Project File · Public records
Every public record we have for Willowbend Capital data center, Little Rock Port
Little Rock, Pulaski County, ArkansasApprovedFirst public 2025Filing entity: Willowbend Capital LLCLast checked Nov 13, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
1 of 8 records · showing tax breaks and payments only ·
2025
Tax agreementApr 29, 2025Little Rock
Payment in lieu of taxes under memorandum of understanding (City of Little Rock)
City support for a net real and personal property tax abatement of at least 65 percent for 30 years for the data center and each additional data center facility, delivered through bond structures (buildout periods of at least 30 years; investment caps of at least $10 billion real property and $50 billion personal property); electric franchise fee reduced to 0.25 percent; water franchise fee to 0 percent; sewer franchise fee to 0 percent; standard permit fees capped at $200,000 per data center. Company pays an annual City Enrichment Investment of $300,000, plus $200,000 for each additional data center, the first payment within 60 days after the initial facility certificate of occupancy. Project terms in the same MOU: approximately 300,000 square foot facility, approximately $1,000,000,000 anticipated investment, approximately 50 jobs.
Draft research, not yet verifiedLast checked Nov 10, 2026Where it says this
Exhibit A, Memorandum of Understanding, tax abatement and franchise fee provisions (adopted with Resolution No. 16,672, April 29, 2025)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Resolution No. 16,672 authorizing a Memorandum of Understanding with Willowbend Capital LLC, with the MOU as Exhibit A; City of Little Rock Board of Directors packet, April 29, 2025
City of Little RockTier 1 · Captured 2026-11-10 · Open the source - 2Public Notice SWL 2026-00038 (Willowbend Capital, LLC), Little Rock District
U.S. Army Corps of Engineers, Little Rock DistrictTier 1 · Captured 2026-11-13 · Open the source - 3Order No. 9 in Docket No. 25-055-P (Entergy Arkansas special rate customer contract approval)
Arkansas Public Service CommissionTier 1 · Captured 2026-11-08 · Open the source - 4Entergy Arkansas notice of construction commencement in Docket No. 25-054-U (Arkansas Cypress Solar CECPN)
Arkansas Public Service CommissionTier 1 · Captured 2026-11-08 · Open the source - 5Order No. 6 (Doc. 87), Docket No. 26-003-U, denying the Big Island Solar power purchase agreement application
Arkansas Public Service CommissionTier 1 · Captured 2026-11-10 · Open the source - 6Attorney General brief in response to Order No. 4 (Doc. 59), Docket No. 26-008-TF, Generating Arkansas Jobs Act annual updates
Arkansas Public Service CommissionTier 1 · Captured 2026-11-10 · Open the source - 7Order No. 14 (Doc. 103), Docket No. 25-049-TF, approving Rate Schedule No. 73, the Generating Arkansas Jobs Act Rider
Arkansas Public Service CommissionTier 1 · Captured 2026-11-10 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page