Project File
Quantum Frederick
Adamstown,Frederick County,MarylandUnder constructionFirst public 2021Filing entity: Quantum Maryland, LLCLast checked Nov 8, 2026
Quantum LoopholeDeveloperCatellusDeveloper
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Quantum Frederick is a under-construction data center project in Adamstown, Frederick County, Maryland. Quantum Loophole is named as developer. It was first public in 2021. It was announced at 2,400 MW.
Quantum Frederick is an under-construction data center project in Adamstown, Frederick County, Maryland. Quantum Loophole is named as developer. It was announced at 2,400 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Adamstown, Frederick County, Maryland. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Quantum FrederickUnder construction
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Maryland SB 116: Requires a state study of data center impacts
The act covers data center development in Maryland, whose environmental, energy, and economic impacts state agencies must analyze; this project has 2,400 MW on record (not stated), but any project-level condition; the act directs state agencies to conduct a study and sets no size, date, or facility condition a project record could establish is not on record.
“Requiring the Department of the Environment, the Maryland Energy Administration, and the University of Maryland School of Business, in coordination with the Department of Legislative Services, to conduct an analysis of the likely environmental, energy, and economic impacts of data center development in the State” (mgaleg SB 116 page, Synopsis)
Rule checks: Project is in Maryland. Still to check: who it covers: not checked
Bills and laws in Maryland
- HB 1534 · Died or failedSets operating and siting standards for data centers
- HB 120 · Died or failedBans new data centers until co-location is required
- SB 116 · Veto overridden · Dec 16, 2025Requires a state study of data center impacts
Who's involved
- DeveloperQuantum Loophole
- DeveloperCatellus
Power
Capacity, as announced or filed
- 2,400 MW · Full campuswhat the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Quantum Frederick?
- Quantum Frederick is a data center project in Adamstown, Frederick County, Maryland.
- Who is developing Quantum Frederick?
- Quantum Loophole is named as the developer of Quantum Frederick.
- How big is Quantum Frederick?
- Quantum Frederick was announced at 2,400 MW of capacity. The site covers 2,100 acres.
- What stage is Quantum Frederick?
- Quantum Frederick is under construction. It was first public in 2021.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Frederick Data Center Sampling/Reports
Maryland Department of the EnvironmentTier 1 · Captured 2026-11-08 · Open the source - 2Hyperscale Data Center Campus
Catellus Development CorporationTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page