Data centers in Iowa

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 30 data center projects in Iowa as of November 2026: 9 operating, 7 under construction and 6 proposed, totaling about 2,013 MW announced where a figure is published.

Iowa has 30 tracked data centers. Their announced capacity totals about 2,013 MW where a figure is published. Of those, 9 operating, 7 under construction and 6 proposed. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.

30Data center projects we track

Data center projects in Iowa

Who serves this place

  • Not collected yet.

Counties and cities in Iowa

Counties

Cities and towns

For homeowners

What the projects here mean if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    • Google Council Bluffs data center campus:The campus's property taxes are partly abated for 20 years from 2022; no record we read states what it actually pays.

      Not known yet
    • Meta Altoona Data Center:No record we could reach states what this campus pays in property tax; its expansion value sits under a long local exemption.

      Not known yet
  2. Tax breaks

    • Meta Altoona Data Center:State records credit this campus with up to $26 million in tax benefits, plus a 20-year local property tax exemption on its 2019 expansion.

      Comes from the community
    • Google Council Bluffs data center campus:Council Bluffs approved a 20 year property tax abatement worth an estimated $16.6 million for Google's $600 million Southlands expansion.

      Comes from the community
  3. Money for schools and services

    • Google Council Bluffs data center campus:Google put $1.3 million with state and nonprofit partners into a 47 site water quality project in Iowa watersheds.

      Comes to the community
    • Meta Altoona Data Center:Meta reports more than $5.6 million in direct funding to Polk County-area schools and nonprofits, and 300-plus local grants and sponsorships since 2015.

      Comes to the community
  4. Electricity bill

    • Google Council Bluffs data center campus:MidAmerican Energy supplies Google's Iowa data centers, under a 2014 agreement for up to 407 megawatts of wind energy.

      Comes from the community
    • Meta Altoona Data Center:MidAmerican Energy serves this campus, which used 1,585,392 megawatt-hours in 2024 and is matched with 100 percent clean and renewable energy.

      Comes from the community
  5. Water

    • Meta Altoona Data Center:The City of Altoona supplies this campus's water and wastewater service; Meta reports withdrawing 242 megaliters in 2024.

      Comes from the community
    • Google Council Bluffs data center campus:Google reported its Council Bluffs campus consumed 1,346.0 million gallons in 2025, the most of any Google location that year.

      Comes from the community
  6. Jobs

    • Google Council Bluffs data center campus:Google committed to 31 new full time jobs in its 2022 expansion agreement, on top of the workforce already in Council Bluffs.

      Comes to the community
    • Meta Altoona Data Center:Meta reports more than 400 operational jobs supported on site, after state deals that required 31 new jobs each in 2013 and 2019.

      Comes to the community
  7. Next door: height, setbacks, noise

    • Google Council Bluffs data center campus:The campus runs under an Iowa air permit covering 361 backup diesel engines at its Bunge Avenue site, with state emission limits.

      Local rule
    • Meta Altoona Data Center:Its 112 backup diesel engines run under a state permit capping facility fuel use and emissions; no local noise rule is in our records.

      Not known yet
  8. Your say

    • Google Council Bluffs data center campus:Council Bluffs' council voted in October 2022 to back Google's state incentive application for the Bunge Avenue expansion.

      How to take part
    • Meta Altoona Data Center:The public could comment on this campus's 2024 air permit renewal; council votes behind its 2013 and 2019 incentive deals are not published online.

      How to take part

Tax breaks and payments

  • Sales and use tax refunds, data center businesses (Iowa Code Section 423.4)

    A data center business that does not qualify for the full exemption may instead claim a refund of 50 percent of the sales and use tax paid (the refund is computed at 5 percent of the sales price, half the state rate) on backup power generation fuel, electricity, computers, and equipment. The refund runs seven to ten years for a facility investing at least $10 million (at least $5 million for a rehabilitated building), and up to five years for a facility investing at least $1 million.

  • Sales and use tax exemption, data center businesses (Iowa Code Section 423.3(95))

    Exempts the sales price of computers and equipment necessary for the maintenance and operation of a data center business, and property directly or indirectly connected to them (including cooling systems and towers, power infrastructure such as exterior dedicated business-owned substations, backup power generation systems, battery systems, and racking systems, cabling, and trays), plus backup power generation fuel and electricity purchased for use by the data center business, from Iowa sales and use tax. As amended by House File 976 (signed June 6, 2025), the exemption for electricity and backup power generation fuel now expires: for a data center that began operating before June 6, 2025 it does not expire; for new construction or additions on or after that date in a city with a population over 30,000 it runs 10 years from the relevant new construction, and 15 years outside such a city. The exemption for computers and equipment has no expiration. House File 976 also made a data center business that leases its data center eligible, and built a registration, annual reporting, and exemption certificate system (certificates in use from February 1, 2026).

  • Property tax exemption, data center business property (Iowa Code Section 427.1(37))

    Exempts qualifying data center business property, the computers, equipment, and related infrastructure described in the Section 423.3(95) definition, from Iowa property tax. The exemption covers the specified equipment and infrastructure, not the land or the buildings. House File 976 (2025) expanded it to property in a data center leased by the entity operating the data center business.

  • 2019 · Meta Altoona Data Center

    Local property tax exemption under the Iowa High Quality Jobs Program (IEDA award 19-HQJPTC-025)

    IEDA's board authorized a local property tax exemption for the 2019 expansion at the City of Altoona's request on May 17, 2019, after the Altoona City Council approved a 20-year abatement on May 6, 2019 (IEDA's May 2019 announcement, read in republication; the announcement original and the council minutes were not retrieved, holders: IEDA and City Clerk, City of Altoona). The exemption percentage is not stated in any original record read this pass, so percent_abated and term are left to the announcement account in this summary rather than the structured fields. IEDA's FY2025 compliance report closes the award as successful with a maximum state tax benefit of $0: no new state incentives were part of this award.

    All tax records for Meta Altoona Data Center
  • 2022 · Google Council Bluffs data center campus

    Local property tax abatement under the Iowa High Quality Jobs program (joint City of Council Bluffs and Google LLC application to IEDA, authorized by City Resolution 22-256)

    Property tax abatement on a sliding scale of 80% down to 45% over the course of twenty years (Resolution 22-256). The city resolution is the local half of the HQJ award; the IEDA board approved the award on October 21, 2022 (news coverage of the board meeting; IEDA's own release not yet collected, holder: IEDA).

    All tax records for Google Council Bluffs data center campus
  • 2013 · Meta Altoona Data Center

    State tax benefits under the Iowa High Quality Jobs Program (IEDA award 13-HQJTC-040)

    High Quality Jobs tax benefits for the original campus project, approved by the IEDA Board on April 23, 2013, the day the project was announced. IEDA's FY2015 compliance report carries a $300,000,000 total project cost, $299,500,000 capital investment, and a $18,000,000 maximum tax benefit with 31 jobs at a $23.12 qualifying wage; IEDA's FY2025 report carries the same award as amended, at a $700,000,000 total project cost and a $26,000,000 maximum tax benefit, with 41 reported jobs and a completion date of March 31, 2023. The program as approved also carried a local property tax exemption component approved by the City of Altoona the same day (terms in the city record were not retrieved; holder: City Clerk, City of Altoona).

    All tax records for Meta Altoona Data Center
  • 2016 · Microsoft Project Osmium (West Des Moines)

    State tax benefits under the Iowa High Quality Jobs Program (IEDA award 17-HQJTC-006)

    Awarded for a West Des Moines project in Warren County. IEDA's FY2025 annual report carries a total project cost of $417,700,000 and 11 jobs for the award.

    All tax records for Microsoft Project Osmium (West Des Moines)
  • 2014 · Microsoft Project Alluvion (West Des Moines)

    State tax benefits under the Iowa High Quality Jobs Program (IEDA award 14-HQJTC-028)

    Awarded for a West Des Moines project. IEDA's FY2025 annual report carries a total project cost of $1,126,218,400 and 66 jobs for the award and shows it closed successful.

    All tax records for Microsoft Project Alluvion (West Des Moines)
  • 2017 · Apple Waukee data center

    State tax benefits under the Iowa High Quality Jobs Program (IEDA award 18-HQJTC-008)

    Awarded for the Waukee campus in Dallas County. IEDA's FY2025 annual report carries a total project cost of $1,375,000,000 and capital investment of $1,330,000,000 for the award, with a required completion date of August 31, 2027.

    All tax records for Apple Waukee data center
  • 2013 · Microsoft Project Mountain (West Des Moines)

    State tax benefits under the Iowa High Quality Jobs Program (IEDA award 13-HQJTC-046)

    Awarded for a West Des Moines project. IEDA's FY2025 annual report carries a total project cost of $679,141,818 for the award and shows it closed successful.

    All tax records for Microsoft Project Mountain (West Des Moines)

In the news

More stories about this place

Recent cases and dockets in Iowa

All 1 court cases and commission dockets in Iowa

Bills and laws in Iowa

Open Bill Watch

Newswire for Iowa

  1. What the record shows · November 22, 2026

    The Dalles has metered Google's water use for 20 years: 13,000 gallons in 2005, 548.7 million in 2025

  2. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  3. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

Questions people ask

How many data centers are in Iowa?
Data Center Fact Check tracks 30 data center projects in Iowa as of November 2026. Of those, 9 operating, 7 under construction and 6 proposed.
What is the biggest data center in Iowa?
By announced capacity, the biggest data center in Iowa is Tract Altoona Technology Park, announced at 1,000 MW. It is announced.
How much power do data centers in Iowa use?
The 30 projects tracked in Iowa have announced about 2,013 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

  1. 1
    Resolution No. 22-256 authorizing a joint application to the Iowa Economic Development Authority by the City of Council Bluffs and Google LLC for benefits under the High Quality Jobs Program
    City of Council Bluffs
    Tier 1 · Open the source
  2. 2
    Council Communication: Google LLC's application to the Iowa Economic Development Authority for financial assistance under the High Quality Jobs Program (City Council meeting, October 10, 2022)
    City of Council Bluffs
    Tier 1 · Open the source
  3. 3
    Iowa Economic Development Authority FY2025 Annual Report (report dated January 31, 2026)
    Iowa Economic Development Authority
    Tier 1 · Open the source
  4. 4
    Iowa Economic Development Authority 2015 Annual Report, Annual Report by Status (report dated January 1, 2015)
    Iowa Economic Development Authority
    Tier 1 · Open the source
  5. 5
    Google data centers: Iowa (Council Bluffs)
    Google
    Tier 4 · Open the source
  6. 6
    Altoona Data Center info sheet (Meta data centers site, current edition)
    Meta Platforms
    Tier 4 · Open the source
  7. 7
    Meta announces new expansion to Altoona campus (Meta data centers site, December 14, 2021)
    Meta Platforms
    Tier 4 · Open the source
  8. 8
    An Earth Day treat: lots of renewable energy for our Iowa data center (Google Green Blog, April 22, 2014)
    Google
    Tier 4 · Open the source
  9. 9
    Bringing New Wind to Iowa (Facebook newsroom post by Vincent Van Son, November 14, 2013)
    Meta Platforms (Facebook newsroom)
    Tier 4 · Open the source
  10. 10
    Meta 2025 Environmental Data Index
    Meta Platforms, Inc.
    Tier 4 · Open the source
  11. 11
    Title V Operating Permit 18-TV-007R1, Siculus, Inc., 100 Share Way, Altoona, IA 50009 (Iowa DNR Air Quality Bureau)
    Iowa Department of Natural Resources
    Tier 1 · Open the source
  12. 12
    Google 2025 Environmental Report (2024 data), Water use by data center location table
    Google
    Tier 4 · Open the source
  13. 13
    Google 2026 Environmental Report
    Google
    Tier 4 · Open the source
  14. 14
    Council Bluffs Water Works Annual Report 2024
    Council Bluffs Water Works
    Tier 1 · Open the source
  15. 15
    Council Bluffs Water Works Annual Report 2025 (Final with Audit)
    Council Bluffs Water Works
    Tier 1 · Open the source
  16. 16
    Title V Operating Permit 16-TV-002R1, Gable Corporation, 10420 Bunge Ave., Council Bluffs, IA 51503 (Iowa DNR Air Quality Bureau, issued September 7, 2021)
    Iowa Department of Natural Resources
    Tier 1 · Open the source
  17. 17
    Air Quality Permits Under Review (published February 29, 2024): draft Title V renewal for Siculus, Inc., Altoona
    Iowa Department of Natural Resources
    Tier 1 · Open the source
  18. 18
    The Tax Impact of Data Centers in Iowa
    Common Sense Institute Iowa
    Tier 2 · Open the source
  19. 19
    Fiscal Note, House File 976 (Department of Revenue Omnibus Tax), Division XII
    Iowa Legislative Services Agency
    Tier 1 · Open the source
  20. 20
    Immediate Iowa Tax Law Changes for Data Centers
    Nyemaster Goode P.C.
    Tier 3 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Iowa." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ia

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page