Data centers in Maryland
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 9 data center projects in Maryland as of November 2026: 4 under construction, 1 announced and 1 in permitting, totaling about 5,114 MW announced where a figure is published.
Maryland has 9 tracked data centers. Their announced capacity totals about 5,114 MW where a figure is published. Of those, 4 under construction, 1 announced and 1 in permitting. Every figure comes from the public record linked on this page.
Data center projects in Maryland
- Aligned Data Centers IAD-04 (Frederick)
OperatingAdamstown
- Aligned Frederick campus
Under constructionAdamstown264 MW announced
- Amazon Data Services Frederick campus
Under constructionAdamstown
- Brightseat Tech Park
PausedLandover820 MW announced
- Calvert Technology Center
CancelledLusby
- Chesapeake Data Campus
Announced1,000 MW announced
- Dickerson Data Center Campus
In permitting
- Quantum Frederick
Under constructionAdamstown2,400 MW announced
- Rowan Bauxite campus
Under constructionAdamstown630 MW announced
Who serves this place
- Not collected yet.
Counties and cities in Maryland
Counties
- Calvert County1 data center project tracked
- Charles County1 data center project tracked
- Frederick County5 data center projects tracked
- Montgomery County1 data center project tracked
- Prince George's County1 data center project tracked
Tax breaks and payments
Sales and use tax exemption (Md. Code, Tax-General Article Sec. 11-236; Chapter 640 of 2020)
The Maryland sales and use tax does not apply to the sale or lease of qualified data center personal property (computer equipment and enabling software, HVAC and mechanical systems, and electrical infrastructure including generators, transformers, and UPS systems) bought to establish or operate a data center certified by the Department of Commerce as a qualified data center. The Comptroller issues the exemption certificate after Commerce certifies the business; the certificate is renewed annually. The benefit period is 10 years, or 20 years for a business that invests at least $250 million in qualified data center personal property within 10 years of applying. Electricity used to operate the data center is not exempt.
Bills and laws in Maryland
- HB 1534 · Died or failedSets operating and siting standards for data centers
- HB 120 · Died or failedBans new data centers until co-location is required
- SB 116 · Veto overridden · Dec 16, 2025Requires a state study of data center impacts
Newswire for Maryland
What the record shows · November 22, 2026
31 data center projects cancelled, 9 paused: the stopped projects in the public record, one by one
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
Questions people ask
- How many data centers are in Maryland?
- Data Center Fact Check tracks 9 data center projects in Maryland as of November 2026. Of those, 4 under construction, 1 announced and 1 in permitting.
- What is the biggest data center in Maryland?
- By announced capacity, the biggest data center in Maryland is Quantum Frederick, announced at 2,400 MW. It is under construction.
- How much power do data centers in Maryland use?
- The 9 projects tracked in Maryland have announced about 5,114 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Data Center Maryland Sales and Use Tax Exemption Incentive Program
Maryland Department of CommerceTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Maryland." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-md
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page