IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, LLC’S GENERATING ARKANSAS JOBS ACT ANNUAL UPDATES

Where it stands: Pending before the commission

Draft research, not yet verified. Open a source to check any detail.

What it is

First annual update cycle under Rate Schedule No. 73. The Attorney General brief in response to Order No. 4 (Doc. 59, filed April 13, 2026) argues that a deficient or non-compliant annual update filing does not trigger the statutory 90-day order deadline under Ark. Code § 23-4-1304(e)(2). Staff testimony in this docket (Doc. 62, April 14, 2026, as cited in the staged Docket 25-054-U row) records the Cypress Solar strategic investment finding and the 100 percent rider allocation that this annual update administers.

The facts

Regulator
Arkansas Public Service Commission
Docket number
26-008-TF
Type
Other
Utility
Entergy Arkansas LLC
State
Arkansas
Large-load rules
Yes

Projects served by Entergy Arkansas LLC

Related cases and proceedings

Sources

  1. 1
    Attorney General brief in response to Order No. 4 (Doc. 59), Docket No. 26-008-TF, Generating Arkansas Jobs Act annual updates
    Arkansas Public Service Commission
    Tier 1 · Doc. 59 (Attorney General brief), filed April 13, 2026, caption and Part I · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, LLC’S GENERATING ARKANSAS JOBS ACT ANNUAL UPDATES." Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-entergy-arkansas-gaja-annual-update-2026