city Card
Data centers in West Jordan, Utah
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 7 data center projects in West Jordan, Utah as of November 2026: 6 operating and 1 expanding, totaling about 387 MW announced where a figure is published.
West Jordan has 7 tracked data centers. Their announced capacity totals about 387 MW where a figure is published. Of those, 6 operating and 1 expanding. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Novva West Jordan video · 2 min 19 sec
Data center projects in West Jordan
- Aligned Data Centers SLC-01 (West Jordan)
OperatingWest Jordan34 MW announced
- Aligned Data Centers SLC-02 (West Jordan)
OperatingWest Jordan48 MW announced
- Aligned Data Centers SLC-03 (West Jordan)
OperatingWest Jordan
- Aligned Salt Lake City Campus (SLC-01, SLC-02, SLC-03)
OperatingWest Jordan130 MW announced
- Flexential South Valley Data Center
OperatingWest Jordan
- Novva West Jordan data center campus
ExpandingWest Jordan175 MW announced
- Oracle West Jordan Data Center
OperatingWest Jordan
Who serves this place
- Not collected yet.
More places in Salt Lake County
West Jordan is part of Salt Lake County.
Nearby places
- Bluffdale8 data center projects tracked
- Salt Lake City4 data center projects tracked
- West Valley City3 data center projects tracked
- Millcreek1 data center project tracked
- South Jordan1 data center project tracked
For homeowners
What the projects here mean if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
Property tax
Novva West Jordan data center campus:The city says this campus generates significant property tax revenue, but no tax figure for it is published.
Comes to the community
Tax breaks
Novva West Jordan data center campus:No tax break or incentive agreement for this campus appears in the state or city records we searched.
Not known yet
Money for schools and services
Novva West Jordan data center campus:No community payment, fee, or benefits agreement for this campus is in the records we searched.
Not known yet
Electricity bill
Novva West Jordan data center campus:Rocky Mountain Power serves the campus through a 200 MW on-site substation, and 72 gas engines now generate primary power for two buildings.
Comes from the community
Water
Novva West Jordan data center campus:The City of West Jordan supplies the campus's water; Novva posts its own bills, which show 144,000 gallons in one winter month.
Comes from the community
Jobs
Novva West Jordan data center campus:The city says the campus can be run by under 200 employees; no campus job count is published by the company.
Comes to the community
Next door: height, setbacks, noise
Novva West Jordan data center campus:State air rules cap backup generator testing at 42 hours a year, two engines at a time, between 7 a.m. and 7 p.m.
Local rule
Your say
Novva West Jordan data center campus:The power plant lot was approved in a public hearing on January 7, 2025, where no resident spoke and one commissioner abstained.
How to take part
Tax breaks and payments
Aligned Salt Lake City Campus (SLC-01, SLC-02, SLC-03)
Tax increment financing (West Jordan City Redevelopment Agency, Fairchild project area)
60% of personal property tax increment to the redevelopment agency; 40% to the original taxing entities (Salt Lake County, Jordan School District, West Jordan City, South Salt Lake Valley Mosquito Abatement District, Jordan Valley Water Conservancy District, Central Utah Water Conservancy District, Salt Lake County Library). Project duration 10 years; activation year 2019.
All tax records for Aligned Salt Lake City Campus (SLC-01, SLC-02, SLC-03)Oracle West Jordan Data Center
Economic Development Tax Increment Financing (EDTIF) post-performance tax credit (Governor’s Office of Economic Opportunity)
Post-performance rebate of 30% of new state revenue over a 12-year term (2008-2020); GOED-estimated 100 jobs and $260,000,000 capital investment.
All tax records for Oracle West Jordan Data CenterOracle West Jordan Data Center
Tax increment financing (West Jordan City Redevelopment Agency, Economic Development Project Area #3 - Data Center)
85% of tax increment to the redevelopment agency; affected taxing entities: Salt Lake County, Jordan School District, West Jordan City, South Salt Lake Valley Mosquito Abatement District, Jordan Valley Water Conservancy District, Central Utah Water Conservancy District, Salt Lake County Library. Project duration 10 years; activation year 2008.
All tax records for Oracle West Jordan Data Center
Court cases and commission dockets in Utah (4)
Bills and laws in Utah
- HB 76 · In effect · May 6, 2026Requires data centers to report water use before and after building
- HB 507 · Signed into law · Mar 25, 2026Limits local incentives for large data centers outside development zones
- SB 132 · In effect · May 7, 2025Sets cost and service rules for electric loads over 100 megawatts
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Officials we track for West Jordan
The lawmakers and local officials whose recorded jurisdiction is West Jordan, with the bills and votes we have on record for each.
- Ammon AllenCommissioner
- Emily GonzalezCommissioner
- Jay ThomasCommissioner
- Jimmy AndersonCommissioner
- John RobertsCommissioner
- Tom HollingsworthCommissioner
- Trish HatchCommissioner
Questions people ask
- How many data centers are in West Jordan?
- Data Center Fact Check tracks 7 data center projects in West Jordan as of November 2026. Of those, 6 operating and 1 expanding.
- What is the biggest data center in West Jordan?
- By announced capacity, the biggest data center in West Jordan is Novva West Jordan data center campus, announced at 175 MW. It is expanding.
- How much power do data centers in West Jordan use?
- The 7 projects tracked in West Jordan have announced about 387 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1West Jordan's $2B Data Boost: How NOVVA's Expansion Benefits You
City of West JordanTier 1 · Open the source - 2Minutes of the Regular Meeting of the West Jordan Planning and Zoning Commission, January 7, 2025
City of West Jordan (filed on the Utah Public Notice Website)Tier 1 · Open the source - 3Approval Order DAQE-AN160660003-24: Modification to Approval Order DAQE-AN160660001-22 to Install New Power Generation Engines, Novva SLC Common, LLC - West Jordan Data Center
Utah Division of Air QualityTier 1 · Open the source - 4Utah Data Center | Salt Lake City Colocation (West Jordan campus page)
Novva Data CentersTier 1 · Open the source - 5City of West Jordan utility billing statement, Novva Holdings, LLC account, service period Dec 9, 2024 - Jan 10, 2025
City of West Jordan (posted by Novva Data Centers)Tier 1 · Open the source - 6City of West Jordan utility billing statement, Novva Holdings, LLC account, service period Nov 14 - Dec 10, 2025
City of West Jordan (posted by Novva Data Centers)Tier 1 · Open the source - 7CIM Group & Novva Data Centers Secure $2B to Expand Sustainable Data Centers in the Western U.S.
CIM Group and Novva Data CentersTier 4 · Open the source - 8Data center tax policy brief
Utah State Legislature (Kem C. Gardner Policy Institute)Tier 2 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "West Jordan." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ut-west-jordan
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page