Data centers in Arkansas
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 7 data center projects in Arkansas as of November 2026: 3 under construction, 2 approved and 1 announced, totaling about 1,652 MW announced where a figure is published.
Arkansas has 7 tracked data centers. Their announced capacity totals about 1,652 MW where a figure is published. Of those, 3 under construction, 2 approved and 1 announced. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Arkansas
- AVAIO Digital Leo data center and power campus, Pulaski County
Under constructionLittle Rock1,070 MW announced
- Forgelight Ventures data center, Conway
ApprovedConway
- Google data center campus, West Memphis
Under constructionWest Memphis
- Serverfarm data center campus, Clarksville (ARK)
Under constructionClarksville432 MW announced
- TierPoint data center, Little Rock
OperatingLittle Rock
- Willowbend Capital data center, Little Rock Port
ApprovedLittle Rock
- Z Squared Union County Campus, El Dorado
AnnouncedEl Dorado150 MW announced
Who serves this place
- Not collected yet.
Counties and cities in Arkansas
Counties
- Crittenden County1 data center project tracked
- Faulkner County1 data center project tracked
- Johnson County1 data center project tracked
- Pulaski County3 data center projects tracked
- Union County1 data center project tracked
Cities and towns
- Little Rock3 data center projects tracked
- Clarksville1 data center project tracked
- Conway1 data center project tracked
- El Dorado1 data center project tracked
- West Memphis1 data center project tracked
Tax breaks and payments
2023
Sales and use tax exemption (Ark. Code Ann. Section 26-52-456)
The gross receipts tax and the compensating use tax do not apply to: data center equipment; eligible data center costs (development, acquisition, construction, expansion, renovation, refurbishment, and operation, including land, buildings, and lease payments); services purchased for developing, acquiring, constructing, expanding, renovating, refurbishing, and operating a qualified data center; and electricity used by a qualified data center.
2025 · Willowbend Capital data center, Little Rock Port
Payment in lieu of taxes under memorandum of understanding (City of Little Rock)
City support for a net real and personal property tax abatement of at least 65 percent for 30 years for the data center and each additional data center facility, delivered through bond structures (buildout periods of at least 30 years; investment caps of at least $10 billion real property and $50 billion personal property); electric franchise fee reduced to 0.25 percent; water franchise fee to 0 percent; sewer franchise fee to 0 percent; standard permit fees capped at $200,000 per data center.
All tax records for Willowbend Capital data center, Little Rock Port
Recent cases and dockets in Arkansas
- Utility commission · DecidedEntergy Arkansas, LLC application for a public interest finding and approval of a 20-year power purchase agreement for the Big Island Solar facility (Mississippi County)
- Utility commission · DecidedIN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, LLC FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED FOR CONSTRUCTION AND RELATED FINDINGS AND APPROVALS OF A SOLAR GENERATING AND BATTERY ENERGY STORAGE SYSTEM FACILITY, AND OTHER FACILITIES IN JEFFERSON COUNTY, ARKANSAS
- Utility commission · DecidedIN THE MATTER OF ENTERGY ARKANSAS, LLC’S APPLICATION FOR APPROVAL TO ENTER INTO A SPECIAL RATE CUSTOMER CONTRACT AND FOR ALL OTHER RELATED APPROVALS
- Utility commission · DecidedIN THE MATTER OF ENTERGY ARKANSAS, LLC’S STRATEGIC INVESTMENT RECOVERY RIDER
- Utility commission · Pending before the commissionIN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, LLC’S GENERATING ARKANSAS JOBS ACT ANNUAL UPDATES
Bills and laws in Arkansas
- HR 1013 · Died or failed · Apr 29, 2026Would have authorized a 2026 bill rewriting the Data Centers Act mining rules
- SB 11 · Died or failed · May 5, 2025Amends the Data Centers Act and money services law
- SB 10 · Died or failed · May 5, 2025Lets state agencies halt mining operations over water and grid harm
- HB 1444 · Signed into law · Apr 10, 2025Cuts the data center tax exemption investment threshold to $100 million
- SB 78 · Signed into law · May 3, 2024Sets mining noise rules and bars prohibited foreign parties from owning Arkansas mining businesses
- SB 79 · Signed into law · May 3, 2024Creates Oil and Gas Commission permitting for digital asset mining businesses
- HB 1476 · Died or failed · May 1, 2023Would have exempted electricity sold to a data center from sales and use tax
- HB 1477 · Died or failed · May 1, 2023Would have exempted certain data centers from storm recovery costs and charges
- HB 1654 · Signed into law · Apr 13, 2023Creates the data center sales and use tax exemption
- HB 1799 · Signed into law · Apr 13, 2023Creates the Arkansas Data Centers Act of 2023
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Officials we track for Arkansas
The lawmakers and local officials whose recorded jurisdiction is Arkansas, with the bills and votes we have on record for each.
- Aaron PilkingtonState Representative
- Bryan KingState Senator
- Jeremiah MooreState Representative
- Jonathan DismangState Senator
- Joshua BryantState Senator
- Missy IrvinState Senator
- Rick McClureState Representative
- Ron McNairState Representative
Questions people ask
- How many data centers are in Arkansas?
- Data Center Fact Check tracks 7 data center projects in Arkansas as of November 2026. Of those, 3 under construction, 2 approved and 1 announced.
- What is the biggest data center in Arkansas?
- By announced capacity, the biggest data center in Arkansas is AVAIO Digital Leo data center and power campus, Pulaski County, announced at 1,070 MW. It is under construction.
- How much power do data centers in Arkansas use?
- The 7 projects tracked in Arkansas have announced about 1,652 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Act 819 of 2023 (HB 1654), sales and use tax exemptions for data centers, creating Ark. Code Section 26-52-455
Arkansas Bureau of Legislative ResearchTier 1 · Open the source - 2HB 1444 of 2025, engrossed text amending Ark. Code Section 26-52-456 (enacted as Act 548 of 2025)
Arkansas Bureau of Legislative ResearchTier 1 · Open the source - 3Resolution No. 16,672 authorizing a Memorandum of Understanding with Willowbend Capital LLC, with the MOU as Exhibit A; City of Little Rock Board of Directors packet, April 29, 2025
City of Little RockTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Arkansas." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ar
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page