Project File
Microsoft Woodward data center
Woodward,Dallas County,IowaAnnouncedFirst public 2026Filing entity: Microsoft CorporationLast checked Nov 8, 2026
MicrosoftDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: First public date
- Still to confirm: Capacity
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Microsoft Woodward data center is an announced data center project in Woodward, Dallas County, Iowa. Microsoft is named as operator. It was first public in 2026. No site capacity figure is published for this project.
Microsoft Woodward data center is an announced data center project in Woodward, Dallas County, Iowa. Microsoft is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Woodward, Dallas County, Iowa. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Microsoft Woodward data centerAnnounced
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Iowa HF 976: Caps data center tax exemptions at 10 or 15 years
The act covers data center businesses whose backup power generation fuel is exempt only for the first ten years of operation of new construction completed, or additions made, on or after the effective date of the act, in a city with a population of more than thirty thousand; this project has no capacity figure on record, but the project's construction or addition completion date and the population of its city is not on record.
“For backup power generation fuel purchased by a data center business in connection with real property with new construction upon the property completed on or after the effective date of this division of this Act, or additions upon existing property on or after the effective date of this division of this Act, and such property is located entirely or in part within a city having a population of more than thirty thousand, according to the most recent decennial federal census, the first ten years of operation in connection with the new construction or addition upon the existing property.” (Division XII, section 73, amending section 423.3, subsection 95, paragraph a, subparagraph (2) (b) (ii))
Rule checks: Project is in Iowa. Still to check: who it covers: not checked
Bills and laws in Iowa
- HF 976 · Signed into lawCaps data center tax exemptions at 10 or 15 years
- HF 2688 · Died or failedData centers must reinvest 5 percent of their tax breaks
- HF 2198 · Died or failedPublic disclosure of data center tax incentives
Who's involved
- Developer and operatorMicrosoft
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Microsoft Woodward data center?
- Microsoft Woodward data center is a data center project in Woodward, Dallas County, Iowa.
- Who operates Microsoft Woodward data center?
- Microsoft is named as the operator of Microsoft Woodward data center.
- How big is Microsoft Woodward data center?
- The site covers 616 acres.
- What stage is Microsoft Woodward data center?
- Microsoft Woodward data center is announced. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Microsoft acquires 600 acres of land for data center in Woodward, Iowa
Data Center DynamicsTier 3 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page