Google Cedar Rapids data center (Big Cedar Industrial Center)
Cedar Rapids,Linn County,IowaUnder constructionFirst public 2024Filing entity: Heaviside LLCLast checked Nov 8, 2026
GoogleDeveloper and operatorAlliant EnergyElectric utilityCity of Cedar RapidsPublic partner
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Google Cedar Rapids data center (Big Cedar Industrial Center) is a under-construction data center project in Cedar Rapids, Linn County, Iowa. Google is named as operator. It was first public in 2024. No site capacity figure is published for this project.
Google Cedar Rapids data center (Big Cedar Industrial Center) is an under-construction data center project in Cedar Rapids, Linn County, Iowa. Google is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Cedar Rapids, Linn County, Iowa. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · New projectFirst public record of Google Cedar Rapids data center (Big Cedar Industrial Center)Under construction
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Iowa HF 976: Caps data center tax exemptions at 10 or 15 years
The act covers data center businesses whose backup power generation fuel is exempt only for the first ten years of operation of new construction completed, or additions made, on or after the effective date of the act, in a city with a population of more than thirty thousand; this project has no capacity figure on record, but the project's construction or addition completion date and the population of its city is not on record.
“For backup power generation fuel purchased by a data center business in connection with real property with new construction upon the property completed on or after the effective date of this division of this Act, or additions upon existing property on or after the effective date of this division of this Act, and such property is located entirely or in part within a city having a population of more than thirty thousand, according to the most recent decennial federal census, the first ten years of operation in connection with the new construction or addition upon the existing property.” (Division XII, section 73, amending section 423.3, subsection 95, paragraph a, subparagraph (2) (b) (ii))
Rule checks: Project is in Iowa. Still to check: who it covers: not checked
Bills and laws in Iowa
- HF 976 · Signed into lawCaps data center tax exemptions at 10 or 15 years
- HF 2688 · Died or failedData centers must reinvest 5 percent of their tax breaks
- HF 2198 · Died or failedPublic disclosure of data center tax incentives
Who's involved
- Developer and operatorGoogle
- Electric utilityAlliant Energy
- Public partnerCity of Cedar Rapids
Public records
1 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
Questions people ask
- Where is Google Cedar Rapids data center (Big Cedar Industrial Center)?
- Google Cedar Rapids data center (Big Cedar Industrial Center) is a data center project in Cedar Rapids, Linn County, Iowa.
- Who operates Google Cedar Rapids data center (Big Cedar Industrial Center)?
- Google is named as the operator of Google Cedar Rapids data center (Big Cedar Industrial Center).
- What stage is Google Cedar Rapids data center (Big Cedar Industrial Center)?
- Google Cedar Rapids data center (Big Cedar Industrial Center) is under construction. It was first public in 2024.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Iowa's Electricity Affordability Divide: What Alliant's Rates and the Data Center Boom Mean for Iowa Consumers
Clean Energy Districts of IowaTier 2 · Captured 2026-11-08 · Open the source - 2Cedar Rapids City Council Resolution 0226-02-24 approving the Google project development agreement (Big Cedar Industrial Center)
City of Cedar RapidsTier 1 · Captured 2026-11-08 · Open the source - 3Alliant Energy news release: Google investment at Big Cedar Industrial Center, Cedar Rapids
Alliant EnergyTier 4 · Captured 2026-11-08 · Open the source - 4City of Cedar Rapids news item on the Google data center at Big Cedar Industrial Center
City of Cedar RapidsTier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page