State Card
Data centers in Iowa
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 30 data center projects in Iowa as of November 2026: 9 operating, 7 under construction and 6 proposed, totaling about 2,013 MW announced where a figure is published.
Iowa has 30 tracked data centers. Their announced capacity totals about 2,013 MW where a figure is published. Of those, 9 operating, 7 under construction and 6 proposed. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Iowa
- Apple Waukee data center
Under constructionWaukee
- Cologix DSM1 (Des Moines)
OperatingDes Moines
- Cologix DSM2 (Des Moines)
OperatingDes Moines
- COPT Defense Van Meter data center site
AnnouncedVan Meter1,000 MW announced
- CyrusOne Council Bluffs data center
OperatingCouncil Bluffs
- Edged Ankeny data center
Under constructionAnkeny13 MW announced
- Edged Council Bluffs data center campus
Under constructionCouncil Bluffs
- Google Cedar Rapids data center (Big Cedar Industrial Center)
Under constructionCedar Rapids
- Google Council Bluffs data center campus
ExpandingCouncil Bluffs
- Google Palo data center
ProposedPalo
- LightEdge Altoona Campus
OperatingAltoona
- Meta Altoona Data Center
ExpandingAltoona
- Meta Davenport data center
ApprovedDavenport
- Microsoft Project Alluvion (West Des Moines)
OperatingWest Des Moines
- Microsoft Project Ginger East (West Des Moines)
Under constructionWest Des Moines
- Microsoft Project Ginger West (West Des Moines)
Under constructionWest Des Moines
- Microsoft Project Mountain (West Des Moines)
OperatingWest Des Moines
- Microsoft Project Osmium (West Des Moines)
OperatingWest Des Moines
- Microsoft Project Ruthenium (West Des Moines)
ProposedWest Des Moines
- Microsoft Van Meter data center (Vision Park)
AnnouncedVan Meter
- Microsoft Woodward data center
AnnouncedWoodward
- QTS Cedar Rapids (Cedar Rapids; listed as in development)
ProposedCedar Rapids
- QTS Cedar Rapids data center campus
Under constructionCedar Rapids
- QTS Clinton (Clinton; listed as in consideration)
Proposed
- QTS Clinton data center
ProposedClinton
- Salix data center project (MidAmerican Energy / Google)
ProposedSalix
- STRATACACHE Waterloo data center and network operations center
OperatingWaterloo
- Tract Altoona Technology Park
AnnouncedAltoona1,000 MW announced
- US Signal IA01 (Waukee)
OperatingWaukee
- Wahawk Power Waterloo data center
ApprovedWaterloo
Who serves this place
- Not collected yet.
Counties and cities in Iowa
Counties
- Black Hawk County2 data center projects tracked
- Clinton County2 data center projects tracked
- Dallas County6 data center projects tracked
- Linn County4 data center projects tracked
- Madison County1 data center project tracked
- Polk County9 data center projects tracked
- Pottawattamie County3 data center projects tracked
- Scott County1 data center project tracked
- Warren County1 data center project tracked
- Woodbury County1 data center project tracked
Cities and towns
- West Des Moines6 data center projects tracked
- Altoona3 data center projects tracked
- Cedar Rapids3 data center projects tracked
- Council Bluffs3 data center projects tracked
- Des Moines2 data center projects tracked
- Van Meter2 data center projects tracked
- Waterloo2 data center projects tracked
- Waukee2 data center projects tracked
- Ankeny1 data center project tracked
- Clinton1 data center project tracked
- Davenport1 data center project tracked
- Palo1 data center project tracked
- Salix1 data center project tracked
- Woodward1 data center project tracked
For homeowners
What the projects here mean if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
Property tax
Google Council Bluffs data center campus:The campus's property taxes are partly abated for 20 years from 2022; no record we read states what it actually pays.
Not known yetMeta Altoona Data Center:No record we could reach states what this campus pays in property tax; its expansion value sits under a long local exemption.
Not known yet
Tax breaks
Meta Altoona Data Center:State records credit this campus with up to $26 million in tax benefits, plus a 20-year local property tax exemption on its 2019 expansion.
Comes from the communityGoogle Council Bluffs data center campus:Council Bluffs approved a 20 year property tax abatement worth an estimated $16.6 million for Google's $600 million Southlands expansion.
Comes from the community
Money for schools and services
Google Council Bluffs data center campus:Google put $1.3 million with state and nonprofit partners into a 47 site water quality project in Iowa watersheds.
Comes to the communityMeta Altoona Data Center:Meta reports more than $5.6 million in direct funding to Polk County-area schools and nonprofits, and 300-plus local grants and sponsorships since 2015.
Comes to the community
Electricity bill
Google Council Bluffs data center campus:MidAmerican Energy supplies Google's Iowa data centers, under a 2014 agreement for up to 407 megawatts of wind energy.
Comes from the communityMeta Altoona Data Center:MidAmerican Energy serves this campus, which used 1,585,392 megawatt-hours in 2024 and is matched with 100 percent clean and renewable energy.
Comes from the community
Water
Meta Altoona Data Center:The City of Altoona supplies this campus's water and wastewater service; Meta reports withdrawing 242 megaliters in 2024.
Comes from the communityGoogle Council Bluffs data center campus:Google reported its Council Bluffs campus consumed 1,346.0 million gallons in 2025, the most of any Google location that year.
Comes from the community
Jobs
Google Council Bluffs data center campus:Google committed to 31 new full time jobs in its 2022 expansion agreement, on top of the workforce already in Council Bluffs.
Comes to the communityMeta Altoona Data Center:Meta reports more than 400 operational jobs supported on site, after state deals that required 31 new jobs each in 2013 and 2019.
Comes to the community
Next door: height, setbacks, noise
Google Council Bluffs data center campus:The campus runs under an Iowa air permit covering 361 backup diesel engines at its Bunge Avenue site, with state emission limits.
Local ruleMeta Altoona Data Center:Its 112 backup diesel engines run under a state permit capping facility fuel use and emissions; no local noise rule is in our records.
Not known yet
Your say
Google Council Bluffs data center campus:Council Bluffs' council voted in October 2022 to back Google's state incentive application for the Bunge Avenue expansion.
How to take partMeta Altoona Data Center:The public could comment on this campus's 2024 air permit renewal; council votes behind its 2013 and 2019 incentive deals are not published online.
How to take part
Tax breaks and payments
Sales and use tax refunds, data center businesses (Iowa Code Section 423.4)
A data center business that does not qualify for the full exemption may instead claim a refund of 50 percent of the sales and use tax paid (the refund is computed at 5 percent of the sales price, half the state rate) on backup power generation fuel, electricity, computers, and equipment. The refund runs seven to ten years for a facility investing at least $10 million (at least $5 million for a rehabilitated building), and up to five years for a facility investing at least $1 million.
Sales and use tax exemption, data center businesses (Iowa Code Section 423.3(95))
Exempts the sales price of computers and equipment necessary for the maintenance and operation of a data center business, and property directly or indirectly connected to them (including cooling systems and towers, power infrastructure such as exterior dedicated business-owned substations, backup power generation systems, battery systems, and racking systems, cabling, and trays), plus backup power generation fuel and electricity purchased for use by the data center business, from Iowa sales and use tax. As amended by House File 976 (signed June 6, 2025), the exemption for electricity and backup power generation fuel now expires: for a data center that began operating before June 6, 2025 it does not expire; for new construction or additions on or after that date in a city with a population over 30,000 it runs 10 years from the relevant new construction, and 15 years outside such a city. The exemption for computers and equipment has no expiration. House File 976 also made a data center business that leases its data center eligible, and built a registration, annual reporting, and exemption certificate system (certificates in use from February 1, 2026).
Property tax exemption, data center business property (Iowa Code Section 427.1(37))
Exempts qualifying data center business property, the computers, equipment, and related infrastructure described in the Section 423.3(95) definition, from Iowa property tax. The exemption covers the specified equipment and infrastructure, not the land or the buildings. House File 976 (2025) expanded it to property in a data center leased by the entity operating the data center business.
2019 · Meta Altoona Data Center
Local property tax exemption under the Iowa High Quality Jobs Program (IEDA award 19-HQJPTC-025)
IEDA's board authorized a local property tax exemption for the 2019 expansion at the City of Altoona's request on May 17, 2019, after the Altoona City Council approved a 20-year abatement on May 6, 2019 (IEDA's May 2019 announcement, read in republication; the announcement original and the council minutes were not retrieved, holders: IEDA and City Clerk, City of Altoona). The exemption percentage is not stated in any original record read this pass, so percent_abated and term are left to the announcement account in this summary rather than the structured fields. IEDA's FY2025 compliance report closes the award as successful with a maximum state tax benefit of $0: no new state incentives were part of this award.
All tax records for Meta Altoona Data Center2022 · Google Council Bluffs data center campus
Local property tax abatement under the Iowa High Quality Jobs program (joint City of Council Bluffs and Google LLC application to IEDA, authorized by City Resolution 22-256)
Property tax abatement on a sliding scale of 80% down to 45% over the course of twenty years (Resolution 22-256). The city resolution is the local half of the HQJ award; the IEDA board approved the award on October 21, 2022 (news coverage of the board meeting; IEDA's own release not yet collected, holder: IEDA).
All tax records for Google Council Bluffs data center campus2013 · Meta Altoona Data Center
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 13-HQJTC-040)
High Quality Jobs tax benefits for the original campus project, approved by the IEDA Board on April 23, 2013, the day the project was announced. IEDA's FY2015 compliance report carries a $300,000,000 total project cost, $299,500,000 capital investment, and a $18,000,000 maximum tax benefit with 31 jobs at a $23.12 qualifying wage; IEDA's FY2025 report carries the same award as amended, at a $700,000,000 total project cost and a $26,000,000 maximum tax benefit, with 41 reported jobs and a completion date of March 31, 2023. The program as approved also carried a local property tax exemption component approved by the City of Altoona the same day (terms in the city record were not retrieved; holder: City Clerk, City of Altoona).
All tax records for Meta Altoona Data Center2016 · Microsoft Project Osmium (West Des Moines)
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 17-HQJTC-006)
Awarded for a West Des Moines project in Warren County. IEDA's FY2025 annual report carries a total project cost of $417,700,000 and 11 jobs for the award.
All tax records for Microsoft Project Osmium (West Des Moines)2014 · Microsoft Project Alluvion (West Des Moines)
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 14-HQJTC-028)
Awarded for a West Des Moines project. IEDA's FY2025 annual report carries a total project cost of $1,126,218,400 and 66 jobs for the award and shows it closed successful.
All tax records for Microsoft Project Alluvion (West Des Moines)2017 · Apple Waukee data center
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 18-HQJTC-008)
Awarded for the Waukee campus in Dallas County. IEDA's FY2025 annual report carries a total project cost of $1,375,000,000 and capital investment of $1,330,000,000 for the award, with a required completion date of August 31, 2027.
All tax records for Apple Waukee data center2013 · Microsoft Project Mountain (West Des Moines)
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 13-HQJTC-046)
Awarded for a West Des Moines project. IEDA's FY2025 annual report carries a total project cost of $679,141,818 for the award and shows it closed successful.
All tax records for Microsoft Project Mountain (West Des Moines)
In the news
Voters across the country reject data centers
Iowa Capital Dispatch
Data centers are now the largest financial bet in US history
Iowa Capital Dispatch
Recent cases and dockets in Iowa
- Utility commission · DecidedInterstate Power and Light Company, individual customer rate service agreements for the Big Cedar Industrial Center data centers (Google and QTS), Cedar Rapids
Bills and laws in Iowa
- HF 976 · Signed into lawCaps data center tax exemptions at 10 or 15 years
- HF 2688 · Died or failedData centers must reinvest 5 percent of their tax breaks
- HF 2198 · Died or failedPublic disclosure of data center tax incentives
Newswire for Iowa
What the record shows · November 22, 2026
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
Questions people ask
- How many data centers are in Iowa?
- Data Center Fact Check tracks 30 data center projects in Iowa as of November 2026. Of those, 9 operating, 7 under construction and 6 proposed.
- What is the biggest data center in Iowa?
- By announced capacity, the biggest data center in Iowa is Tract Altoona Technology Park, announced at 1,000 MW. It is announced.
- How much power do data centers in Iowa use?
- The 30 projects tracked in Iowa have announced about 2,013 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Resolution No. 22-256 authorizing a joint application to the Iowa Economic Development Authority by the City of Council Bluffs and Google LLC for benefits under the High Quality Jobs Program
City of Council BluffsTier 1 · Open the source - 2Council Communication: Google LLC's application to the Iowa Economic Development Authority for financial assistance under the High Quality Jobs Program (City Council meeting, October 10, 2022)
City of Council BluffsTier 1 · Open the source - 3Iowa Economic Development Authority FY2025 Annual Report (report dated January 31, 2026)
Iowa Economic Development AuthorityTier 1 · Open the source - 4Iowa Economic Development Authority 2015 Annual Report, Annual Report by Status (report dated January 1, 2015)
Iowa Economic Development AuthorityTier 1 · Open the source - 5
- 6Altoona Data Center info sheet (Meta data centers site, current edition)
Meta PlatformsTier 4 · Open the source - 7Meta announces new expansion to Altoona campus (Meta data centers site, December 14, 2021)
Meta PlatformsTier 4 · Open the source - 8An Earth Day treat: lots of renewable energy for our Iowa data center (Google Green Blog, April 22, 2014)
GoogleTier 4 · Open the source - 9Bringing New Wind to Iowa (Facebook newsroom post by Vincent Van Son, November 14, 2013)
Meta Platforms (Facebook newsroom)Tier 4 · Open the source - 10
- 11Title V Operating Permit 18-TV-007R1, Siculus, Inc., 100 Share Way, Altoona, IA 50009 (Iowa DNR Air Quality Bureau)
Iowa Department of Natural ResourcesTier 1 · Open the source - 12Google 2025 Environmental Report (2024 data), Water use by data center location table
GoogleTier 4 · Open the source - 13
- 14
- 15Council Bluffs Water Works Annual Report 2025 (Final with Audit)
Council Bluffs Water WorksTier 1 · Open the source - 16Title V Operating Permit 16-TV-002R1, Gable Corporation, 10420 Bunge Ave., Council Bluffs, IA 51503 (Iowa DNR Air Quality Bureau, issued September 7, 2021)
Iowa Department of Natural ResourcesTier 1 · Open the source - 17Air Quality Permits Under Review (published February 29, 2024): draft Title V renewal for Siculus, Inc., Altoona
Iowa Department of Natural ResourcesTier 1 · Open the source - 18
- 19Fiscal Note, House File 976 (Department of Revenue Omnibus Tax), Division XII
Iowa Legislative Services AgencyTier 1 · Open the source - 20
Cite this page
Copy this citation when you reuse a figure or a finding from this page.