Project File

Capital One Knolls Campus

Glen Allen,Henrico County,VirginiaOperatingFiling entity: Capital One Services, Inc.Last checked Nov 10, 2026

Capital OneOperator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Capital One Knolls Campus is an operating data center project in Glen Allen, Henrico County, Virginia. Capital One is named as operator. No site capacity figure is published for this project.

Capital One Knolls Campus is an operating data center project in Glen Allen, Henrico County, Virginia. Capital One is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Glen Allen, Henrico County, Virginia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

7Public records we have found
5Backup generators, engine-generator sets

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Aerial view of Capital One Knolls Campus in Glen Allen, Henrico County, Virginia, captured 2023
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2023Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Henrico County, Virginia.See every project on the map

Timeline

  1. · DecisionVirginia Department of Environmental Quality: decided (air permit) for Capital One Knolls CampusRegistration 52281
  2. · DecisionVirginia Department of Environmental Quality: decided (air permit) for Capital One Knolls CampusRegistration 52281

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia HB 30: Budget act item taxing data center electricity at 1.1 cents per kWh

    The budget item taxes every data center operator on electricity consumed at each data center from July 1, 2026 to July 1, 2028 and defines a data center to include equipment for the transformation, transmission, distribution, or management of at least one megawatt of electrical power and cooling; this project is an operating data center in Virginia with a capacity figure over one megawatt on record, so every condition the text sets is met by a fact on record.

    “"Data center" means a facility whose primary services are to centralize the storage, management, and processing of digital data and is used to house (i) computer and network systems, including associated components such as servers, network equipment and appliances, telecommunications, and data storage systems; (ii) systems for monitoring and managing infrastructure performance; (iii) equipment used for the transformation, transmission, distribution, or management of at least one megawatt of capacity of electrical power and cooling, including substations, uninterruptible power supply systems, all electrical plant equipment, and associated air handlers; (iv) Internet-related equipment and services; (v) data communications connections; (vi) environmental controls; (vii) fire protection systems; and (viii) security systems and services. “Data center" does not include a facility whose primary function is to facilitate the provision of internet access service, a communication service as defined in § 58.1-647, or any combination thereof.” (Item 3-5.24, paragraph A.2 (HB 30, Chapter 1, Part 3))

    Rule checks: Project is in Virginia. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia HB 496: Requires monthly water use reports for data centers

    The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia with a DEQ air permit on record, so it falls in the reporting category the text sets.

    “Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (Chapter 623), § 62.1-44.38 C)

    Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia SB 553: Requires monthly water use reports for data centers

    The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia with a DEQ air permit on record, so it falls in the reporting category the text sets.

    “Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (conference substitute 26109885D, as passed), § 62.1-44.38 C)

    Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 1393: Shifts grid costs to the largest electricity customers

    The bill directs Dominion Energy Virginia to propose allocating capacity procurement and distribution infrastructure costs to its customer class with a contracted or measured demand of 25 megawatts or greater and an average load factor of 75 percent or greater, in rate proceedings commencing after January 1, 2027 and before July 1, 2033; this project's serving utility is not on record, so whether it is in Dominion Energy Virginia's customer class and what its contracted or measured demand and average load factor are is not on record.

    “Dominion Energy Virginia to propose to the Commission, in any proceeding to determine rates for generation and distribution services commencing after January 1, 2027, and before July 1, 2033, that certain costs related to capacity procurement requirements and distribution infrastructure investments are allocated to the utility's customer class approved to serve customers with a contracted or measured electric demand of 25 megawatts or greater and an anticipated or measured average annual electric load factor of 75 percent or greater” (LIS bill-details page for HB 1393 (2026), Summary)

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 153: Requires site assessments before local approval of large data centers

    The act covers new high energy use facilities, facilities an applicant reasonably anticipates at the time of filing a rezoning, special exception, or special use permit application will require 100 megawatts or more of electrical power from a retail electric utility, which require a site assessment before local approval; this project has 8.975 MW on record (generator capacity), but whether this project is a new facility seeking such a local approval and the electrical power anticipated for it at filing is not on record.

    “"high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.” (Va. Code Sec. 15.2-2209.4 A)

    Rule checks: Project is in Virginia. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 323: Directs a state study of data center waste heat

    The act directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth, convene a work group, and report by September 1, 2026; it sets no project-level condition on an individual data center, and whether this project's waste heat is within the work group's scope is not on record.

    “Directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth by making certain findings and recommendations and convening a work group to provide expertise, assistance, and feedback on the Department's efforts.” (LIS bill-details page for HB 323 (2026), Summary As Passed)

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 507: Sets Tier 4 generator emission limits in data center air permits

    The section bars the Department of Environmental Quality from issuing a data center permit on an application submitted on or after July 1, 2026 unless the emission limit for each gen-set is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set; this project has a DEQ air permit on record, but the submission date of any permit application on or after July 1, 2026 is not on record.

    “For any application submitted for a data center on or after July 1, 2026, for a permit issued by the Department pursuant to this chapter, including coverage under any general permit, the Department shall not issue such permit unless the emission limit for each gen-set established by such permit is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set.” (Va. Code Sec. 10.1-1322.6(B) (2026, c. 397))

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia SB 94: Requires site assessments before local approval of large data centers

    The section's site assessment duty turns on the electrical power a facility is anticipated to require from its retail electric utility, and no such figure is on record for this project; its on-record capacity is 8.975 MW of standby generator capacity, which does not measure power drawn from the utility.

    “"high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.” (Chapter 568 (2026 Acts of Assembly), new Code of Virginia section 15.2-2209.4, subsection A)

    Rule checks: Project is in Virginia. Still to check: size: unknown, who it covers: not checked

Bills and laws in Virginia

All 29 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 8.975 MW · Knolls 2 Data Center (4871 Cox Road)Jan 2026 · generator_capacity

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Virginia Department of Environmental Quality, Registration 52281

    Backup generators
    5 engine-generator sets

Public records

7 records found so far. 7 kinds of record are still being collected.

See every record

Questions people ask

Where is Capital One Knolls Campus?
Capital One Knolls Campus is a data center project in Glen Allen, Henrico County, Virginia.
Who operates Capital One Knolls Campus?
Capital One is named as the operator of Capital One Knolls Campus.
What stage is Capital One Knolls Campus?
Capital One Knolls Campus is operating.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Issued Air Permits for Data Centers (list as of January 29, 2026)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Virginia DEQ air permit, Capital One Services Inc, Registration 52281, administrative amendment January 22, 2026
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-10 · Open the source
  3. 3
    Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
    Dominion Energy Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  4. 4
    SCC Issues Order on DEV Biennial Review 2025
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-07 · Open the source
  5. 5
    Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
    Virginia Electric and Power Company
    Tier 1 · Captured 2026-11-07 · Open the source
  6. 6
    How the SCC Rider T1 Decision Protects Ratepayers
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Order for Notice and Hearing, Case No. PUR-2026-00056
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  8. 8
    Issued Air Permits for Data Centers, as of Oct. 26, 2026
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source · Archived copy
  9. 9
    EIA Form 861, Service Territory file, 2025 (final)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page