Little Rock,Pulaski County,ArkansasApprovedFirst public 2025Filing entity: Willowbend Capital LLCLast checked Nov 13, 2026

Willowbend CapitalDeveloperEntergy ArkansasElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: Capacity
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Willowbend Capital data center, Little Rock Port is an approved data center project in Little Rock, Pulaski County, Arkansas. Willowbend Capital is named as developer. It was first public in 2025. No site capacity figure is published for this project.

Willowbend Capital data center, Little Rock Port is an approved data center project in Little Rock, Pulaski County, Arkansas. Willowbend Capital is named as developer. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Little Rock, Pulaski County, Arkansas. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

8Public records we have found
1Tax agreement on record

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Aerial view of Willowbend Capital data center, Little Rock Port in Little Rock, Pulaski County, Arkansas, captured 2023
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2023Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Pulaski County, Arkansas.See every project on the map

Timeline

  1. · DecisionCity of Little Rock: Adopted: the Board of Directors authorized the Mayor to execute a Memorandum of Understanding with Willowbend Capital LLC for a data center development project at the Little Rock Port for Willowbend Capital data center, Little Rock PortResolution No. 16,672; Memorandum of Understanding (Exhibit A)
  2. · FilingFiled with City of Little Rock for Willowbend Capital data center, Little Rock PortResolution No. 16,672; Memorandum of Understanding (Exhibit A)
  3. · New projectFirst public record of Willowbend Capital data center, Little Rock PortApproved
  4. · Tax dealTax agreement approved: Payment in lieu of taxes under memorandum of understanding (city of little rock) for Willowbend Capital LLCCity support for a net real and personal property tax abatement of at least 65 percent for 30 years for the data center and each additional data center facility, delivered through bond structures (buildout periods of at least 30 years; i...

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas HB 1444: Cuts the data center tax exemption investment threshold to $100 million

    The act covers qualified data centers that create a qualified investment of at least $100 million at the facility no later than five years after certification, pay at least $1 million in aggregate annualized compensation, are not primarily engaged in virtual currency transactions, and hold a positive cost-benefit analysis from the Arkansas Economic Development Commission; this project has no capacity figure on record, but the project's capital investment, annualized compensation, and commission cost-benefit analysis is not on record. Status part: the bill's status (Notification that HB1444 is now Act 548) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Creates a qualified investment of at least one hundred million dollars ($100,000,000) at the facility no later than five (5) years” (Engrossed text, Section 1 (new-law reading; the engrossment strikes $500,000,000 and inserts $100,000,000))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas HB 1654: Creates the data center sales and use tax exemption

    The act covers qualified data centers that create a qualified investment of at least $500 million within five years of the issuance of a certificate of occupancy, pay at least $1 million in aggregate annualized compensation, are not primarily engaged in virtual currency transactions, and hold a positive cost-benefit analysis from the Arkansas Economic Development Commission; this project has no capacity figure on record, but the project's capital investment, annualized compensation, and commission cost-benefit analysis is not on record. Status part: the bill's status (Notification that HB1654 is now Act 819) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Creates a qualified investment of at least five hundred million dollars ($500,000,000) within five (5) years of the issuance of a certificate of occupancy by the relevant local building authority” (Act 819 of 2023, Section 1, § 26-52-455(a)(4)(B)(i))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas HB 1799: Creates the Arkansas Data Centers Act of 2023

    The act covers digital asset mining businesses and their customers, whose rates the Public Service Commission may not set in an unreasonably discriminatory way and whose local requirements the act limits; this project has no capacity figure on record, but whether this project is a digital asset mining business is not on record. Status part: the bill's status (Notification that HB1799 is now Act 851) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “the Arkansas Public Service Commission shall not establish an unreasonably discriminatory rate for a digital asset mining business customer” (Act 851 of 2023, Section 1, § 14-1-505(c))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas SB 78: Sets mining noise rules and bars prohibited foreign parties from owning Arkansas mining businesses

    The act covers digital asset mining businesses, which must apply noise-reduction techniques such as liquid cooling or a fully enclosing envelope; this project has no capacity figure on record, but whether this project is a digital asset mining business is not on record. Status part: the bill's status (Notification that SB78 is now Act 173) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Apply noise-reduction techniques, including without limitation: (A) Using liquid cooling or submerged cooling” (Act 173 of 2024, § 14-1-604(b)(3)(A))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arkansas SB 79: Creates Oil and Gas Commission permitting for digital asset mining businesses

    The act covers digital asset mining businesses, which may not operate in Arkansas without a valid permit from the Oil and Gas Commission; this project has no capacity figure on record, but whether this project is a digital asset mining business and whether it holds such a permit is not on record. Status part: the bill's status (Notification that SB79 is now Act 174) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “A digital asset mining business shall not operate in Arkansas without a valid permit from the Oil and Gas Commission under this chapter” (Act 174 of 2024, § 23-119-103(a))

    Rule checks: Project is in Arkansas. Still to check: who it covers: not checked

Bills and laws in Arkansas

All 10 in Bill Watch

Who's involved

Public records

8 records found so far. 5 kinds of record are still being collected.

See every record

Questions people ask

Where is Willowbend Capital data center, Little Rock Port?
Willowbend Capital data center, Little Rock Port is a data center project in Little Rock, Pulaski County, Arkansas.
Who is developing Willowbend Capital data center, Little Rock Port?
Willowbend Capital is named as the developer of Willowbend Capital data center, Little Rock Port.
What stage is Willowbend Capital data center, Little Rock Port?
Willowbend Capital data center, Little Rock Port is approved. It was first public in 2025.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Resolution No. 16,672 authorizing a Memorandum of Understanding with Willowbend Capital LLC, with the MOU as Exhibit A; City of Little Rock Board of Directors packet, April 29, 2025
    City of Little Rock
    Tier 1 · Captured 2026-11-10 · Open the source
  2. 2
    Public Notice SWL 2026-00038 (Willowbend Capital, LLC), Little Rock District
    U.S. Army Corps of Engineers, Little Rock District
    Tier 1 · Captured 2026-11-13 · Open the source
  3. 3
    Order No. 9 in Docket No. 25-055-P (Entergy Arkansas special rate customer contract approval)
    Arkansas Public Service Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Entergy Arkansas notice of construction commencement in Docket No. 25-054-U (Arkansas Cypress Solar CECPN)
    Arkansas Public Service Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Order No. 6 (Doc. 87), Docket No. 26-003-U, denying the Big Island Solar power purchase agreement application
    Arkansas Public Service Commission
    Tier 1 · Captured 2026-11-10 · Open the source
  6. 6
    Attorney General brief in response to Order No. 4 (Doc. 59), Docket No. 26-008-TF, Generating Arkansas Jobs Act annual updates
    Arkansas Public Service Commission
    Tier 1 · Captured 2026-11-10 · Open the source
  7. 7
    Order No. 14 (Doc. 103), Docket No. 25-049-TF, approving Rate Schedule No. 73, the Generating Arkansas Jobs Act Rider
    Arkansas Public Service Commission
    Tier 1 · Captured 2026-11-10 · Open the source