff guidance before the end of 2026; amendments due 2026-06-16); CRA guidance memorandum, 2025-10-17 (rules to be published 2025-10-31, intended effective 2026-01-01; flexible tariff and cost allocation not addressed); Utah Code 54-26-101 (100 MW definitions) and 54-26-301 (contract requirements)

  • Utility proceedingIn effectNo date in the recordPublic Utility Commission of Oregon

    Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)

    The standard Oregon large service delivery schedule. It applies to loads that have registered 1,000 kW or more more than once in a preceding 18-month period, and stays applicable until the consumer fails to meet or exceed 1,000 kW for 36 consecutive months. Monthly billing is a Distribution Charge plus a Transmission and Ancillary Services Charge plus a System Usage Charge. Distribution Charge at secondary, primary and transmission voltage: basic charge $800, $1,130 or $1,750 per month for facility capacity up to 4,000 kW, and $2,210, $3,120 or $4,480 above 4,000 kW; facilities charge per kW of facility capacity; on-peak demand charge $6.28, $7.78 or $6.09 per kW. Facility capacity is the average of the two greatest non-zero monthly demands in the 12 months ending with the current month. The minimum monthly charge is the basic charge plus the facilities charge, and a higher minimum may be required by contract. The company may require a written contract with a term of not less than one year. A consumer with a load of 25,000 kW or greater that received only the metering extension allowance gets a customer funded substation credit of $1.43 per kW at primary voltage. Partial requirements loads of 1,000 kW and over are served under Schedule 47, not this schedule.

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Schedule 48, Sixth Revision of Sheets No. 48-1 and 48-2 (Available, Applicable, Monthly Billing, Facility Capacity, Minimum Charge, Customer Funded Substation, Term of Contract sections; Advice No. 24-024, Docket No. UE 433, effective 2025-01-01)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Votes and minutes

    Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
    PacifiCorp d/b/a Pacific Power & Light Company
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Settlement Stipulation, Docket No. 26-035-05, Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
    Public Service Commission of Utah (filing by Rocky Mountain Power with the Division of Public Utilities and the Office of Consumer Services)
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Notice of Decisions on UAE motion and approval of the Settlement Stipulation, Docket No. 26-035-05
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Rocky Mountain Power advances Utah's Operation Gigawatt through landmark energy agreement
    Rocky Mountain Power (PacifiCorp)
    Tier 4 · Captured 2026-11-08 · Open the source
  5. 5
    Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  6. 6
    Rocky Mountain Power Idaho Electric Service Schedule No. 400, Special Contract (I.P.U.C. No. 1, Thirteenth Revision of Sheet No. 400.1)
    Rocky Mountain Power (PacifiCorp)
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Final Order No. 35277, Case No. PAC-E-21-07 (Rocky Mountain Power Idaho rate case)
    Idaho Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  8. 8
    Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Rocky Mountain Power Wyoming Electric Service Schedule No. 400, Special Contracts (P.S.C. Wyoming No. 19, Original Sheets 400-1 to 400-3)
    Rocky Mountain Power (PacifiCorp)
    Tier 1 · Captured 2026-11-08 · Open the source
  10. 10
    Public notice of Rocky Mountain Power application to establish Tariff Schedule 400, Special Contracts, Docket No. 20000-602-ET-21 (legal notice as published July 13, 2021)
    Wyoming Public Service Commission (notice published in the Kemmerer Gazette)
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    PacifiCorp Reply Testimony of Craig M. Eller, Oregon Docket No. UE 463, Exhibit PAC/200
    PacifiCorp
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  13. 13
    Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
    Utah State Legislature
    Tier 1 · Captured 2026-11-08 · Open the source
  14. 14
    Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
    Utah State Legislature
    Tier 1 · Captured 2026-11-08 · Open the source
  15. 15
    PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  16. 16
    Staff Opening Testimony (Staff/100), Docket UE 463
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    Data Center Coalition Opening Testimony of Bieber, Docket UE 463
    Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
    PacifiCorp d/b/a Pacific Power
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    UTC Case Docket Detail Page, Docket UE-231037 (PacifiCorp, Advice 23-06)
    Washington Utilities and Transportation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  21. 21
    PacifiCorp Advice 23-06 cover letter and Rule 14 tariff sheets, Docket UE-231037
    PacifiCorp d/b/a Pacific Power & Light Company (filed with the Washington Utilities and Transportation Commission)
    Tier 1 · Captured 2026-11-08 · Open the source
  22. 22
    Alliance of Western Energy Consumers filing in Docket No. UE 463
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-07 · Open the source
  23. 23
    PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-07 · Open the source
  24. 24
    Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source
  25. 25
    ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy
  26. 26
    Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source
  27. 27
    Groundbreaking Ceremony Held for $1.2 Billion Utah Data Center
    National Security Agency
    Tier 1 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page