Novva West Jordan data center campus

West Jordan,Salt Lake County,UtahExpandingFirst public 2021Filing entity: Novva SLC Common, LLCLast checked Nov 9, 2026

NovvaDeveloper and operatorPacifiCorpElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

6 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Novva West Jordan data center campus is an expanding data center project in West Jordan, Salt Lake County, Utah. Novva is named as operator. It was first public in 2021. It was announced at 175 MW.

Novva West Jordan data center campus is an expanding data center project in West Jordan, Salt Lake County, Utah. Novva is named as operator. It was announced at 175 MW. All six of the core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in West Jordan, Salt Lake County, Utah. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

Novva West Jordan video · 2 min 19 sec

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

175 MWAnnounced capacity
22Public records we have found

For homeowners

What this project means if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    The city says this campus generates significant property tax revenue, but no tax figure for it is published.

    Comes to the community
  2. Tax breaks

    No tax break or incentive agreement for this campus appears in the state or city records we searched.

    Not known yet
  3. Money for schools and services

    No community payment, fee, or benefits agreement for this campus is in the records we searched.

    Not known yet
  4. Electricity bill

    Rocky Mountain Power serves the campus through a 200 MW on-site substation, and 72 gas engines now generate primary power for two buildings.

    Comes from the community
  5. Water

    The City of West Jordan supplies the campus's water; Novva posts its own bills, which show 144,000 gallons in one winter month.

    Comes from the community
  6. Jobs

    The city says the campus can be run by under 200 employees; no campus job count is published by the company.

    Comes to the community
  7. Next door: height, setbacks, noise

    State air rules cap backup generator testing at 42 hours a year, two engines at a time, between 7 a.m. and 7 p.m.

    Local rule
  8. Your say

    The power plant lot was approved in a public hearing on January 7, 2025, where no resident spoke and one commissioner abstained.

    How to take part
Aerial view of Novva West Jordan data center campus in West Jordan, Salt Lake County, Utah, captured 2021
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2021Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Salt Lake County, Utah.See every project on the map

The land, to scale

One football field
100 acres, about 76 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionCity of West Jordan: decided for Novva West Jordan data center campus
  2. · FilingFiled with City of West Jordan for Novva West Jordan data center campus
  3. · DecisionCIM Group and Novva Data Centers: Closed a new commitment of $2 billion in construction financing from J.P. Morgan and Starwood Property Trust to complete phases 2 and 3 of the West Jordan campus for Novva West Jordan data center campus
  4. · FilingFiled with CIM Group and Novva Data Centers for Novva West Jordan data center campus
  5. · DecisionCity of West Jordan: decided for Novva West Jordan data center campus
  6. · DecisionCity of West Jordan Planning and Zoning Commission: Preliminary Major Subdivision for Novva West Jordan Power Generation (2 lots on 27.65 acres) approved 5-0, with Commissioner Anderson abstaining and Commissioner Gonzalez absent for Novva West Jordan data center campusApplication #33294; parcel 26-10-276-005
  7. · DecisionUtah Division of Air Quality: Approval Order issued: modification to install 72 new natural gas-fired generator engines providing primary power for the two new data center buildings, with updates to the diesel emergency fleet; supersedes DAQE-AN160660001-22 (air permit) for Novva West Jordan data...DAQE-AN160660003-24 (Project N160660003)
  8. · FilingFiled with Utah Division of Air Quality: air permit for Novva West Jordan data center campusDAQE-IN160660003-24
All 11 events for this project

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 507: Limits local incentives for large data centers outside development zones

    The act covers large load data centers that are not located within a regionally significant development zone, for which a county or municipality may not offer an incentive, except project areas and agreements predating May 6, 2027; this project has 235.57 MW on record (generator capacity), but whether this project is a large load data center, whether it is located within such a zone, and whether a county or municipality offered it an incentive is not on record.

    “Except as provided in Subsection (1)(b), a county or municipality may not offer an incentive for a large load data center that is not located within a zone.” (Utah Code Sec. 63N-3a-402(1)(a))

    Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 76: Requires data centers to report water use before and after building

    The act covers large data centers, facilities with an annual water withdrawal of 75 acre feet per year or more whose buildings total at least 10,000 square feet; this project has 235.57 MW on record (generator capacity), but the project's annual water withdrawal and its building area is not on record.

    “"Large data center" means a facility with an annual water withdrawal of 75 acre feet per year or more that: (i) houses a group of networked server computers in one physical location to disseminate, manage, and store data and information as the primary service of the facility; (ii) consists of one or more buildings that in total equals or exceeds 10,000 square feet;” (Utah Code Sec. 73-5-8.3(1)(d), as enacted by H.B. 76, Section 2)

    Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah SB 132: Sets cost and service rules for electric loads over 100 megawatts

    The act covers large-scale service requests to a qualified electric utility, for new service expected to reach a cumulative demand of 100 megawatts or greater within five years, or added service expected to raise a customer's total by 100 megawatts or greater within five years; this project has 235.57 MW on record (generator capacity), but whether this project has submitted a large-scale service request and its expected demand within five years of the requested start date is not on record.

    “"Large-scale service request" means a request submitted to a qualified electric utility for: (a) new electric service that is expected to reach a cumulative demand of 100 megawatts or greater within five years of the requested initial start date; or (b) additional electric service that is expected to increase a customer's total service level by 100 megawatts or greater within five years of the requested start date for the additional electric service.” (Definitions enacting Utah Code Title 54, Chapter 26, S.B. 132 enrolled text)

    Rule checks: Project is in Utah; 200 MW on record (grid connection), threshold 100 MW (Definitions enacting Utah Code Title 54, Chapter 26, S.B. 132 enrolled text). Still to check: dates: not checked, who it covers: not checked

Bills and laws in Utah

Open Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 235.57 MW · Generator fleet (72 natural gas engines, primary power)Dec 2024 · generator_capacity
  • 76.87 MW · Generator fleet (diesel emergency generators)Dec 2024 · generator_capacity
  • 72 MW · Phase 3 (third data center building)Mar 2025 · it_load
  • 72 MW · Phase 2 (second data center building)Mar 2025 · it_load
  • 175 MW · Campus total (at completion, three buildings)Mar 2025 · what the figure measures is not stated
  • 200 MW · On-campus substation (utility grid connection)Nov 2026 · grid connection

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • CIM Group and Novva Data Centers

    Stated in the filing
    2,023 year
    Stated in the filing
    $2 billion
  • City of West Jordan

    Stated in the filing
    under 200 employees
  • City of West Jordan Planning and Zoning Commission, Application #33294; parcel 26-10-276-005

    Stated in the filing
    approximately 3500 square feet
    Stated in the filing
    27.65 acres
    Stated in the filing
    3 data center buildings
  • Novva Data Centers

    Stated in the filing
    394,667 gallons per month (company-stated average)
    Stated in the filing
    4 purpose-built data centers
    Stated in the filing
    100 acres
    Stated in the filing
    200 MW
    Stated in the filing
    1.18 PUE
  • Utah Division of Air Quality, DAQE-AN160660003-24 (Project N160660003)

    Stated in the filing
    37 engines
    Stated in the filing
    42 hours per rolling 12 months, per engine, outside emergencies
    Stated in the filing
    3,271.8 kW per engine
    Stated in the filing
    At most 2 engines at one time, tested only between 7:00 a.m. and 7:00 p.m.
    Stated in the filing
    DAQE-AN160660001-22, dated February 23, 2022
    Stated in the filing
    997,261 tons per year (total potential to emit)
    Stated in the filing
    Reclassified as a major CO and HAP source subject to Title V
    Stated in the filing
    411,485 m Easting; 4,491,982 m Northing; NAD83, UTM Zone 12
    Stated in the filing
    47 tons per year of NOx
    Stated in the filing
    72 engines
    Stated in the filing
    51.28 tons per year (total potential to emit)
    Stated in the filing
    Primary power for the two new data center buildings (phases 2 and 3)
  • Novva Data Centers

    Stated in the filing
    2021-09 month

Public records

22 records found so far. 6 kinds of record are still being collected.

See every record

All 12 court cases and commission dockets for this project

Questions people ask

Where is Novva West Jordan data center campus?
Novva West Jordan data center campus is a data center project in West Jordan, Salt Lake County, Utah.
Who operates Novva West Jordan data center campus?
Novva is named as the operator of Novva West Jordan data center campus.
How big is Novva West Jordan data center campus?
Novva West Jordan data center campus was announced at 175 MW of capacity. The site covers 100 acres.
What stage is Novva West Jordan data center campus?
Novva West Jordan data center campus is expanding. It was first public in 2021.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    CIM Group & Novva Data Centers Secure $2B to Expand Sustainable Data Centers in the Western U.S.
    CIM Group and Novva Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  2. 2
    West Jordan's $2B Data Boost: How NOVVA's Expansion Benefits You
    City of West Jordan
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Minutes of the Regular Meeting of the West Jordan Planning and Zoning Commission, January 7, 2025
    City of West Jordan (filed on the Utah Public Notice Website)
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    City of West Jordan utility billing statement, Novva Holdings, LLC account, service period Dec 9, 2024 - Jan 10, 2025
    City of West Jordan (posted by Novva Data Centers)
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    City of West Jordan utility billing statement, Novva Holdings, LLC account, service period Nov 14 - Dec 10, 2025
    City of West Jordan (posted by Novva Data Centers)
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Utah Data Center | Salt Lake City Colocation (West Jordan campus page)
    Novva Data Centers
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Intent to Approve DAQE-IN160660003-24: Modification to Approval Order DAQE-AN160660001-22 to Install New Power Generation Engines
    Utah Division of Air Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Approval Order DAQE-AN160660003-24: Modification to Approval Order DAQE-AN160660001-22 to Install New Power Generation Engines, Novva SLC Common, LLC - West Jordan Data Center
    Utah Division of Air Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Novva's Year in Review (Utah flagship grand opening, September 2021)
    Novva Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  10. 10
    Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
    PacifiCorp d/b/a Pacific Power & Light Company
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    Settlement Stipulation, Docket No. 26-035-05, Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
    Public Service Commission of Utah (filing by Rocky Mountain Power with the Division of Public Utilities and the Office of Consumer Services)
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Notice of Decisions on UAE motion and approval of the Settlement Stipulation, Docket No. 26-035-05
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  13. 13
    Rocky Mountain Power advances Utah's Operation Gigawatt through landmark energy agreement
    Rocky Mountain Power (PacifiCorp)
    Tier 4 · Captured 2026-11-08 · Open the source
  14. 14
    Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  15. 15
    Rocky Mountain Power Idaho Electric Service Schedule No. 400, Special Contract (I.P.U.C. No. 1, Thirteenth Revision of Sheet No. 400.1)
    Rocky Mountain Power (PacifiCorp)
    Tier 1 · Captured 2026-11-08 · Open the source
  16. 16
    Final Order No. 35277, Case No. PAC-E-21-07 (Rocky Mountain Power Idaho rate case)
    Idaho Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Rocky Mountain Power Wyoming Electric Service Schedule No. 400, Special Contracts (P.S.C. Wyoming No. 19, Original Sheets 400-1 to 400-3)
    Rocky Mountain Power (PacifiCorp)
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Public notice of Rocky Mountain Power application to establish Tariff Schedule 400, Special Contracts, Docket No. 20000-602-ET-21 (legal notice as published July 13, 2021)
    Wyoming Public Service Commission (notice published in the Kemmerer Gazette)
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    PacifiCorp Reply Testimony of Craig M. Eller, Oregon Docket No. UE 463, Exhibit PAC/200
    PacifiCorp
    Tier 1 · Captured 2026-11-08 · Open the source
  21. 21
    Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  22. 22
    Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
    Utah State Legislature
    Tier 1 · Captured 2026-11-08 · Open the source
  23. 23
    Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
    Utah State Legislature
    Tier 1 · Captured 2026-11-08 · Open the source
  24. 24
    PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  25. 25
    Staff Opening Testimony (Staff/100), Docket UE 463
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  26. 26
    Data Center Coalition Opening Testimony of Bieber, Docket UE 463
    Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)
    Tier 1 · Captured 2026-11-08 · Open the source
  27. 27
    Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  28. 28
    Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
    PacifiCorp d/b/a Pacific Power
    Tier 1 · Captured 2026-11-08 · Open the source
  29. 29
    UTC Case Docket Detail Page, Docket UE-231037 (PacifiCorp, Advice 23-06)
    Washington Utilities and Transportation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  30. 30
    PacifiCorp Advice 23-06 cover letter and Rule 14 tariff sheets, Docket UE-231037
    PacifiCorp d/b/a Pacific Power & Light Company (filed with the Washington Utilities and Transportation Commission)
    Tier 1 · Captured 2026-11-08 · Open the source
  31. 31
    Alliance of Western Energy Consumers filing in Docket No. UE 463
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-07 · Open the source
  32. 32
    PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-07 · Open the source
  33. 33
    Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source
  34. 34
    ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy
  35. 35
    Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source
  36. 36
    Banks Loan $2 Billion to Build a 100-Acre AI Data Center in Utah (CIM Group and Novva announcement, March 2025, republished)
    CIM Group and Novva Data Centers (via Dow Jones newswires)
    Tier 4 · Captured 2026-11-08 · Open the source
  37. 37
    Spanish Fork City Council meeting materials, August 18, 2026 (data center comparison appendix naming Novva West Jordan)
    City of Spanish Fork (filed on the Utah Public Notice Website)
    Tier 1 · Captured 2026-11-09 · Open the source