Skip to content

Utility commission

IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, LLC FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED FOR CONSTRUCTION AND RELATED FINDINGS AND APPROVALS OF A SOLAR GENERATING AND BATTERY ENERGY STORAGE SYSTEM FACILITY, AND OTHER FACILITIES IN JEFFERSON COUNTY, ARKANSAS

Where it stands: Decided as of Mar 3, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Certificate for Arkansas Cypress Solar, a 600 MW solar array with a 350 MW battery storage system interconnecting at the White Bluff substation, the resource built to support the Google special rate contract in Docket 25-055-P. Order No. 4 (March 3, 2026) granted the certificate and found Cypress Solar a strategic investment under the Generating Arkansas Jobs Act of 2025, authorizing Entergy Arkansas to allocate 100 percent of the costs of acquiring and operating it to retail customers through the Generating Arkansas Jobs Act Rider (Rate Schedule No. 73), subject to an independent monitor proposal. The company gave notice that construction began on or around July 10, 2026.

The facts

Regulator
Arkansas Public Service Commission
Docket number
25-054-U
Type
Other
Utility
Entergy Arkansas LLC
State
Arkansas
Filed
Sep 5, 2025
Status date
Mar 3, 2026
Large-load rules
Yes

Projects served by Entergy Arkansas LLC

Related cases and proceedings

In the record

  1. Utility case, Sep 5, 2025. Utility case filed: IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, LLC FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED FOR CONSTRUCTION AND RELATED FINDINGS AND APPROVALS OF A SOLAR GENERATING AND BATTERY ENERGY STORAGE SYSTEM FACILITY, AND OTHER FACILITIES IN JEFFERSON CO... Arkansas Public Service Commission, 25-054-U

Sources

  1. 1
    Entergy Arkansas notice of construction commencement in Docket No. 25-054-U (Arkansas Cypress Solar CECPN)
    Arkansas Public Service Commission
    Tier 1 · Doc. 110 (company notice, filed July 27, 2026), p. 1 (Order No. 4 of March 3, 2026 granted the CECPN; construction began on or around July 10, 2026); strategic investment and 100 percent allocation findings per Staff Responsive Testimony in Docket No. 26-008-TF (Doc. 62, April 14, 2026), p. 61 · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, LLC FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED FOR CONSTRUCTION AND RELATED FINDINGS AND APPROVALS OF A SOLAR GENERATING AND BATTERY ENERGY STORAGE SYSTEM FACILITY, AND OTHER FACILITIES IN JEFFERSON COUNTY, ARKANSAS." Last activity 2026-03-03. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-entergy-arkansas-cypress-solar-2025