Project File
Google Council Bluffs data center campus
Council Bluffs,Pottawattamie County,IowaExpandingFirst public 2007Filing entity: Google LLCLast checked Nov 9, 2026
GoogleDeveloper and operatorMidAmerican EnergyElectric utilityGable CorporationOther role
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Google Council Bluffs data center campus is an expanding data center project in Council Bluffs, Pottawattamie County, Iowa. Google is named as operator. It was first public in 2007. No site capacity figure is published for this project.
Google Council Bluffs data center campus is an expanding data center project in Council Bluffs, Pottawattamie County, Iowa. Google is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Council Bluffs, Pottawattamie County, Iowa. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
- Property tax
The campus's property taxes are partly abated for 20 years from 2022; no record we read states what it actually pays.
Not known yet - Tax breaks
Council Bluffs approved a 20 year property tax abatement worth an estimated $16.6 million for Google's $600 million Southlands expansion.
Comes from the community - Money for schools and services
Google put $1.3 million with state and nonprofit partners into a 47 site water quality project in Iowa watersheds.
Comes to the community - Electricity bill
MidAmerican Energy supplies Google's Iowa data centers, under a 2014 agreement for up to 407 megawatts of wind energy.
Comes from the community - Water
Google reported its Council Bluffs campus consumed 1,346.0 million gallons in 2025, the most of any Google location that year.
Comes from the community - Jobs
Google committed to 31 new full time jobs in its 2022 expansion agreement, on top of the workforce already in Council Bluffs.
Comes to the community - Next door: height, setbacks, noise
The campus runs under an Iowa air permit covering 361 backup diesel engines at its Bunge Avenue site, with state emission limits.
Local rule - Your say
Council Bluffs' council voted in October 2022 to back Google's state incentive application for the Bunge Avenue expansion.
How to take part
Newswire for Google Council Bluffs data center campus
What the record shows · November 22, 2026
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

Timeline
- · DecisionCity of Council Bluffs: Approved; the City declares Google LLC an eligible business for the High Quality Jobs Program and approves and supports its requests for state assistance, including the local property tax abatement for Google Council Bluffs data center campusResolution No. 22-256
- · Tax dealTax agreement approved: Local property tax abatement under the iowa high quality jobs program (joint city of council bluffs and google llc application to ieda, authorized by city resolution 22-256) for Google LLCProperty tax abatement on a sliding scale of 80% down to 45% over the course of twenty years (Resolution 22-256). The city resolution is the local half of the HQJ award; the IEDA board approved the award on October 21, 2022 (news coverag...
- · DecisionIowa Department of Natural Resources, Air Quality Bureau: Issued; five-year operating permit term September 7, 2021 through September 6, 2026 (renewal application deadline March 6, 2026) (air permit) for Google Council Bluffs data center campusTitle V Operating Permit 16-TV-002R1; Facility File (Plant) No. 78-01-121; EIQ No. 92-6982
- · New projectFirst public record of Google Council Bluffs data center campusExpanding
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Iowa HF 976: Caps data center tax exemptions at 10 or 15 years
The act covers data center businesses whose backup power generation fuel is exempt only for the first ten years of operation of new construction completed, or additions made, on or after the effective date of the act, in a city with a population of more than thirty thousand; this project has no capacity figure on record, but the project's construction or addition completion date and the population of its city is not on record.
“For backup power generation fuel purchased by a data center business in connection with real property with new construction upon the property completed on or after the effective date of this division of this Act, or additions upon existing property on or after the effective date of this division of this Act, and such property is located entirely or in part within a city having a population of more than thirty thousand, according to the most recent decennial federal census, the first ten years of operation in connection with the new construction or addition upon the existing property.” (Division XII, section 73, amending section 423.3, subsection 95, paragraph a, subparagraph (2) (b) (ii))
Rule checks: Project is in Iowa. Still to check: who it covers: not checked
Bills and laws in Iowa
- HF 976 · Signed into lawCaps data center tax exemptions at 10 or 15 years
- HF 2688 · Died or failedData centers must reinvest 5 percent of their tax breaks
- HF 2198 · Died or failedPublic disclosure of data center tax incentives
Who's involved
- Developer and operatorGoogle
- Electric utilityMidAmerican Energy
- Other roleGable Corporation
Power and water
Water, as reported by the operator
Council Bluffs, IA facility as named in the location table of Google's 2026 Environmental Report (2025 data)
- 2025 · Consumption: 1,346 Mgal
- 2025 · Discharge: 400.4 Mgal
- 2025 · Withdrawal: 1,746.4 Mgal
- 2024 · Consumption: 1,010.2 Mgal
- 2024 · Discharge: 400.1 Mgal
- 2024 · Withdrawal: 1,410.3 Mgal
From the filings
Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.
City of Council Bluffs, Resolution No. 22-256
- Stated in the filing
- $16.6 million
- Stated in the filing
- $600 million
- Stated in the filing
- $24 per hour
- Stated in the filing
- 31 full-time equivalent jobs
Iowa Department of Natural Resources, Air Quality Bureau, Title V Operating Permit 16-TV-002R1; Facility File (Plant) No. 78-01-121; EIQ No. 92-6982
- Stated in the filingEstimated
- 1,353,458 bhpSum of the permit-stated brake horsepower ratings of the 361 counted engines: 18x3,058 + 4x2,561 + 16x3,351 + 4x2,328 + 16x3,351 + 3x2,328 + 2x1,940 + 32x3,673 + 6x2,561 + 4x3,058 + 44x3,673 + 32x4,035 + 2x3,673 + 51x4,036 + 102x4,036 + 8x4,680 + 6x3,055 + 7x4,680 + 2,328 + 3,673 + 3,673 + 1,838 = 1,353,458 bhp. bhp is engine shaft power as the permit states it, not generator electrical (kWe) nameplate.
- Stated in the filing
- 3 units excluded from the generator fleet count: guardhouse emergency diesel engine (324 bhp, EP 1001) and two diesel fire pumps (237 bhp and 315 bhp, Fire Pump 1 and E-5-g-FP) units
- Backup generatorsEstimated
- 361 emergency diesel enginesCount of emergency diesel-fired IC engines in the permit for the facility at 10420 Bunge Ave: GIP groups 1, 2, 3A, 4, 5, 6A, 7, 8, 9, 10A, 11, 12A, 16, 17, 18, 19, 20, 21 plus four ungrouped units (150005, C_5_e, C_7_g, J1-3-f). Excludes the guardhouse emergency engine (324 bhp) and two diesel fire pumps (237 bhp and 315 bhp), which the permit lists outside the GIP groups; those three units are recorded in the fleet fact below. Group-by-group census is in the cov-031 notes file.
- Stated in the filingEstimated
- 49 cooling modulesEvaporative cooling modules permitted at the facility: 8 + 3 + 8 + 6 + 10 + 6 + 8 = 49 across the seven cooling groups. Consistent with the campus's evaporative-cooling water use in Google's environmental reports; the permit itself states no water volume.
- Stated in the filing
- 8,804,000 gallons per rolling 12-month period
Public records
3 records found so far. 6 kinds of record are still being collected.
See every recordQuestions people ask
- Where is Google Council Bluffs data center campus?
- Google Council Bluffs data center campus is a data center project in Council Bluffs, Pottawattamie County, Iowa.
- Who operates Google Council Bluffs data center campus?
- Google is named as the operator of Google Council Bluffs data center campus.
- What stage is Google Council Bluffs data center campus?
- Google Council Bluffs data center campus is expanding. It was first public in 2007.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Council Communication: Google LLC's application to the Iowa Economic Development Authority for financial assistance under the High Quality Jobs Program (City Council meeting, October 10, 2022)
City of Council BluffsTier 1 · Captured 2026-11-09 · Open the source - 2Resolution No. 22-256 authorizing a joint application to the Iowa Economic Development Authority by the City of Council Bluffs and Google LLC for benefits under the High Quality Jobs Program
City of Council BluffsTier 1 · Captured 2026-11-09 · Open the source - 3Title V Operating Permit 16-TV-002R1, Gable Corporation, 10420 Bunge Ave., Council Bluffs, IA 51503 (Iowa DNR Air Quality Bureau, issued September 7, 2021)
Iowa Department of Natural ResourcesTier 1 · Captured 2026-11-09 · Open the source - 4Google Plans $600M Expansion for Iowa Data Hub (IEDA incentive approval, 2022-10-26)
GlobeStTier 3 · Captured 2026-11-08 · Open the source - 5An Earth Day treat: lots of renewable energy for our Iowa data center (Google Green Blog, April 22, 2014)
GoogleTier 4 · Captured 2026-11-09 · Open the source - 6Council Bluffs Water Works Annual Report 2024
Council Bluffs Water WorksTier 1 · Captured 2026-11-09 · Open the source - 7Council Bluffs Water Works Annual Report 2025 (Final with Audit)
Council Bluffs Water WorksTier 1 · Captured 2026-11-09 · Open the source - 8
- 9Google 2025 Environmental Report (2024 data), Water use by data center location table
GoogleTier 4 · Captured 2026-11-09 · Open the source - 10
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page