Data Center Fact Check tracks 6 data center projects in Dallas County, Iowa as of November 2026: 3 announced, 2 under construction and 1 operating, totaling about 1,000 MW announced where a figure is published.
Dallas County has 6 tracked data centers. Their announced capacity totals about 1,000 MW where a figure is published. Of those, 3 announced, 2 under construction and 1 operating. Every figure comes from the public record linked on this page.
Data center projects in Dallas County
- Apple Waukee data center
Under constructionWaukee
- COPT Defense Van Meter data center site
AnnouncedVan Meter1,000 MW announced
- Microsoft Project Ginger West (West Des Moines)
Under constructionWest Des Moines
- Microsoft Van Meter data center (Vision Park)
AnnouncedVan Meter
- Microsoft Woodward data center
AnnouncedWoodward
- US Signal IA01 (Waukee)
OperatingWaukee
Who serves this place
- Not collected yet.
A data center is proposed in Dallas County
3 projects here are at the announced or proposed stage. Before the hearing, the resident checklist walks through what to check: the proposal's documents, the local rules where you live, the tax agreement, and the recorded votes.
Places in and around Dallas County
Dallas County is part of Iowa.
Cities and towns
Nearby places
- Polk County9 data center projects tracked
- Linn County4 data center projects tracked
- Pottawattamie County3 data center projects tracked
- Black Hawk County2 data center projects tracked
- Clinton County2 data center projects tracked
- Madison County1 data center project tracked
- Scott County1 data center project tracked
- Warren County1 data center project tracked
- Woodbury County1 data center project tracked
Tax breaks and payments
2017 · Apple Waukee data center
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 18-HQJTC-008)
Awarded for the Waukee campus in Dallas County. IEDA's FY2025 annual report carries a total project cost of $1,375,000,000 and capital investment of $1,330,000,000 for the award, with a required completion date of August 31, 2027.
All tax records for Apple Waukee data center
Court cases and commission dockets in Iowa (1)
Bills and laws in Iowa
- HF 976 · Signed into lawCaps data center tax exemptions at 10 or 15 years
- HF 2688 · Died or failedData centers must reinvest 5 percent of their tax breaks
- HF 2198 · Died or failedPublic disclosure of data center tax incentives
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Dallas County?
- Data Center Fact Check tracks 6 data center projects in Dallas County as of November 2026. Of those, 3 announced, 2 under construction and 1 operating.
- What is the biggest data center in Dallas County?
- By announced capacity, the biggest data center in Dallas County is COPT Defense Van Meter data center site, announced at 1,000 MW. It is announced.
- How much power do data centers in Dallas County use?
- The 6 projects tracked in Dallas County have announced about 1,000 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Iowa Economic Development Authority FY2025 Annual Report (report dated January 31, 2026)
Iowa Economic Development AuthorityTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Dallas County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ia-dallas
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page