Serverfarm data center campus, Clarksville (ARK)

Clarksville,Johnson County,ArkansasUnder constructionFirst public 2025Filing entity: SF ARK1 LLCLast checked Nov 8, 2026

ServerfarmDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Serverfarm data center campus, Clarksville (ARK) is a under-construction data center project in Clarksville, Johnson County, Arkansas. Serverfarm is named as operator. It was first public in 2025. It was announced at 432 MW.

Serverfarm data center campus, Clarksville (ARK) is an under-construction data center project in Clarksville, Johnson County, Arkansas. Serverfarm is named as operator. It was announced at 432 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Clarksville, Johnson County, Arkansas. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

432 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Johnson County, Arkansas.See every project on the map

The land, to scale

One football field
135 acres, about 102 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Serverfarm data center campus, Clarksville (ARK)Under construction

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas HB 1444: Cuts the data center tax exemption investment threshold to $100 million

    The act covers qualified data centers that create a qualified investment of at least $100 million at the facility no later than five years after certification, pay at least $1 million in aggregate annualized compensation, are not primarily engaged in virtual currency transactions, and hold a positive cost-benefit analysis from the Arkansas Economic Development Commission; this project has 430 MW on record (not stated), but the project's capital investment, annualized compensation, and commission cost-benefit analysis is not on record.

    “Creates a qualified investment of at least one hundred million dollars ($100,000,000) at the facility no later than five (5) years” (Engrossed text, Section 1 (new-law reading; the engrossment strikes $500,000,000 and inserts $100,000,000))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas HB 1654: Creates the data center sales and use tax exemption

    The act covers qualified data centers that create a qualified investment of at least $500 million within five years of the issuance of a certificate of occupancy, pay at least $1 million in aggregate annualized compensation, are not primarily engaged in virtual currency transactions, and hold a positive cost-benefit analysis from the Arkansas Economic Development Commission; this project has 430 MW on record (not stated), but the project's capital investment, annualized compensation, and commission cost-benefit analysis is not on record. Status part: the bill's status (Notification that HB1654 is now Act 819) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Creates a qualified investment of at least five hundred million dollars ($500,000,000) within five (5) years of the issuance of a certificate of occupancy by the relevant local building authority” (Act 819 of 2023, Section 1, § 26-52-455(a)(4)(B)(i))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas HB 1799: Creates the Arkansas Data Centers Act of 2023

    The act covers digital asset mining businesses and their customers, whose rates the Public Service Commission may not set in an unreasonably discriminatory way and whose local requirements the act limits; this project has 430 MW on record (not stated), but whether this project is a digital asset mining business is not on record. Status part: the bill's status (Notification that HB1799 is now Act 851) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “the Arkansas Public Service Commission shall not establish an unreasonably discriminatory rate for a digital asset mining business customer” (Act 851 of 2023, Section 1, § 14-1-505(c))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas SB 78: Sets mining noise rules and bars prohibited foreign parties from owning Arkansas mining businesses

    The act covers digital asset mining businesses, which must apply noise-reduction techniques such as liquid cooling or a fully enclosing envelope; this project has 430 MW on record (not stated), but whether this project is a digital asset mining business is not on record. Status part: the bill's status (Notification that SB78 is now Act 173) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Apply noise-reduction techniques, including without limitation: (A) Using liquid cooling or submerged cooling” (Act 173 of 2024, § 14-1-604(b)(3)(A))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas SB 79: Creates Oil and Gas Commission permitting for digital asset mining businesses

    The act covers digital asset mining businesses, which may not operate in Arkansas without a valid permit from the Oil and Gas Commission; this project has 430 MW on record (not stated), but whether this project is a digital asset mining business and whether it holds such a permit is not on record. Status part: the bill's status (Notification that SB79 is now Act 174) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “A digital asset mining business shall not operate in Arkansas without a valid permit from the Oil and Gas Commission under this chapter” (Act 174 of 2024, § 23-119-103(a))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

Bills and laws in Arkansas

All 10 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 430 MW · First four buildingsOct 2026 · what the figure measures is not stated

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Serverfarm data center campus, Clarksville (ARK)?
    Serverfarm data center campus, Clarksville (ARK) is a data center project in Clarksville, Johnson County, Arkansas.
    Who operates Serverfarm data center campus, Clarksville (ARK)?
    Serverfarm is named as the operator of Serverfarm data center campus, Clarksville (ARK).
    How big is Serverfarm data center campus, Clarksville (ARK)?
    Serverfarm data center campus, Clarksville (ARK) was announced at 432 MW of capacity. The site covers 135 acres.
    What stage is Serverfarm data center campus, Clarksville (ARK)?
    Serverfarm data center campus, Clarksville (ARK) is under construction. It was first public in 2025.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      A $6.6B Clarksville Data Center Will Generate Its Own Power. Will It Win Over Skeptics?
      Arkansas Business
      Tier 3 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page