city Card
Data centers in West Des Moines, Iowa
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 6 data center projects in West Des Moines, Iowa as of November 2026: 3 operating, 2 under construction and 1 proposed.
West Des Moines has 6 tracked data centers. Of those, 3 operating, 2 under construction and 1 proposed. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in West Des Moines
- Microsoft Project Alluvion (West Des Moines)
OperatingWest Des Moines
- Microsoft Project Ginger East (West Des Moines)
Under constructionWest Des Moines
- Microsoft Project Ginger West (West Des Moines)
Under constructionWest Des Moines
- Microsoft Project Mountain (West Des Moines)
OperatingWest Des Moines
- Microsoft Project Osmium (West Des Moines)
OperatingWest Des Moines
- Microsoft Project Ruthenium (West Des Moines)
ProposedWest Des Moines
Who serves this place
- Not collected yet.
More places in Polk County
West Des Moines is part of Polk County.
Nearby places
- Altoona3 data center projects tracked
- Des Moines2 data center projects tracked
- Ankeny1 data center project tracked
Tax breaks and payments
2016 · Microsoft Project Osmium (West Des Moines)
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 17-HQJTC-006)
Awarded for a West Des Moines project in Warren County. IEDA's FY2025 annual report carries a total project cost of $417,700,000 and 11 jobs for the award.
All tax records for Microsoft Project Osmium (West Des Moines)2014 · Microsoft Project Alluvion (West Des Moines)
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 14-HQJTC-028)
Awarded for a West Des Moines project. IEDA's FY2025 annual report carries a total project cost of $1,126,218,400 and 66 jobs for the award and shows it closed successful.
All tax records for Microsoft Project Alluvion (West Des Moines)2013 · Microsoft Project Mountain (West Des Moines)
State tax benefits under the Iowa High Quality Jobs Program (IEDA award 13-HQJTC-046)
Awarded for a West Des Moines project. IEDA's FY2025 annual report carries a total project cost of $679,141,818 for the award and shows it closed successful.
All tax records for Microsoft Project Mountain (West Des Moines)
Court cases and commission dockets in Iowa (1)
Bills and laws in Iowa
- HF 976 · Signed into lawCaps data center tax exemptions at 10 or 15 years
- HF 2688 · Died or failedData centers must reinvest 5 percent of their tax breaks
- HF 2198 · Died or failedPublic disclosure of data center tax incentives
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in West Des Moines?
- Data Center Fact Check tracks 6 data center projects in West Des Moines as of November 2026. Of those, 3 operating, 2 under construction and 1 proposed.
Sources
- 1Iowa Economic Development Authority FY2025 Annual Report (report dated January 31, 2026)
Iowa Economic Development AuthorityTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "West Des Moines." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ia-west-des-moines
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page