Project File · Public records

Every public record we have for Aligned Salt Lake City Campus (SLC-01, SLC-02, SLC-03)

West Jordan, Salt Lake County, UtahOperatingFirst public 2019Filing entity: Aligned Data CentersLast checked Nov 8, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

1 of 14 records · showing tax breaks and payments only ·

No date in the record(rules in force and undated records)

  • Tax agreementNo date in the recordWest Jordan

    Tax increment financing (West Jordan City Redevelopment Agency, Fairchild project area)

    60% of personal property tax increment to the redevelopment agency; 40% to the original taxing entities (Salt Lake County, Jordan School District, West Jordan City, South Salt Lake Valley Mosquito Abatement District, Jordan Valley Water Conservancy District, Central Utah Water Conservancy District, Salt Lake County Library). Project duration 10 years; activation year 2019.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Table 3: Tax Increment Financing for Select Data Center Construction Projects (Aligned Energy/PayPal row)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Data center tax policy brief
    Utah State Legislature (Kem C. Gardner Policy Institute)
    Tier 2 · Captured 2026-11-08 · Open the source
  2. 2
    Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
    PacifiCorp d/b/a Pacific Power & Light Company
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Settlement Stipulation, Docket No. 26-035-05, Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
    Public Service Commission of Utah (filing by Rocky Mountain Power with the Division of Public Utilities and the Office of Consumer Services)
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Notice of Decisions on UAE motion and approval of the Settlement Stipulation, Docket No. 26-035-05
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Rocky Mountain Power advances Utah's Operation Gigawatt through landmark energy agreement
    Rocky Mountain Power (PacifiCorp)
    Tier 4 · Captured 2026-11-08 · Open the source
  6. 6
    Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Rocky Mountain Power Idaho Electric Service Schedule No. 400, Special Contract (I.P.U.C. No. 1, Thirteenth Revision of Sheet No. 400.1)
    Rocky Mountain Power (PacifiCorp)
    Tier 1 · Captured 2026-11-08 · Open the source
  8. 8
    Final Order No. 35277, Case No. PAC-E-21-07 (Rocky Mountain Power Idaho rate case)
    Idaho Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  10. 10
    Rocky Mountain Power Wyoming Electric Service Schedule No. 400, Special Contracts (P.S.C. Wyoming No. 19, Original Sheets 400-1 to 400-3)
    Rocky Mountain Power (PacifiCorp)
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    Public notice of Rocky Mountain Power application to establish Tariff Schedule 400, Special Contracts, Docket No. 20000-602-ET-21 (legal notice as published July 13, 2021)
    Wyoming Public Service Commission (notice published in the Kemmerer Gazette)
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    PacifiCorp Reply Testimony of Craig M. Eller, Oregon Docket No. UE 463, Exhibit PAC/200
    PacifiCorp
    Tier 1 · Captured 2026-11-08 · Open the source
  13. 13
    Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
    Public Service Commission of Utah
    Tier 1 · Captured 2026-11-08 · Open the source
  14. 14
    Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
    Utah State Legislature
    Tier 1 · Captured 2026-11-08 · Open the source
  15. 15
    Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
    Utah State Legislature
    Tier 1 · Captured 2026-11-08 · Open the source
  16. 16
    PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    Staff Opening Testimony (Staff/100), Docket UE 463
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Data Center Coalition Opening Testimony of Bieber, Docket UE 463
    Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
    Staff of the Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
    PacifiCorp d/b/a Pacific Power
    Tier 1 · Captured 2026-11-08 · Open the source
  21. 21
    UTC Case Docket Detail Page, Docket UE-231037 (PacifiCorp, Advice 23-06)
    Washington Utilities and Transportation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  22. 22
    PacifiCorp Advice 23-06 cover letter and Rule 14 tariff sheets, Docket UE-231037
    PacifiCorp d/b/a Pacific Power & Light Company (filed with the Washington Utilities and Transportation Commission)
    Tier 1 · Captured 2026-11-08 · Open the source
  23. 23
    Alliance of Western Energy Consumers filing in Docket No. UE 463
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-07 · Open the source
  24. 24
    PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-07 · Open the source
  25. 25
    Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source
  26. 26
    ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy
  27. 27
    Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
    Public Utility Commission of Oregon
    Tier 1 · Captured 2026-11-11 · Open the source
  28. 28
    Minutes of the Regular Meeting of the West Jordan Planning and Zoning Commission, January 7, 2025
    City of West Jordan (filed on the Utah Public Notice Website)
    Tier 1 · Captured 2026-11-09 · Open the source
  29. 29
    Salt Lake City Data Centers (SLC-01 to SLC-04)
    Aligned Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  30. 30
    Aligned Breaks Ground on Second Salt Lake Metro Data Center
    Aligned Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  31. 31
    Supply Chain Scale: Meeting the Need for Speed
    Aligned Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  32. 32
    Aligned Expands Campus with New Salt Lake Data Center (SLC-03)
    Aligned Data Centers (release carried by Utah Business)
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page